Loading...
HomeMy WebLinkAbout07 - Public Dock Access ImprovementsCITY OF NEWPORT BEACH CITY COUNCIL STAFF REPORT Agenda Item No. 7 August 10, 2010 TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL FROM: Public Works Department Patrick Arciniega, Senior Civil Engineer 949 - 644 -3347 or parciniega @newportbeachca.gov SUBJECT: PUBLIC DOCK ACCESS IMPROVEMENTS —15TH, 19TH, AND FERNANDO STREETS — COMPLETION AND ACCEPTANCE OF CONTRACT NO. 4110 ISSUE: Work for the public docks has been completed and they are ready for acceptance by the City. RECOMMENDATIONS: 1. Accept the completed work and authorize the City Clerk to file a Notice of Completion. 2. Authorize the City Clerk to release the Labor and Materials bond 35 days after the Notice of Completion has been recorded in accordance with applicable portions of the Civil Code. 3. Release the Faithful Performance Bond one year after Council acceptance. Construction Contract Summary: Construction Contract Final Cost at Benchmark Contract Award Amount Completion Target Actual Time (days) Contract Contract E(3) $164,903.00 $158,222.00 Less 45 Plus10% 4.1% DISCUSSION: On March 23, 2010, City Council authorized the award of the Public Dock Access Improvements — 15th, 19th, and Fernando Streets Project to Swift Slip Dock and Pier Builders, Inc. The contract provided for replacing the existing gangway at the 15th Street dock as well as expanding existing dinghy capacity at 15th 19th and Fernando Street docks. Public Dock Access Improvements 15", 19" and Fernando Sts. -Completion and Acceptance of Contract No. 4110 August 10, 2010 Page 2 The project was completed without delay and beat the CIP schedule by three days. Swift Slip Dock and Pier builders did an excellent job and the boating public is very pleased with the new mooring spaces. The contract has now been completed to the satisfaction of the Public Works Department. A summary of the contract cost is as follows: Original bid amount: $165,903.00 Actual cost of bid items constructed: 154,903.00 Total change orders: 5,599.00 Final contract cost: $160,502.00 The final overall construction cost, including two change orders was approximately 3.3% percent below the original bid amount. The two change orders consisted of extra work items as listed below: Item No. Description Amount 1 Removal of 11° of excess width from Fernando St. Dock $ 300.00'. extension. 2 Fernando St. Dock — New wood facia, white rubstrip and 4,519.00 cleats for the existing float and pile caps for the new piles. 15th St. Dock - New wood facia, white rubstrip and cleats for the existing float and pile caps for the new piles. 19`h St. Dock — New wood facia, white rubstrip and cleats for the existing float and pile caps for the new piles. 3 Additional cleats for 15 th St. Dock 780.00 Total Project Change Orders $5,599.00 A summary of the project schedule is as follows: Estimated completion date per March 2010 Schedule: July 23, 2010 Project Award for construction: March 23, 2010 Date of Notice To Proceed (NTP): April 16, 2010 Contract Completion Date per NTP & Approved Extensions: June 22, 2010 Actual Construction Completion Date: June 18, 2010 Environmental Review: This project is exempt from the California Environmental Quality Act (CEQA) pursuant to Section 15301 Class 1 (c), of the CEQA Implementing Guidelines. This exemption covers Public Dock Access Improvements 15' ", 19`" and Fernando Sts. -Completion and Acceptance of Contract No. 4110 August 10, 2010 Page 3 the maintenance and alteration of existing public facilities with negligible expansion of the facilities in areas that are not environmentally sensitive. PUBLIC NOTICE: The Notice Inviting Bids was advertised in the City's official publication and in construction industry publications. Prior to starting work, the City - prepared construction informational notices that were distributed by the Contractor to residents who live within the work vicinity. The notice was distributed ten days prior to the scheduled work. FUNDING AVAILABILITY: In addition to the original construction contract, this project involved other project expenses, as summarized below: Construction Consultant Design Eelgrass Inspection Incidentals Total Project Cost $160,502.00 25,647.01 2,750.00 369.38 $187,430.18 Funds for the construction project were expended from the following account: Account Description Tide and Submerged Lands Prepared by: Patrick Arcin' g Senior Civil i eer Attachment: Location Map Account Number Amount 7231- C4402000 $160,222.00 Total: $160,222.00 Submitted by: H W W K F U) m NEWPORTBAY PUBLIC DOCK BAY AVENUE WEST PROJECT LOCATION NEWPORTBAY PUBLIC DOCK F- w w m BAY AVENUE i WEST N PUBLIC DOCK ACCESS IMPROVEMENTS 19TH ST., 15TH ST. & FERNANDO ST. 4oRN �I /nOO j� 1v�!I 1" el NEWPORTBAY PUBLIODOCK F FG E GF A�FN FATFR e W 0 0 Z a Z W W CITY OF NEWPORT BEACH PUBLIC WORKS DEPARTMENT aTE 3/10/10 SCALE N.T.S SHT 1 OF 1 2AWN PA I C -4110