Loading...
HomeMy WebLinkAbout09 - McFadden Square Phase 2CITY OF NEWPORT BEACH CITY COUNCIL STAFF REPORT Agenda Item No. 9 April 27, 2010 TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL FROM: Public Works Department Fong Tse, Principal Civil Engineer 949 - 644 -3321 orftse @newportbeachca.gov SUBJECT: MCFADDEN SQUARE PHASE 2 — COMPLETION AND ACCEPTANCE OF CONTRACT NO. 4365 Recommendations: 1. Accept the completed work and authorize the City Clerk to file a Notice of Completion. 2. Authorize the City Clerk to release the Labor and Materials bond 35 days after the Notice of Completion has been recorded in accordance with applicable portions of the Civil Code. 3. Release the Faithful Performance Bond 1 year after Council acceptance. Construction Contract Summary: Construction Final Cost at Benchmark Contract Time Over Contract Award Completion Target Actual Time or (Under) Amount days $32,150.00 $33,002.36 Contract Contract 25 (20) +10% +2.65% Discussion: On October 27, 2009, the City Council authorized the award of the McFadden Square Phase -II improvements to EBS Concrete, Inc. The contract consisted of removing and disposing of the existing dark cobble stones and installing a second ring of granite tiles adjacent to those installed under Phase -1. A total of fifty -six (56) blank donor tiles, fifty - five (55) engraved "marine" tiles and a band of new custom -cut half -sized cobble stones were installed. McFadden Square Phase -II Contract No. 4365 - NOC April 27, 2010 Page 2 The construction contract has now been completed to the satisfaction of the Public Works Department. A summary of the contract cost is as follows: Original bid amount: $32,150.00 Actual amount of bid items constructed: $32,300.00 Total amount of one change order: $ 702.36 Final contract cost: $33,002.36 One change order was approved in the amount of $702.36 to purchase two custom -cut donor tiles to replace two engraved (Phase -I) tiles that contained typographical errors. These replacement tiles will be installed by others prior to the Memorial Day weekend. A summary of the project schedule is as follows: Estimated Completion Date per July 2009 Master October 15, 2010 Schedule: Project Awarded for Construction: October 27, 2009 Estimated completion per contract: March 19, 2010 Actual substantial construction completion date: March 19, 2010 To maintain consistency, the engraving of donor names on the new tiles will be performed under separate purchase order(s) by the company that engraved the Phase -I tiles. Environmental Review: The project was determined to be exempt from the California Environmental Quality Act (CEQA) pursuant to Section 15301 of the CEQA Implementation Guidelines. This exemption covers the repair, maintenance and minor alterations of existing public facilities with negligible expansion. Funding Availability: In addition to the construction contract with EBS, this project involved other project expenses. Total project expenses are summarized as follows: Construction $ 33,002.36 Conceptual Design — Peridian International, Inc. $ 7,510.78 Incidentals $ 338.73 Total Project Cost $ 40,751.09 McFadden Square Phase -II Contract No. 4365 - NOC April 27, 2010 Page 3 Funds for the construction contract were expended from the following account: Account Description Account Number Amount General Fund 7015- C4002005 $ 33,002.36 Total: $ 33,002.36 Prepared by: Submitted bv: Fob /e Pri al Civil Engineer Attachment: Location Map V,,'A // z co o MCFADDEN SQUARE PHASE 11 CENTENIAL MONUMENT ADDITIONAL DONOR TILE BAND PROJECT 0P WRO Nal LOCATION MAP NOT TO SCALE