HomeMy WebLinkAbout10 - Balboa Island & Other City Sewer Main Point RepairsCITY OF NEWPORT BEACH CITY COUNCIL STAFF REPORT Agenda Item No. 10 September 28, 2010 TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL FROM: Public Works Department Alfred Castanon, Associate Civil Engineer 949- 644 -3314 or acastanon @newportbeachca.gov SUBJECT: BALBOA ISLAND AND OTHER CITY SEWER MAIN POINT REPAIRS — AWARD OF CONTRACT NO. 3802 ISSUE Staff requests City Council approval to award the Balboa Island and Other City Sewer Main Point Repair Project to John T. Malloy, Inc. RECOMMENDATIONS 1. Approve the project drawings and specifications. 2. Accept Westcoast Public Work's request to withdraw their bid. 3. Award Contract No. 3802 to the 2nd Low Bidder, John T. Malloy, Inc., for the Total Bid Price of $286,050, and authorize the Mayor and the City Clerk to execute the contract. 4. Establish an amount of $43,000 (15 %) to cover the cost of unforeseen work. 5. Additional contract costs of approximately $14,450 in consulting geotechnical services is estimated for this project and will be performed under the on -call professional services agreement with Harrington Geotechnical Engineering, Inc. DISCUSSION At 10:00 A.M. on September 2, 2010, the City Clerk opened and read the following bids for this project: TOTAL BID AMOUNT $249,690.00 $286,050.00 $308,400.00 $311,419.81 $319,263.00 $377,140.00 $412,396.00 $559,905.00 BIDDER Low Westcoast Public Work, Inc. 2 John T. Malloy, Inc. 3 M & E Construction 4 TTS Engineering, Inc. 5 Nikola Corporation 6 GCI Construction, Inc. 7 Mike Prlich & Sons, Inc. 8 Paulus Engineering, Inc. TOTAL BID AMOUNT $249,690.00 $286,050.00 $308,400.00 $311,419.81 $319,263.00 $377,140.00 $412,396.00 $559,905.00 Balboa Island and Other City Sewer Main Point Repairs — Award of Contract No. 3802 September 28, 2010 Page 2 Upon Staffs review of the Low Bid, Westcoast Public Works, Inc., it became apparent that the contractor made a major error in the dewatering bid item. After discussions with the Contractor it was confirmed that an error was made in that only $1,000 was listed as his cost for the dewatering bid item. A majority of this project work is on Balboa Island and Balboa Peninsula where an extensive dewatering system will be required to complete the work. The Contractor admitted that he does not own the appropriate dewatering system nor did he list a sub - contractor to perform the work. The Contractor has since submitted a letter withdrawing his bid citing the error in the dewatering bid item. Staff would also note that the Low Bid contractor listed no sewer experience in the required Technically Ability and Experience References required in the bid documents. Further, the Contractor listed experience from a previous company and not work completed by Westcoast Public Works. Staff would recommend accepting this contractors request to withdraw their bid because of the contractor's inexperience working in a marine area with major dewatering requirements. The second low bidder, John T. Malloy, Inc., provided all necessary forms. A check of the contractor's references indicated that they have satisfactorily completed similar projects for the City of Newport Beach and for other public agencies. The low total bid amount is 12 percent below the Engineer's Estimate of $323,785.00. The low bidder, John T. Malloy, Inc., possesses a California State Contractors License Classification "A" as required by the project specifications. The work necessary to complete this contract consists of removing and replacing deteriorated sewer mains, manholes and service laterals and restoring affected surface improvements within Balboa Island, Balboa Peninsula and West Newport. Past projects in these communities have encountered shallow water tables that are affected by the tide. Contract unit prices were established to control the cost to dewater trenches. Although effort was made to anticipate problems with the point repair project, staff recommends a fifteen percent (15 %) contingency to be included in the contract award to cover the cost of unforeseen items that may arise within these communities, particularly due to the nature of this underground work. Pursuant to the Contract Specifications, the Contractor will have 120 consecutive working days to complete the work. ENVIRONMENTAL REVIEW This project is exempt from the California Environmental Quality Act (CEQA) pursuant to Section 15301 of the CEQA Guidelines. This exemption covers the minor alteration of existing public facilities with negligible expansion of the facilities in areas that are not environmentally sensitive. PUBLIC NOTICE The Notice Inviting Bids was advertised in the City's official publication and in construction industry publications. Prior to starting work, two City prepared notices are distributed by the contractor to both residents and businesses. The first notice will be distributed ten days before work in the area and the second notice 48 hours prior to starting work in the area. Balboa Island and Other City Sewer Main Point Repairs — Award of Contract No. 3802 September 28, 2010 Page 3 FUNDING AVAILABILITY There are sufficient funds in the following account for the project: Account Description Account Number Balboa Island Sewer Main Improvements 7531- C7002003 Total Proposed uses are as follows: Vendor John T. Malloy, Inc. John T. Malloy, Inc. Harrington Geotechnical Various Prepared by: Alf ed Castanon Associate Civil Engineer Attachments: Project Location Map Purpose Construction Contract Construction Contingency Geotechnical Services Printing and Incidentals Total Submitted by: Amount $ 344,500.00 $ 344,500.00 Amount $ 286,050.00 $ 43,000.00 $ 14,450.00 $ 1,000.00 $ 344,500.00 m «f OR7 ❑ ALLEY 418 -M AND ALLEY 407 -C F4 N/S OF PARK AVENUE ® ALLEY 403 -B AND PARK AVENUE BETWEEN DAMOND AVE. & RUBY AVE 5� 602 KINGS ROAD AND 1300 - 1310 KINGS ROAD �6 14TH STREET @ BALBOA BOULEVARD AND ALLEY 256 -C ❑7 ALLEY 256 -D 16 SANTA ANA AVENUE & LA JOLLA DRIVE AND ALLEY 256 -F & 14TH STREET �9 47TH STREET & NEPTUNE AVENUE AND 3101 W. COAST HWY. 10 BAL80A ISLAND - MANHOLE REPLACEMENTS (VARIOUS LOCATIONS) BALBOA ISLAND & OTHER CITY SEWER MAIN POINT REPAIRS LOCATION MAP "ACIFC a 3 S� 0 Q J �[ OH4 "k- LOCATION MAP NOT TO SCALE FX = LOCATOR ITEM NUMBER 2 FASHION ISLAND E CITY OF NEWPORT BEACH PUBLIC WORKS DEPARTMENT DATE 9/8/101 SCALE N.T.S SLIT 1 OF 1 DRAWN AC 0-3802