Loading...
HomeMy WebLinkAbout15 - Rhine Channel Contaminated Sediment Cleanup ProjectCITY OF NEWPORT BEACH CITY COUNCIL STAFF REPORT Agenda Item No. 15 June 22, 2010 TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL FROM: City Manager's Office Chris Miller, Harbor Resources Manager (949) 644 -3043, cmiller @newportbeachca.gov SUBJECT: Second Amendment to Professional Services Agreement with Anchor QEA, L.P. for Final Engineering Evaluation, Design and Permitting Support for the Rhine Channel Contaminated Sediment Cleanup Project ISSUE: Should the City amend the contract with Anchor QEA, L.P. to include preparation of the final engineering evaluation, design and permitting support for the Rhine Channel contaminated sediment cleanup project? RECOMMENDATIONS: Approve the Second Amendment to the Professional Services Agreement ( "PSA ") with Anchor QEA, L.P. to prepare the final engineering evaluation, design and permitting support for the Rhine Channel project, and Approve Budget Amendment #BA for the attached scope of work for $307,460 and for permit fees and air quality mitigation credits for $71,035 from Unappropriated Reserves (Tidelands) to Capital Improvement Project #7231 - C4402001 (Newport Harbor Dredging Project). DISCUSSION: Anchor QEA, L.P. is currently assisting the City with initial planning, alternative analysis, and environmental impacts evaluation related to the Rhine Channel cleanup and Lower Newport Bay (LNB) dredging. Sediments within the Rhine Channel, as well as portions of the U.S. Army Corps of Engineers managed Federal Channel, are suspected of being unsuitable for open -ocean disposal and, therefore, require an alternative disposal site. It is anticipated that these sediments will be accepted for disposal at the Port of Long Beach's (POLB) Middle Harbor confined disposal facility slip fill site. As part of the next step for this project, Anchor QEA has submitted a new scope of work that details tasks needed to be undertaken to complete the necessary engineering Anchor PSA for Final Design and Permitting June 22, 2010 Page 2 evaluations, dredge design, permit applications, and construction bid documents for the City's portion of cleanup dredging with the Rhine Channel and maintenance dredging of selected City- managed properties along the adjoining Newport Channel (i.e. Marina Park, American Legion, and 15th Street public pier). Scope of Services Under the proposed PSA Amendment, Anchor QEA would continue to be retained on a time and materials basis ( for a not -to- exceed amount) to complete the engineering and permitting tasks summarized below and detailed in the scope of services included as Exhibit 2 to the PSA Amendment ?. Task 1: Structural Review and Updated Bathvmetry Survey Under a subcontract with URS Corporation (a structural engineering firm) Anchor QEA will perform surveys and measurements at the project site to establish existing conditions to a degree of detail needed for design and analysis efforts. Subtask 1.1: Updated Bathvmetric Base Map of Complete Proiect Area This subtask will involve creating an updated, complete bathymetric survey map for the entire Rhine Channel and selected properties along the Newport Channel (i.e. Marina Park, American Legion, and the 15th Street public pier). An updated bathymetric survey will be critical for: • Identifying shallow areas within the channel that may need to be dredged. • Indicating water depths available for dredging equipment. • Indicating mudline elevations for determining dredging volumes. Estimated costs are $30,656. Subtask 1.2: Investigation of Seawalls and Panels This subtask will involve supplementing and "reality checking" the understanding of the existing marine structures within the Rhine Channel and adjoining properties through a structural review to be conducted by URS. This evaluation will include a vessel -based "swim -by" reconnaissance during which exposed seawalls, floats, and guide piles will be visually inspected. Seawall embedment depths at representative locations will also be measured using a jet probe. Estimated costs are $12,783. Subtask 1.3: Investigation of Guide Piles This subtask will involve direct testing and evaluation of the piles in the field via impact - echo testing, a non - destructive pile testing method that can be conducted by personnel using specialized hand -held instruments which allow for estimation of their actual in- place embedded lengths below the mudline. This field testing will allow Anchor to fine Anchor PSA for Final Design and Permitting June 22, 2010 Page 3 tune and reality check the actual pile conditions and potentially reduce the number of piles that need to be extracted during dredging. Estimated costs are $10,000. Task 2: Permitting Anchor QEA will prepare and submit required resource agency permit applications. Anchor QEA will also assist the City with the Port of Long Beach disposal applications for the Rhine Channel, Marina Park, American Legion, 15th St. beach and the Federal Lower Newport Bay material. Estimated costs are $65,360. Subtask 2.1: California Coastal Commission — Securing a Coastal Development Permit Subtask 2.2: Regional Water Quality Control Board — Securing Water Quality CertificationNVaste Discharge Requirements Subtask 2.3: State Lands Commission — Securing a Dredging Lease Subtask 2.4: US Army Corps of Engineers — Securing a Standard Individual Permit Note: Permit fees and air quality credits are not included in this Agreement, and will be the City's responsibility. Fees are anticipated to be as follows: • Coastal Commission - $12,500 • Regional Water Quality Control Board - $25,000 • State Lands Commission - $1,525 • Army Corps of Engineers - $10 • AQMD air quality mitigation credits - $32,000 (based on current market rate assumptions and other worst case scenarios — final cost may be lower) Task 3: Final Engineering Design and Documentation Anchor QEA will complete final engineering analysis and design of the dredging project as well as preparation of construction documents (plans and technical specifications) that can be used for soliciting bids. A key aspect of the final engineering evaluation is to evaluate the effects of dredging on seawalls and guide piles at the site so that the dredge prism can be designed and optimized. Because dredging removes sediment that helps to retain the toe of the seawalls, an offset distance will need to be included in the dredge design so the walls are not destabilized as a result of the work. Subtask 3.1: Geotechnical Engineering Exploration and Analysis The analysis of seawall stability and how it would be affected by dredging requires a thorough understanding not only of the characteristics of the seawalls themselves but also of the geotechnical properties of the soils in which the seawalls are situated and Anchor PSA for Final Design and Permitting June 22, 2010 Page 4 which they retain. Anchor proposes to conduct the following series of geotechnical explorations at locations where no information is available: • Five in -water geotechnical borings to depths of 20 feet, using a small, maneuverable mud rotary drilling barge. • Two landside borings to depths of 40 feet, using a truck - mounted mud rotary drilling rig. • Seven cone penetrometer tests (CPTs) to depths of 50 feet, on landside locations, using a truck - mounted CPT rig. Estimated costs are $57,145. Subtask 3.2: Analvsis of Structural Stabilit Once geotechnical data has been gathered, Anchor and URS will use geotechnical and structural engineering analysis techniques to determine how dredging affects pressures experienced by the seawalls and the potential response and deflection of surrounding ground and seawall elements. These approaches will be used to estimate the current stability level of the seawalls and to define the relationship between dredging prism geometry and the seawall stability, which will allow the design team to develop a protective dredging plan while also meeting the City's Rhine Channel cleanup goals. Analysis will include an assessment of gravity and seismic loads, including possible liquefaction effects. Estimated costs are $47,720. Subtask 3.3: Plans, Specifications and Opinion of Probable Cost Anchor and URS will prepare Draft (65 percent), Draft Final (95 percent) and Final (100 percent level) design plans, technical specifications, and opinion of probable cost for the construction work. Estimated costs are $83,796. Ootional Tasks Anchor has identified some optional tasks that could be needed if a further level of detail is required. However, both staff and Anchor believe these optional tasks are not necessary at this time, and that it is best to proceed with the scope of work as described above. The anticipated costs for these optional tasks, should they be necessary, is $62,000 and would therefore require an additional Amendment to the Agreement. Schedule: Anchor QEA is proposing to immediately begin this work in order to meet the anticipated deadline for the Port of Long Beach disposal opportunity. Our current schedule shows the City being shovel -ready by mid January 2011 assuming the POLB, the driving factor, is ready to begin construction. Anchor PSA for Final Design and Permitting June 22, 2010 Page 5 ENVIRONMENTAL REVIEW: The approval of the Professional Services Agreement for final engineering evaluation, design and permitting support does not require environmental review. PUBLIC NOTICE: This agenda item has been noticed according to the Ralph M. Brown Act (72 hours in advance of the public meeting at which the City Council considers the item). FUNDING AVAILABILITY: The scope of work requires a Budget Amendment of $307,460 for the attached Scope of Work and $71,035 for permit fees and air quality mitigation credits from Unappropriated Reserves (Tidelands) to account CIP #7231- C4402001 (Newport Harbor Dredging Project). Submitted by: ris Miller Harbor Resources Manager Attachments: 1. Anchor Professional Services Agreement 2. Anchor QEA Scope of Work SECOND AMENDMENT TO PROFESSIONAL SERVICES AGREEMENT WITH ANCHOR QEA, L.P. FOR ADDITIONAL PROFESSIONAL SERVICES FOR THE RHINE CHANNEL CONTAMINATED SEDIMENT CLEANUP PROJECT THIS SECOND AMENDMENT TO PROFESSIONAL SERVICES AGREEMENT ( "Second Amendment "), is entered into as of this day of 12010, by and between the City of Newport Beach,-a California Municipal Corporation and Charter City ( "City'), and Anchor QEA, L.P., a California Limited Partnership whose address is 28202 Cabot Road, Suite 425 Laguna Niguel, California, 92677 ( "Consultant "), and is made with reference to the following: RECITALS A. On July 14, 2009 City and Consultant entered into a Professional Services Agreement ( "Agreement "), to initiate environmental analysis ( "CEQA ") and engineering processes for the disposal of contaminated materials from a Lower Newport Bay dredging project into a Confined Aquatic Disposal ( "CAD ") site within Newport Harbor. B. On November 10, 2009 City and Consultant entered into a First Amendment to Professional Services Agreement to allow for the preparation of a Mitigated Negative Declaration ( "MND ") to analyze the potential disposal of contaminated material from non - federal areas (Rhine Channel and RGP -54 exclusion zones) in an upcoming Port of Long Beach CAD ( "First Amendment "). C. City and Consultant desire to enter into this Second Amendment to modify the scope of work to include engineering evaluations, dredge design, permit applications, and construction bid documents for the City's portion of the cleanup dredging within the Rhine Channel and maintenance dredging of selected City - managed properties along the Newport Channel ('Project "). D. City and Consultant also desire to extend the Agreement's term to August 30, 2012. E. Agreement Section 34 authorizes the City and Consultant to enter into this Second Amendment. NOW, THEREFORE, it is mutually agreed by and between the City and Consultant that adequate consideration has been provided and that the Agreement shall be amended as follows: 1. TERM Agreement Section 1 "Term" shall be amended to read as follows: "The term of this Agreement shall commence on the above written date, and shall terminate on the 30t" day of August, 2012, unless terminated earlier as set forth herein." First Amendment Section 1 "Term" shall be deleted in its entirety. 2. SERVICES TO BE PERFORMED The Scope of Services attached to the Agreement as Exhibit "A" as superseded by Exhibit "A" to the First Amendment incorporated by reference in Section 2 of the First Amendment shall be supplemented to include the Scope of Services dated June 11, 2010, which is attached to this Second Amendment as Exhibit "A" and incorporated herein by reference. The City may elect to delete certain tasks from the Scope of Services at its sole discretion. 3. COMPENSATION TO CONSULTANT The not to exceed total compensation dollar amount provided in Agreement Section 4 shall be increased to a not to exceed amount of Seven Hundred Fifty - Two Thousand Four Hundred Sixty and 00/100 Dollars ($752,460.00). 4. INSURANCE Agreement Section 14 shall be amended hereby and the following terms are substituted in their entirety: Without limiting Consultant's indemnification of City, and prior to commencement of work, Consultant shall obtain, provide and maintain at its own expense during the term of this Agreement, policies of insurance of the type and amounts described below and in a form satisfactory to City. A. Proof of Insurance. Consultant shall provide certificates of insurance to City as evidence of the insurance coverage required herein, along with a waiver of subrogation endorsement for workers' compensation. Insurance certificates and endorsement must be approved by City's Risk Manager prior to commencement of performance. Current certification of insurance shall be kept on file with City at all times during the term of this contract. City reserves the right to require complete, certified copies of all required insurance policies, at any time. Consultant shall procure and maintain for the duration of the Agreement insurance against claims for injuries to persons or damages to property, which may arise from or in connection with the performance of the work hereunder by Consultant, his agents, representatives, employees or subconsultants. The cost of such insurance shall be included in Consultant's bid. 21Page B. Acceptable Insurers. All insurance policies shall be issued by an insurance company currently authorized by the Insurance Commissioner to transact business of insurance in the State of California, with an assigned policyholders' Rating of A- (or higher) and Financial Size Category Class VII (or larger) in accordance with the latest edition of Best's Key Rating Guide, unless otherwise approved by the City's Risk Manager. C. Coverage Requirements Workers' Compensation Coverage. Consultant shall maintain Workers' Compensation Insurance (Statutory Limits) and Employer's Liability Insurance (with limits of at least one million dollars ($1,000,000)) for Consultant's employees in accordance with the laws of the State of California, Section 3700 of the Labor Code In addition, Consultant shall require each subconsultant to similarly maintain Workers' Compensation Insurance and Employer's Liability Insurance in accordance with the laws of the State of California, Section 3700 for all of the subconsultant's employees. Any notice of cancellation or non - renewal of all Workers' Compensation policies must be received by City at least thirty (30) calendar days (ten (10) calendar days written notice of non- payment of premium) prior to such change. Consultant shall submit to City, along with the certificate of insurance, a Waiver of Subrogation endorsement in favor of City, its officers, agents, employees and volunteers. ii. General Liability Coverage. Consultant shall maintain commercial general liability insurance in an amount not less than one million dollars ($1,000,000) per occurrence for bodily injury, personal injury, and property damage, including without limitation, blanket contractual liability. iii. Automobile Liability Coverage. Consultant shall maintain automobile insurance covering bodily injury and property damage for all activities of the Consultant arising out of or in connection with Work to be performed under this Agreement, including coverage for any owned, hired, non -owned or rented vehicles, in an amount not less than $1,000,000 combined single limit for each accident. iv. Professional Liability (Errors & Omissions) Coverage. Consultant shall maintain professional liability insurance that covers the services to be performed in connection with this Agreement, in the minimum amount of one million dollars ($1,000,000) limit per claim and in the aggregate. 31 Page D. Other Insurance Provisions or Requirements. The policies are to contain, or be endorsed to contain, the following provisions: Waiver of Subrogation. All insurance coverage maintained or procured pursuant to this Agreement shall be endorsed to waive subrogation against City, its elected or appointed officers, agents, officials, employees and volunteers or shall specifically allow Consultant or others providing insurance evidence in compliance with these requirements to waive their right of- recovery prior to a loss. Consultant hereby waives its own right of recovery against City, and shall require similar written express waivers and insurance clauses from each of its subconsultants. ii. Enforcement of Contract Provisions. Consultant acknowledges and agrees that any actual or alleged failure on the part of the City to inform Consultant of non - compliance with any requirement imposes no additional obligations on the City nor does it waive any rights hereunder. iii. Requirements not Limiting. Requirements of specific coverage features or limits contained in this Section are not intended as a limitation on coverage, limits or other requirements, or a waiver of any coverage normally provided by any insurance. Specific reference to a given coverage feature is for purposes of clarification only as it pertains to a given issue and is not intended by any party or insured to be all inclusive, or to the exclusion of other coverage, or a waiver of any type. iv. Notice of Cancellation. Consultant agrees to oblige its insurance agent or broker and insurers to provide to City with thirty (30) days notice of cancellation (except for nonpayment for which ten (10) days notice is required) or nonrenewal of coverage for each required coverage. E. Timely Notice of Claims. Consultant shall give City prompt and timely notice of claims made or suits instituted that arise out of or result from Consultant's performance under this Agreement. F. Additional Insurance. Consultant shall also procure and maintain, at its own cost and expense, any additional kinds of insurance, which in its own judgment may be necessary for its proper protection and prosecution of the work. 5. INTEGRATED CONTRACT Except as expressly modified herein, all other provisions, terms, and covenants set forth in the Agreement and First Amendment shall remain unchanged and shall be in full force and effect. 4 i Page IN WITNESS WHEREOF, the parties hereto have executed this Second Amendment on the date first above written. APPROVED AS TO FORM: OFFICE OF THE CITY ATTORNEY ,VV 1� eonie Mulvihill, Assistant City Attorney ATTEST: By: Leilani Brown, City Clerk CITY OF NEWPORT BEACH, A California Municipal Corporation By: Keith Curry, Mayor for the City of Newport Beach CONSULTANT: A California Limited Partnership Title: General Partner Print Name: [END OF SIGNATURES] Attachment: Exhibit "A" —June 11, 2010 Scope of Services 51 Page ANCHOR OEA 26300 La Alameda, Suite 240 Mission Viejo, California 92691 Phone 949.347.2780 Fax 949.334.9646 June 11, 2010 Mr. Chris Miller City of Newport Beach, Harbor Resources Division 829 Harbor Island Drive Newport Beach, California 92660 Re: Scope of Work for Final Engineering Evaluation, Design, and Permitting Support for Rhine Channel Contaminated Sediment Cleanup Dear Mr. Miller: Anchor QEA, L.P., is currently assisting the City of Newport Beach (City) with initial planning, alternatives analysis, and environmental impacts evaluation related to Rhine Channel cleanup and Lower Newport Bay (LNB) dredging. Sediments within the Rhine Channel, as well as portions of the U.S. Army Corps of Engineers- (USACE -) managed Federal Channel, are suspected of being unsuitable for open -ocean disposal and, therefore, require an alternative disposal site. It is anticipated that these sediments will be accepted for disposal at the Port of Long Beach's Middle Harbor confined disposal facility (CDF) slip fill site. This scope of work details tasks needed to be undertaken to complete the necessary engineering evaluations, dredge design, permit applications, and construction bid documents for the City's portion of cleanup dredging within the Rhine Channel and maintenance dredging of selected City- managed properties along the adjoining Newport Channel (i.e., Marina Park, American Legion, and 15th Street Pier). Some necessary pre- design work has already been completed under our existing scope of work for pre- design activities associated with a potential confined aquatic disposal (CAD) site in Newport Bay but a few items still remain. Completed pre - engineering tasks include searching City archives for existing information on structures, seawalls, and utilities and reviewing available geotechnical www.anchorqea.com Mr. Chris Miller lune11,2010 Pate 2 information for the Rhine Channel area. The final engineering and permitting tasks required to complete the Rhine Channel contaminated sediment cleanup project are detailed below. RHINE CHANNEL FINAL ENGINEERING DESIGN TASKS AND ANALYSES Task 1: Structural Review and Updated Bathymetric Survey Under Task 1, Anchor QEA and URS Corporation (a structural engineering firm working as a sub - consultant to Anchor QEA) will perform surveys and measurements at the project site to establish existing conditions to a degree of detail needed for design and analysis efforts. Specific subtasks will include creating an updated base map, investigating seawalls and panels, and investigating guide piles. Task 1.1: Updated Bathymetric Base Map of Complete Project Area In preparation for design efforts, this subtask will involve creating an updated, complete bathymetric survey map of the entire Rhine Channel and selected properties along the Newport Channel (i.e., Marina Park, American Legion, and 15th Street Pier). An updated bathymetric survey will be critical for: • Identifying shallow areas within the channel that may need to be dredged • Indicating water depths available for dredging equipment • Indicating mudline elevations for determining dredging volumes The USACE recently (May 2010) completed a survey of open -water portions of the Rhine Channel, which supersedes that previous 2004 survey. Although Anchor QEA plans to use this 2010 survey to prepare a project -wide bathymetry map, it will be necessary to perform additional bathymetric surveys to cover the perimeter of the Rhine Channel and the selected Newport Channel properties. This supplementary survey effort will be performed by Gahagan and Bryant Associates (GBA), a well- established national survey firm with local personnel who performed 2004 survey. Remaining open -water areas will be surveyed by GBA using multi -beam equipment. Because much of the Rhine Channel and nearby properties are occupied by private vessels and docks, a majority of the supplementary survey will be completed by dropping lead lines by hand. Mr. Chris Miller June 11, 2010 Page 3 Task 1.2: Investigation of Seawalls and Panels To date, Anchor QEA has reviewed available City records and as -built plans for information on seawalls and guide piles at the site. Under Task 1.2, we will supplement and "reality - check" our understanding of the existing marine structures within the Rhine Channel and adjoining properties through a structural review to be conducted by URS. This evaluation will include a vessel -based site "swim -by" reconnaissance, during which exposed seawalls, floats, and guide piles will be visually inspected. We will directly measure seawall embedment depths by jet probing at representative locations. A small diameter water jet pipe will be advanced along and in contact with the face of the wall. Once the pipe loses contact with the wall, it is assumed to have reached the bottom of the wall's embedded length. We plan to test the embedded depth at 15 to 20 different seawall locations within the Rhine Channel. Optional Item: Direct Observation of Seawall Tierods. While our swim -by site reconnaissance will include direct observation of seawalls and their condition, as well as allow for observation of evidence of stabilizing tierods where their ends are exposed at the wall face, we will have no way of determining the actual condition of the tierods because they are buried behind the walls. As a result, our design work will use fairly broad and conservative assumptions for the state and load capacity of the tierods. This potential uncertainty will be a key aspect of our design work, because the tierods are an integral part of the seawall stability. Our assumptions could be refined through a set of tierod unearthings, or "test pits," wherein temporary excavations are made behind the seawall in accessible locations to expose and allow visual observation of the tierod conditions. This process would be a fairly intrusive process and could add an estimated $20,000 to $30,000 to the design fee, depending on how many locations are available for such an exercise. At this time, we have not included tierod unearthing in our scope and fee estimate. If during the course of our analysis, it becomes evident that tierod unearthings would contribute significantly to the long -term adequacy and efficiency of the design and construction, we will discuss adding this effort to our scope. Mr. Chris Miller June 11, 2010 Page 4 Task 1.3: Investigation of Guide Piles The City currently would prefer to remove and replace guide piles as part of the dredge program to better facilitate dredging around the dock structure. The design team will evaluate and qualify the current state and embedment depth of the guide piles to determine the number and locations of guide piles that should be replaced. Our swim -by reconnaissance and a general review of the City's archived records will allow us to develop a general idea of pile conditions. Because these sources of information are limited in their completeness and accuracy, we will conduct a more detailed analysis of the guide piles. Direct testing and evaluation of the piles in the field will be accomplished via impact -echo testing, a non - destructive pile testing method that can be conducted by personnel using specialized hand -held instruments, which allows for estimation of their actual in -place embedded lengths below the mudline. This field testing will enable us to fine -tune and reality -check the actual pile conditions and potentially reduce the number of piles that need to be extracted. Note that because theguide piles are private structures, permission from e_ ndstiug property owners would be required for ourpersonnel to conduct testing from the docks. Task 2: Permitting Under Task 2, Anchor QEA will prepare and submit required resource agency permit applications to the California Coastal Commission (CCC), Santa Ana Regional Water Quality Control Board (RWQCB), State Lands Commission (SLC), and USACE Regulatory Division for Rhine Channel and other City- managed areas to be dredged with material targeted for disposal at the Port of Long Beach. Anchor QEA will also assist the City with the Port of Long Beach disposal applications for the Rhine Channel, non -RGP City areas and Federal Lower Newport Bay material. Specific tasks will include attending pre - application meetings with the regulatory agencies, attending meetings with Port staff, preparing agency permit documents, and providing any additional agency requested biological resource information. Meetings with agency staff, as needed, are included in our costs for this task. Mr. Chris Miller June 11, 2010 Task 2.1: CCC Coastal Development Permit Anchor QEA will initially facilitate at least one pre - application meeting with CCC staff prior to submitting a complete request for a Coastal Development Permit (CDP). Anchor QEA will prepare a pre - application package for use at these meetings that will comprise the project description, conceptual -level figures, and a summary of the analysis showing compliance with California Coastal Act (CCA) regulations. Based on our discussions with CCC staff, we will initially facilitate a meeting with Mr. Jack Gregg, the Coastal Commission staff member on the Los Angeles Region Contaminated Sediments Task Force (CSTF). Meetings with other CCC staff may be required. Building on information gathered during the previous meetings with the CCC, Anchor QEA would complete the CDP application package and submit it to the CCC. Work associated with this subtask will include completing the required questionnaire and preparing the permit application attachments. One internal draft CDP application package will be provided to the City for review and comment. Anchor QEA will then submit the CDP application package to the CCC on behalf of the City, and respond to all questions posed by CCC staff. We will coordinate with City staff to synchronize City Council approval with prompt submission to the CCC. Anchor QEA will also prepare a draft Staff Report (if requested) to accelerate the processing of the permit application and attend the CCC hearing on behalf of the City. Note that the CCC cannot consider an application complete until a final California Environmental Quality Act (CE(2A) document is available. Task 2.2: RWQCB 401 Water Quality Certification /Waste Discharge Requirements Anchor QEA will facilitate at least one pre - application meeting with the RWQCB staff prior to submitting a complete request for a 401 Water Quality Certification/Waste Discharge Requirements (WQC/WDR). Following this meeting, we will prepare a draft application for WQC/WDR for review by the City. A draft Confirmatory Sediment Sampling Plan and draft Water Quality Monitoring Plan will also be prepared. Anchor QEA will respond to Mr. Chris Miller June 11, 2010 Paee 6 comments from the City and submit the final permit application to the RWQCB on behalf of the City. Anchor QEA will respond to all questions posed by RWQCB staff. Note that the RWQCB cannot consider an application complete until a final CEQA document is available. Task 23: SLC Dredging Lease Because the project involves dredging of submerged tidelands held in trust for the state of California, a SLC dredging lease will be required. Anchor QEA will prepare the necessary application for a dredging lease and will work with the City to negotiate the lease, and will represent the City at the SLC hearing if required. We will prepare a draft request for the dredging lease and provide it to the City for comments. Once comments are incorporated, Anchor QEA will submit the lease application to the SLC on behalf of the City. Anchor QEA will respond to all questions posed by CSLC staff. Based on our experience with other projects involving contaminated sediments, the SLC will likely agree that there are no valuable mineral rights requiring compensation. Task 2.4: USACE Standard Individual Permit Anchor QEA will initially facilitate at least one pre - application meeting with USACE Regulatory Division staff. We will again prepare a pre - application package that will comprise the project description, figures, and a summary of the analysis showing compliance with CCA regulations. We will facilitate this meeting with Ms. Cori Farrar of the Los Angeles District Regulatory Program. Anchor QEA will then prepare a complete application for a Standard Individual Permit (SIP), including discussions of alternatives considered; avoidance, minimization, and mitigation measures; necessary Endangered Species Act/Essential Fish Habitat (ESA/EFH) information; and a draft public notice. The City will be provided a draft of the application package prior to submittal for review and comment. To further accelerate the processing of this application, we will also prepare a draft National Environmental Policy Act (NEPA) Environmental Assessment (EA) for use by USACE staff. One internal draft EA will be provided to the City for review and comment. Anchor QEA will finalize the EA and submit it to the USACE. Anchor QEA will respond to all questions posed by USACE staff. Permit Fees Current costs do not include any fees due to the agencies for processing permit applications; these fees will be paid directly by the City. Based on available fee calculators (fees will be confirmed by agencies), we estimate permit fees to be as follows: • USACE — $10 (fee for SIP for public agency) • RWQCB — $25,000 (maximum fee) • CCC — $12,500 (application fee plus grading/fill fee) • SLC — $1,525 (application fee plus dredging lease) Cost assumptions for Task 2 and all associated subtasks: • Draft documents submitted to the City will be in electronic form. Final deliverables will be submitted to the City in electronic and hard -copy form (five copies). • Agency meetings will be combined when possible, as to avoid duplication of effort. • Attendance at agency meetings will occur as needed. • Agency concerns will be reviewed and addressed as necessary, and permits applications revised, if needed, as a result of agency comments. Task 3: Final Engineering Design and Documentation Following our initial structural overview and bathymetric survey performed under Task 1, Anchor QEA will proceed with final engineering analysis and design of the Rhine Channel and City- controlled (non- Regional General Permit) dredging project as well as preparation of construction documents (plans and technical specification) that can be used for soliciting bids. We anticipate that the construction process will be managed by the USACE, and thus, our construction documents will be prepared in a format consistent with USACE project standards. A key aspect of our final engineering evaluation is to evaluate the effects of dredging on seawalls and guide piles at the site, so that the dredge prism can be designed and optimized. Because dredging removes sediment that helps to retain the toe of the seawalls, an offset Mr. Chris Miller June 11, 2010 distance will need to be included in the dredge design so the walls are not destabilized as a result of the work. However, it is in the City's interests to maximize the volume of removed sediments to best achieve overall cleanup goals, and it will be important to determine the relationship between dredging geometry /offset distance and overall seawall stability with as much certainty and detail as possible. While the exact scope and level of effort for these tasks will be somewhat dependent on our findings from Task 1, we anticipate the following subtasks will need to be completed. Task 3.1: Geo technical Engineering Explorations and Analysis The analysis of seawall stability and how it would be affected by dredging requires a thorough understanding not only of the characteristics of the seawalls themselves but also the geotechnical properties of the soils in which the seawalls are situated and which they retain. Any gaps in our understanding of geotechnical site conditions would require the design team to make conservative assumptions about soil properties. In our design experience at Newport Harbor, we have found that seawall stability in the area is generally marginal, and we expect the same to be true at Rhine Channel. Making overly conservative assumptions about the seawall and soil conditions could have significant impacts on our results and could lead to excessive dredging setback distances, excessive costs for possible seawall repairs, or both. It is, therefore, important to the adequacy of our analyses that sufficient geotechnical information be gathered throughout the Rhine Channel —in the "retained" upland areas behind the seawalls and in the offshore areas in front of the seawalls —and to sufficient depths to demonstrate geotechnical conditions below the bottom of the seawall panels. Anchor QEA has reviewed City records and archives and has found relevant geotechnical subsurface data at a few properties adjacent to the Rhine Channel. These data will be critical for our analysis, but because the information is widely separated, and in some cases does not reach a sufficient depth for our design needs, it will be necessary to obtain additional data to develop a sufficiently complete understanding of geotechnical conditions in the project area. Anchor QEA proposes to conduct the following series of geotechnical explorations at locations where no information is currently available, as follows: • Five in -water geotechnical borings to depths of 20 feet, using a small, relatively maneuverable mud rotary drilling barge • Two landside borings to depths of 40 feet, using a truck - mounted mud rotary drilling rig • Seven cone penetrometer tests (CPTs) to depths of 50 feet, on landside locations, using a truck - mounted CPT rig Boring samples will be obtained at 5- foot -depth intervals, with some samples submitted to a local geotechnical laboratory for testing of moisture content, grain size distribution, Atterberg Limits (for fine - grained samples), and soil strength (by triaxial testing). Altogether, we expect that the proposed geotechnical exploration program will require 4 days by an Anchor QEA geotechnical representative and a drilling firm working as a subcontractor to Anchor QEA. We have assumed that it will not be necessary to conduct geotechnical investigations at the Marina Park, American Legion, or 15th Street Pier locations. We understand that a recent 2008 geotechnical evaluation was conducted at the Marina Park site, but we are not aware of any geotechnical information from the American Legion or 15th Street Pier locations. For these sites, we plan to use existing information in combination with appropriately conservative structural assumptions to design a maintenance dredging program that is protective of the existing seawall, floats, guide piles, and timber pier. If, during the course of our analysis, it becomes clear that additional geotechnical information is needed to avoid a significant project impact, then we will discuss with the City the reasons and advantages of adding this element of work to the proposed scope. Our labor under this task includes the following elements: • Field time for an Anchor QEA representative during the entirety of the geotechnical field work, including equipment set -up, demobilization, and oversight of site cleanup • Securing any required permits from the City of Newport Beach, the County, and/or any other public agencies, as necessary • Reviewing available information on utility lines that are present, including coordinating with "DigAlert" for a pre - drilling utility locate (includes one site visit to lay out the on -land exploration locations) Mr. Chris Miller June 11, 2010 Page 10 • Packaging and documenting all samples obtained, delivering to our geotechnical laboratory, selecting samples for testing, coordinating the lab tests, and reviewing the laboratory results • Establishing contracts and administrative requirements with subcontractors performing the drilling and laboratory work • Providing a signed, stamped report documenting all geotechnical and structural stability work performed Task 3.2: Analysis of Structural Stability Once geotechnical data has been gathered, Anchor QEA and URS will use geotechnical and structural engineering analysis techniques, such as determination of stability ratios, and two - dimensional (2D) limit equilibrium methods and a finite element modeling, to determine how dredging affects pressures experienced by the seawalls and the potential response and deflection of surrounding ground and seawall elements. These approaches will be used to estimate the current stability level of the seawalls and to define the relationship between dredging prism geometry and the seawall stability, which will allow the design team to develop a protective dredging plan while also meeting the City's Rhine Channel cleanup goals. Analysis will include an assessment of gravity and seismic loads, including possible liquefaction effects. Following completion of our field work and structural and geotechnical stability analysis, a draft report will be prepared that summarizes our findings and conclusions regarding the stability of the seawall and how dredging will be designed to maintain the stability of the walls. As stated for Task 3. 1, we have assumed that it will not be necessary to perform a structural stability evaluation for the American Legion site and that existing information can be used to create a sufficiently protective maintenance dredging design. Conservative assumptions will be made regarding the ability of existing site features to withstand removal of sediments during maintenance dredging. If it becomes clear during the design process that additional analysis would be beneficial to the City, then the option for conducting additional studies can be discussed. Mr. Chris Miller June 11, 2010 Page 11 Optional Task: Structural Analysis of Existing Guide Piles. We have not included structural analysis of existing guide pile stability in this scope and fee estimate, as it is assumed that all piles will be removed prior to dredging. If, however, the City chooses to leave some or all of the guide piles in place, a structural evaluation of the piles will be required. As discussed under Task 1, we can offer the City the option of conducting a full structural analysis of the guide piles. We estimate that this structural analysis would add approximately $32,000 to our design costs, in addition to the more comprehensive field study of the piles described under Task 1. At this time, however, we are not including such an analysis in our scope, anticipating that our review of the piles will be more cursory and based on visual observations from our swim -by reconnaissance and review of City records. If during the course of our analysis, it becomes evident that a thorough structural analysis of the guide piles appears warranted and would contribute significantly to the long -term adequacy and efficiency of the design and construction, then a modification to the scope of work can be discussed. Task 3.3: Plans, Specifications, and Opinion of Probable Cost Anchor QEA and URS will prepare Draft (65 percent), Draft Final (95 percent level) and Final (100 percent level) design plans, technical specifications, and opinion of probable cost for the construction work. The development of these documents will occur concurrently with the permitting process, and Draft (65 percent) documents will be prepared specifically to support permit applications. Construction plans will depict site bathymetry, existing structures, site conditions and restrictions, required extents and limits of dredging, required side slopes, allowable overdepth limits, allowable equipment mooring areas, and typical cross sections. The plans will include a series of drawings that depict the seawalls, floating docks, and guide piles, incorporating aerial photography that has been obtained from the City, and the results of the bathymetric survey and structural analysis conducted as part of the current scope of work. Technical specifications will include sections for dredging, transport, and disposal of material. Any permit conditions and environmental restrictions known at the time of preparation will also be included in the plans. Specifications will be prepared using USACE standard format. Should the City request that specifications be prepared in another format, Mr. Chris Miller June 11, 2010 Page 12 we may be able to accommodate that request without budget increase if the alternate format is provided early in the design process. A bid schedule will be included as part of the bid package, which will contain our estimate of payable dredging volume quantities for design plans, including allowable overdepth and side slopes. This quantity will also be used in our opinion of probable costs. At this stage, we have made our best estimate of the level of effort that will be necessary to adequately document the project details in this set of deliverables. As our engineering analysis proceeds, we will be able to refine our expectations of this effort. Therefore, after completion of Tasks 1, 3. 1, and 3.2, and prior to making significant progress on the construction documents, we will meet with the City to discuss our findings and their effect on the plans and specifications preparation effort. If appropriate, we will refine our overall scope and level of effort at that time to reflect our more refined project understanding. We have assumed that the Draft (65 percent) deliverables will be submitted to the City in electronic form only and that the Draft Final (95 percent) and Final (100 percent) deliverables will be submitted to the City in electronic and hard -copy form (five copies). ESTIMATED SCHEDULE A detailed project schedule in the form of a Gantt chart has been created based on the current project status as well as several aggressive assumptions (e.g., assuming that construction bid documents will be released prior to obtaining final permits) and is attached to this scope of work for reference. SUMMARY OF COSTS Table 1 presents our estimated costs for the recommended and presented scope of work, on a task -by -task basis. Our scope description has also presented various optional scope items that the City may elect to undertake. Table 2 summarizes the projected costs of these optional items. We propose to conduct this work on a not -to- exceed, time - and - materials basis, as has been done for our work to date. Our previous engineering- related scope of work for pre- design Mr. Chris Miller June 11, 2010 Paee 13 tasks to support the construction of a CAD cell is temporarily on hold pending the disposal option at the Port of Long Beach. As such, the funds authorized for our previous scope of work have been applied to the Rhine Channel effort to advance to the current stage of the project, such that we can now enter into the final design stage. Throughout the conduct of these tasks, Anchor QEA will provide detailed comments and summarize staff efforts on all invoices. Table 1 Summary of Estimated Costs for "Base" Tasks Task Task Description Estimated Cost 1 Structural Review and Updated Bathymetric Survey 1.1 Updated Bathymetric Base Map of Complete Project Area $30,656 1.2 Investigation of Seawalls and Panels $12,783 1.3 Investigation of Guide Piles $10,000 2 Permitting 21 CCC CDP $65,360 2.2 RWQCB 401 WQC/WDR 2.3 SLC Dredging Lease 2.4 USACE SIP 3 Final Engineering Design and Documentation Geotechnical Engineering Explorations and Analysis $57,145 Analysis of Structural Stability $47,720 L33 Plans, Specifications, and Opinion of Probable Cost $83,796 Total Estimated Cost $307,460 Table 2 Summary of Estimated Costs for "Optional' Tasks Optional Task Item Estimated Cost Direct Observation of Seawall Tie Rods $20,000 to $30,000 Structural Analysis of Existing Guide Piles' $32,000 Notes: 1 As presented in description for Task 1 2 As presented in description for Task 3.2 Mr. Chris Miller June 11, 2010 Page 14 We appreciate the opportunity work with the City on this important project. If there are any questions about this scope of work, please do not hesitate to contact us at (949) 347 -2780. Sincerely, Michael Whelan, P.E. Steve Cappellino Anchor QEA, L.P. Anchor QEA, L.P. f rwrre.raavwcar obn rree+o rravly ) +rel.evwM.ranr.w vaw wrr roan rx YYlo rr OglllD ) Y!uOYCea'YVa VaYa4Y Yla van InYUID lr Y!vlD a.�x+. <s..w cbn vw b!blo In vela f Yrvnrrr Lw.p- vv[wy.Vy. 'C bn 1'4n6^blE 1'.. Y1Y10 e yM wCNVx an••'wrn.,v !Lan V4Y 6'VIL r V)YID I 4M y.r/vran IDan NYe Nb1D Irry V)Y +0 e +a. >,. v.earrlwrr )lawn rr«Yla in )yle r 9lr Metl.la MVine). btl v. •Dh. i. bY!') lrubllM !D MM.ar!v[wv!. !pbn inbY.] Iw Y1 n10 11 'y�1Yx Jal b:yr )evry Inb1V 10 Va•MND v c.vr.Mel.rx rre can +remnw Irma a o.sn wlw'r.rry sbrr lin•nov!s i. ry,o a 1M ee�ar/1br WM ✓r YYMI Han in lylp rnv YYp 11 fnp4WVy v //inpl.eii N."`r 1)an Vm rN!p .r llpa fe Vnrr.�V ee.1 r...rr Very hal. irrmlD Ini aylD fl 1r. 43 (srrabn Dawwl. Man rnHWle fr 1Vy10 If yPrtrt >/1w4YI hbn In Inb10 T. Y!Y10 n fwr r.r. )an Ir YNYa l,n VlYa H Yelbb(rge ♦ra IN VYO Y^Vlp !MOV JIp )1 NIV!h.IWrr !L bn `v YpfO •1!y \M WIO H Grvn.. )an an!0 Va VrY!D )1 Yalb aevn <mwT !y .rV!Y!0 Ir V!YW ). IM pn.wa i+Y wlmlV !fan rlrJ Vt V!c lr 1py!O H Mr rlrrM Me.n WM IMM +a1VWq H rJyK)epa yl piMM SOa. YaJ!D6 ^L 1P!b!T!0 11 yarnap HC.n VIe !4!Y!C Ir.I W10 H ®a wry.!a wn0 san Vra!!nV!c VlYlo l+r iH CaWeea qYn Yb01yVp vllnl 111 U4 [ucMp IO bn Ybl!Nr!0 iu lbl4!0 II SWR Aan rM11NI V!D r lrlV 1 U Wrarm rbn vwe lyly!0 1!x lnl I )1 IrYb O•gV.e an 1v In V1! Iw In 11! >. ttorl nan rrwro vw YHne N Wl'uw.1/wl �.T )bn I!nbn10 MVVIO M r(I bClvr.rwe Ibl Ycw VlrlO YeVIIIO 1I VJi.Ywr y15MMJ %bn ly bYlp Nrl lll110 x.r«.nn.Dx.ebrn.r...P :bn Inr:ro!c rr r.y,w 1 Grr.pv wo..awry Iva .. rnnro .r mn•c .> Gri. MT.reCMi !M M.0 In4tJ ✓1J %nblJ .1 Cf[M MpII�mf >l ery. n•by!C rn V!'r!a a eY.b vlen ve tone rw mlYq a 4WrGrWter!xwn r)rxn WYrrWO rn IVINO .l Yen ..:.:.�o^'Yr•rD::n L.v.M•n. vn.rr pJnv Np'.Y!L' IIV VJY'10 a na'.v 1'F>< uan rvn.•o r. •InY!o e vs Y..r- onriror+n. v.,r„r...a •xv.re sr;nmD v!Inv!o 14' Nprn11 V>yy p.r4( rY 1VYnNMrrV.y pt an Iyrp lGl•1D Yew!D'NIe of V. AVIVMCennYVJr VagreVN ealx Va01lJVr0 W1Nry 10 U NP•b nrrlJ /bn IMO lan ll/p 1O p1Yl I la. aM.. b!wrV I!CFin $rMa 1q 1nNYa Sla Vn bn Sa W rp �rr11° ba.a.rw orl' �� rre 1. YT..rraa. ry urer alr. 1 1 ly r, )1.Odv[rnulf Ybrns. V V �� lu) }. Y..ryY. r Nraswr)WIM +r, l ). caurWw MPrawb s y beMlr ti tl� cfv } y C I rruVr LnM ^ lMrrA +r 6.a V V✓v. . rrMwf lrla.F � famVlrrmn• Vy 1 v.1 rti ie Agenda Item No. 15 June 22, 2010 NEW M. I . wnnx prNp •vl 'rrcr.mice.,.r.xr _1 ANCHOR QEA, LLC. 2010 PROJECT COST ESTIMATING FORM Proposal /Project Name: COmpinbon 01 EnP.Indaring, Design and Permitting Revised &2772010 Cleanup Dredging of Rhine Channel I owport Beach CA $307,460 Task 1 Strurt ral Review and 610ylaeinc S arvey $ ' 53,439 Task Perk 2-9 $ 66,380 Task 3.1 ^cfecnnlcal Enq n.r,nng Fxpld.al ", and Anp,s $ ' 57,145 Task 3.2 alyvis of Stluw ral Sfabhity $ 47,720 Task 3.3 plans: SnadrtCatldns andJl9non orP abaNO COaC $ 83796 Rbine CM1a11el - Design antl Pit"tilling - Ap Budget revised 5 -27 -1 axlsx Number. Prepared: (':Vhr,D! E E $ Billing Task Task Task Task Task Task Total Total Labor Cate ones Rate 1 2 3.1 3.2 3.3 4 Hours Dollars ',:al C YI/ /I. b 1'la° P 5 197 - 0 96 4 8 36 0 0 0 0 a nq vial s CM a ' r SCi F 133' 20 0 32 50 110 0 0 0 0 144 5 28,368 i n 01nry c11y 1'ngr, /Pb ^ i $ W 0 60 0 a 0 0 0 0 0 0 212 S 38.796 orA1 ldiVCM C qfA ur!Srii 6 142' 26 0 16 a 72 0 0 0 0 0 60 S 0,720 Slaft:I PoIa,Y:ACM /Engrl4.AlPlanrri $ 125 0 160 0 0 0 0 0 0 0 0 114 S 16,188 gtay 2 Analy If N R+yrelA /*'Ian /Sei S 144 0 0 0 0 0 0 0 0 0 0 0 0 160 0 $ 20,000 $ b ?1A UcM. L:aPYLi 7. 1. mSci $ 99 0 0 84 124 168 0 0 0 0 0 376 S 37,224 Cvi,c 105 16 40 4 8 112 0 0 0 0 0 180 6 18,900 CA') fle. ,,rcr 5... _. 142 0 0 0 0 0 0 0 0 0 0 0 $ - e ftr_fC''A, S $2- 20 104 24 24 44 0 0 0 0 0 216 $ 17.712 £Ybed G",dinatm(.Ahmlr) $ e2. 0 0 0 0 0 0 0 a 0 0 0 $ 1'e t...n n $ 83" 0 0 0 0 0 0 0 0 0 0 0 $ - Na6o, ^,a. ' =svgs Conauilanl :3 : 35'0. 0 0 0 0 0 0 0 0 0 0 0 $ Total Hours 82 460 164 214 542 0 0 0 0 0 1,462 Total Labor $ 10,672 $ 61.S60 $ 19,620 S 25,810 $ 69,446 $ - $ - S - $ - $ - $ 186,906 Average Hour Rate $ 120 Suhoonsubants URS (Slmctural E -oir sj $ 18,400 $ - $ - S 21,500 $ 13,100 $ - $ - $ - $ - $ - S 53,000 G64; iEa hym tc3urveya ^) $ 23,895 $ - $ - $ - 8 $ - $ - $ - $ - $ 23,895 G egg 0,11 ng (reuterr inal Expl0,a5one) $ - $ - $ 33,165 $ - $ - $ - $ $ _ $ $ _ $ 33.165 Go, ¢h I ,I laboiyo Dh $ - $ - S 2,400 S - $ - $ - $ - $ - $ - $ $ 2,400 $ - $ - $ $ _ $ $ - $ - $ $ - $ $ Total Cost $ 42,295 $ - $ 35,565 $ 21,500 $ 13,100 $ - $ - $ - $ $ - S 112,460 Markup ' 0:0 %. $ - $ - $ $ _ $ . $ 1 $ - $ - $ - $ S Reimbursahfes CAD /Computer($/hr) 510,00 > $ 160 $ - $ 40 $ 240 $ 800 $ - $ - $ - $ - $ - 5 1,240 Mileage (Vents) $0.50^ $ 52 $ - $ 100 $ 50 $ . $ - $ - $ - $ - $ - $ 202 Copies ($ /copy) ' 50.10 $ 20 $ - $ 20 S 20 $ 5o $ - $ - $ - $ - $ - $ 110 Anchor beat($ /day) - SSOQ.'1 $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - $ - Faxes($flax) 5i.03. ': $ $ $ $ $ $ $ $ $ $ $ Ourtslde Expenses V.Ncfe Rental $ - $ - $ 300 $ - $ - $ - $ - $ - $ - $ - $ 300 Rep^ Alk,'t ^g $ 100 $ - $ 50 S 100 $ 400 $ - $ - $ - $ - $ - S 650 MnIfFecexlCr.ner $ 50 $ - $ 50 $ - $ - $ - $ - $ - $ - $ - $ 100 r'fare... $ - $ - $ 600 $ $ - $ - $ - $ - $ - $ - $ 600 HotellPer a,i $ - $ - $ 600 $ - $ - $ - $ - $ - $ - $ - $ 800 64isceltaneous I $ 90 $ 4.000 1 $ - I $ - $ - I S - 1 $ - S - 1 $ - $ - 1 1 $ 4.090 Total Cost $ 472 $ 4,000 $ 1 960 S 410 $ 1,250 1 $ - $ - $ - $ - $ - $ 8,092 Markup 0A'�1 -.' -, $ - $ - $ - $ - $ - $ - $ - $ - $ - $ $ Field Equipment and Supplies Sunni $ - g - $ - $ - $ - $ - $ - $ - $ - S $ - Markup :DA $ - $ - $ - $ -.$ - $ - $ - $ - $ - $ $ TOTAL COSTS $ 53.439 $ 65,360 $ 57,145 $ 47,720 $ 83,796 S - $ - $ - $ - $ $ 307,460 City of Newport Beach BUDGET AMENDMENT 2009 -10 'ECT ON BUDGETARY FUND BALANCE: Increase Revenue Estimates X Increase Expenditure Appropriations AND Transfer Budget Appropriations SOURCE: from existing budget appropriations from additional estimated revenues PX from unappropriated fund balance EXPLANATION: This budget amendment is requested to provide for the following: NO. BA- 10BA -054 AMOUNT: $37a,ass.00 Increase in Budgetary Fund Balance X Decrease in Budgetary Fund Balance No effect on Budgetary Fund Balance To increase expenditure appropriations to approve amendment No. 2 to the professional services agreement with Anchor QEA Inc. for preparation of final engineering evaluation design and permitting support for the Rhine Channel Contaminated Sediment Cleanup Project. ACCOUNTING ENTRY: BUDGETARY FUND BALANCE Fund Account 230 3605 REVENUE ESTIMATES (3601) Fund /Division Account EXPENDITURE APPROPRIATIONS (3603) Description Tidelands Fund - Fund Balance Division Number 7231 Tidelands Capital Account Number C4402001 Harbor Dredging Project Division Number Account Number Division Number Account Number Division Number Account Number Signed: Signed: Signed: Financial Apprnal: Administrative Services Administrative Approval: City Manager City Council Approval: City Clerk Amount Debit Credit $378,495.00 , $378,495.00 !&,J [) Date Date Date