HomeMy WebLinkAbout12 - CdM State Beach Landscape ImprovementsCITY OF NEWPORT BEACH CITY COUNCIL STAFF REPORT Agenda Item No. 12 April 13, 2010 TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL FROM: Public Works Department Frank Tran, Associate Civil Engineer 949 - 644 -3345 or ftran @newportbeachca.gov SUBJECT: CDM STATE BEACH LANDSCAPE IMPROVEMENTS — COMPLETION AND ACCEPTANCE OF CONTRACT NO. 4089 Recommendations: 1. Accept the completed work and authorize the City Clerk to file a Notice of Completion. 2. Authorize the City Clerk to release the Labor and Materials bond 35 days after the Notice of Completion has been recorded in accordance with applicable portions of the Civil Code. 3. Release the Faithful Performance Bond 1 year after Council acceptance. Construction Contract Summary: Construction Contract Final Cost at Benchmark Actual Contract Time Over Award Amount Completion Target Time (days) or (Under) $113,330.00 $115,655.00 Contract Contract 45 (9) +10% +2.05% Discussion: On September 22, 2009, the City Council authorized the award of the CDM State Beach Landscape Improvements to Hondo Company, Inc. The contract consists of the removal of the existing improvements within the planter area along the north side of the Corona del Mar State Beach parking lot adjacent to Breakers Drive; constructing new, curb, three -foot high retaining wall, concrete steps with handrail, and gravel bed along Breakers Drive; and installing landscape material and irrigation system. The construction contract has now been completed to the satisfaction of the Public Works Department. A summary of the contract cost is as follows: Original bid amount: $113,330.00 Actual amount of bid items constructed: $107,966.00 Total amount of one change order: $7,689.00 Final contract cost: $115,655.00 CDM State Beach Landscape Improvements Contract No. 4089 - NOC April 13, 2010 Page 2 Three change orders in the total amount of $7,689.00 were approved for the asphalt replacement adjacent to the concrete steps, constructing additional catch basins for drainage improvements, change planting materials and additional maintenance period and fencing. A summary of the project schedule is as follows: Estimated Completion Date per July 2009 Master Schedule: December 04, 2009 Project Awarded for Construction: September 22, 2009 Date of Notice To Proceed: November 9, 2009 Estimated completion date on Notice To Proceed: January 5, 2010 Actual substantial construction completion date: December 22, 2010 Environmental Review: The project was determined to be exempt from the California Environmental Quality Act (CEQA) pursuant to Section 15301 of the CEQA Implementation Guidelines. This exemption covers the repair, maintenance and minor alterations of existing public facilities with negligible expansion. Funding Availability: In addition to the primary construction contract, this project involved other project expenses. Total project expenses are summarized as follows: Construction Design — David Pedersen, Incidentals Total Project Cost Landscape Architect $115,655.00 $5,765.00 $1,497.87 $122,917.87 Funds for the construction contract were expended from the following account: Account Description General Fund Prepared by: Frank Tran Associate Civil Engineer Account Number Amount 7013- C2002027 $115,655.00 Total: $115,655.00 Submitted by: ' i ILA J • � - Agenda Item No. 12 April 13, 2010 CDM State Beach (Breakers Dr.) Landscape Improvements Project Map Exhibit S1, F� �S l r ?tea O CS. OQ P HBFACH RAMP O CF 4ye <� O SF 9p� Fes. qLF PJt�, �QJQ ..rq�AKFRS OR i� Project Location: between Breakers Drive and CDM State Beach Parking Lot View from the CDM Parking Lot i L: AL s. it View from Breakers Drive