HomeMy WebLinkAboutSS3 - Wastewater Rate StudyCTY OF F NEWPORT BEACH City Council Staff Report May 26, 2015 Agenda Item No. SS3 TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL FROM: George Murdoch, Acting Municipal Operations Department Director - (949) 644- 3011, gmurdoch @newportbeachca.gov PREPARED BY: George Murdoch PHONE: (949) 644 -3011 TITLE: Wastewater Rate Study (4:45 p.m.) ABSTRACT: The Municipal Operations Department retained the consulting services of H F & H Consultants, LLC ( "HF &H ") to prepare a wastewater and recycled water rate study. The purpose of this presentation is to review the results of the wastewater rate portion of the study and propose the adoption of an appropriate wastewater rate. RECOMMENDATION: The City has recently hired an outside expert to take a look at the rate structure and capital demands of the long -term wastewater fund. Staff will go over aspects of the report with the City Council and community. If the rate structure continues as is without any change, eventually the wastewater reserve fund will be depleted. FUNDING REQUIREMENTS: Should Council move forward with the formal review and approval of the recommendations, a waste water rate and structure may be established unless written protests against the proposed rate are presented by a majority of owners of the parcels subject to the rate. DISCUSSION: Background: The Municipal Operations Department operates and maintains approximately 197 miles of wastewater sewer mains, 4.7 miles of force mains, 4,922 manholes and cleanouts, 25,525 sewer laterals, and 21 sewer lift stations. Operations, maintenance and repair activities include: Sewer line cleaning, root removal, manhole maintenance and repair, lift station operation and maintenance, sewer line video inspection, as well as sewer lateral maintenance, repair and replacement. SS3 -1 Funding for maintenance and replacement activities is collected from rate payers via the Municipal Services bill. Salaries, maintenance, operations, and internal service charges are estimated to be approximately $3.5 million for FY 14 -15. Capital Improvement Projects (CIP) is based upon the Wastewater Master Plan which was last updated in 2009. The Wastewater Master Plan sets $500,000 per year for CIP, increasing to $1,000,000 per year to replace aging infrastructure over a 30 -year period. The estimated wastewater revenue for FY 14 -15 is approximately $3.5 million. City Council Policy F -2 sets the wastewater enterprise reserve level at 50% of the operations budget which is about $1.5 million. Wastewater rates were last raised in 2006 going from $0.30 /HCF to $0.35 /HCF. Thanks to an increase in outsourced services, reduced staff, and other factors, rates have not been increased in almost nine years. Rate Studv: In 2013, the City entered into an agreement with HF &H to conduct a Wastewater and Recycled Water Rate Study, the first priority being to identify the recycled water rates. The recycled rates were adopted by City Council on June 10, 2014 lowering the overall cost to our customers by about 50 %. The next phase of the study was to address the wastewater rates. Attachment "A" is a draft report that includes details of the proposed wastewater rates. Current wastewater revenues provide adequate funding for operations. Ending reserves are approximately $900,000 - but this is short of the minimum reserve balance. To fund capital improvement, reserve funds would need to be used. This trend will fully deplete reserves by 2017 as shown in the attached Figure 1 Projected Fund Balance. Currently the wastewater rates include a fixed fee, sewer use charge and two additional surcharges of $2.00 /month for each additional dwelling unit and $10.00 /month for customers with two -inch or larger water meters. The proposed rate structure eliminates these surcharges and moves the costs to the monthly fixed charge. The proposed rates include: • Fixed charge - a monthly sewer service charge based on the size of water connection. • Sewer use charge - a monthly charge for all customers based on water use. For a comparison of how the new rate structure will affect sample residents, please see Attachment B. SS3 -2 Current Structure FY 15 -16 FY 16 -17 FY 17 -18 FY 18 -19 FY 19 -20 Monthly Sewer Use Charge 5/8" or 3/4" $4.50 $7.34 $8.07 $8.47 $8.90 $9.34 1" $4.50 $7.34 $8.07 $8.47 $8.90 $9.34 1 1/2" $4.50 $8.07 $8.88 $9.32 $9.79 $10.28 2" $14.50 $11.01 $12.11 $12.71 $13.35 $14.02 2 1/2" $14.50 $11.74 $12.91 $13.56 $14.24 $14.95 3" $14.50 $12.47 $13.72 $14.41 $15.13 $15.88 4" $14.50 $14.68 $16.14 $16.95 $17.80 $18.69 6" $14.50 $16.51 $18.16 $19.07 $20.02 $21.02 8" $14.50 $18.34 $20.18 $21.19 $22.25 $23.36 10" $14.50 $23.48 $25.83 $27.12 $28.48 $29.90 Monthly Sewer Use Charge Sewer Only Customers Rate per Account $6.25 $12.28 $13.51 $14.19 $14.90 $15.64 Consumption Charge Rate per HCF $0.35 $0.43 $0.47 $0.50 $0.52 $0.55 Sewer Surcharges Multi Unit surcharge (per DU) $2.00 Note 1 Note 1 Note 1 Note 1 Note 1 Note 1: The surcharge has been incorporated into the Monthly Sewer Use Charge under the revised structure For a comparison of how the new rate structure will affect sample residents, please see Attachment B. SS3 -2 How do we comoare? The study compared the proposed wastewater rates to those of our neighboring agencies (see attached Figure 2 Neighboring Agency Comparison). Next Steps Following incorporation of the City Council's comments and recommendations, staff will present and recommend the proposed wastewater rate and structure to the City Council at a regular Council meeting for final review and approval to move forward with adoption. Staff will be required to issue Proposition 218 notices to the owners of parcels that are subject to the wastewater rate pursuant to California Constitution Article XIII D, Section 6. There will be a 45 -day public notice period, and all written protests will be received and tabulated. Following a public hearing on the proposed wastewater rate and structure, the City Council may thereafter proceed to adjust the wastewater rates unless written protests against the proposed rate are presented by a majority of owners of the parcels subject to the rate. ENVIRONMENTAL REVIEW: Staff recommends the City Council find this action is not subject to the California Environmental Quality Act ( "CEQA ") pursuant to Sections 15060(c)(2) (the activity will not result in a direct or reasonably foreseeable indirect physical change in the environment) and 15060(c)(3) (the activity is not a project as defined in Section 15378) of the CEQA Guidelines, California Code of Regulations, Title 14, Chapter 3, because it has no potential for resulting in physical change to the environment, directly or indirectly. NOTICING: The agenda item has been noticed according to the Brown Act (72 hours in advance of the meeting at which the City Council considers the item). ATTACHMENTS: Description Figure 1 - Proiected Fund Balance Figure 2 - Neighboring Agency Comparisons Attachment A - Draft Sewer and Recycled Water Rate Study Attachment B - Example of Implemented Rate Structure SS3 -3 FIGURE 1 SS3 -4 Target Balance $3.50 - (Operations + Capital) $3.00 a c O $2.50 c c. m es with Rate $2'00 Increase c ` $1.50 o LL ` ��� (Operations) U `�` m $1.00 ■ a `. `%% Reserves without $0.50 �. Rate Increase $0.00 A. FY 2014 -15 FY 2015 -16 FY 2016 -17 FY 2017 -18 FY 2018 -19 FY 2019 -20 SS3 -4 Figure 2 - City Comparison SS3 -5 ATTACHMENT A May 26, 2015 - REVISED DRAFT SS3 -7 CITY OF NEWPORT BEACH 592 Superior Avenue Newport Beach, CA 92663 .W;-� ' c4 '' I v C� NEW � Llh't >RLO SEWER AND RECYCLED WATER RATE STUDY May 26, 2015 HF &H CONSULTANTS,, LLC 201 North Civic Drive, Suite 230 Walnut Creek, CA 94596 C tff CONSULTANTS, LLC All rights reserved. Td, document is printed on 100% recycled, poet - consumer content paper SS3 -8 SS3 -9 May 26, 2015 Mr. George Murdoch Utilities General Manager City of Newport Beach 592 Superior Avenue Newport Beach, CA 92663 Subject: Sewer and Recycled Water Rate Study Dear Mr. Murdoch: HF &H Consultants, LLC, is pleased to submit this Sewer and Recycled Water Rate Study to the City of Newport Beach (City). The report summarizes the analysis that was conducted to develop the recommended rates. A copy of the rate model is included in the appendix. The Recycled Water revenue increases and Recycled Water rate design sections presented in this report summarize the analysis that was previously submitted as a staff report and presented to City Council on April 29, 2014. The City Council subsequently adopted, by Resolution 2014 -78 on September 9, 2014, the recommended Recycled Water rates in compliance with Proposition 218, effective October 9, 2014, and updated each January 1 thereafter. The City has demonstrated leadership in improving rate payer equity during a time when costs are increasing in compliance with regulatory mandates. It has been a privilege to assist the City with this step forward. Very truly yours, HF &H CONSULTANTS, LLC John W. Farnkopf, P.E. Senior Vice President SS3 -10 SS3 -94 TABLE OF CONTENTS 1. EXECUTIVE SUMMARY .................................................. ............................... 1 Findings And Recommmendations ........................................... ..............................1 Sewer.............................................................................. ..............................1 RecycledWater ................................................................. ..............................2 2. INTRODUCTION ............................................................ ............................... 4 StudyPurpose ....................................................................... ..............................4 Rate Making Objectives .......................................................... ..............................4 Background........................................................................... ..............................4 Sewer.............................................................................. ..............................4 RecycledWater ................................................................. ..............................4 3. SEWER PROJECTED REVENUE INCREASES ................... ............................... 6 Revenue Requirements ........................................................... ..............................6 Salaries............................................................................ ..............................6 Benefits........................................................................... ............................... 6 Operations & Maintenance ................................................. ..............................6 Internal Services Allocation ................................................ ..............................7 Operating Reserve Expense ............................................... ..............................7 Capital Reserve Expense .................................................... ..............................7 Miscellaneous Costs .......................................................... ..............................7 Revenue Increases ................................................................. ..............................7 FundBalance ......................................................................... ..............................8 MinimumFund Balance ..................................................... ..............................9 TargetFund Balance ......................................................... ..............................9 4. SEWER RATE DESIGN .................................................. ............................... 10 CurrentRate Structure .......................................................... .............................10 Proposed Rate Structure ........................................................ .............................10 Current and Proposed Customer Bill Comparisons ................... .............................12 Comparison with Neighboring agencies .................................. .............................13 5. RECYCLED WATER PROJECTED REVENUE INCREASES .............................. 15 Revenue Requirements .......................................................... .............................15 Operating Expenses ......................................................... .............................15 Purchased Recycled Water ................................................ .............................15 Pump Station Operating and Maintenance ......................... .............................15 Depreciation.................................................................... .............................16 6. RECYCLED WATER RATE DESIGN ................................ ............................... 17 Current Rate Structure .......................................................... .............................17 Proposed Rate Structure ........................................................ .............................17 SS3 -12 CustomerBill Comparisons .................................................... .............................20 APPENDIX A. SEWER AND RECYCLED WATER RATE MODEL TABLE OF FIGURES Figure 1 -1. Current and Proposed Sewer Rates ............................. ..............................2 Figure 1 -2. Average Current and Proposed Monthly Sewer Bills ...... ..............................2 EDU Figure 1 -3. Current and Proposed Recycled Water Rates ............... ..............................3 Figure 3 -1. Annual Revenue Requirement Components ................ ..............................6 EMU Figure 3 -2. Capital Projects ......................................................... ..............................7 FY Figure 3 -3. Projected Revenue Increases ..................................... ..............................8 GPD Figure 3 -4. Fund Balance With and Without Rate Increases .......... ..............................9 HCF or CCF Figure 4 -1. Fixed and Variable Revenue ....................................... .............................10 Figure 4 -2. Calculation of Monthly Fixed Charges ......................... .............................11 I &I Figure 4 -3. Calculation of Sewer Consumption Charge .................. .............................11 Figure 4 -4. Five Year Sewer Rate Projections ............................... .............................12 O &M Figure 4 -5. Customer Bill Comparison .......................................... .............................13 OCSD Figure 4 -6. Neighboring Agency Comparison ................................ .............................14 OCWD Figure 5 -1. Revenue Requirement Projections .............................. .............................15 PAYGo Figure 6 -1. FY 2014 -15 Revenue Requirement by Cost Category ... .............................18 Figure 6 -2. Calculation of Monthly Fixed Charges ......................... .............................19 SFR Figure 6 -3. Calculation of Commodity and Pump Station Charges .. .............................19 Figure 6 -4. Five Year Recycled Water Rate Projections ................. .............................20 ACRONYMS CIP Capital Improvement Plan EDU Equivalent Dwelling Unit, an average single - family residential customer EMU Equivalent meter unit FY Fiscal Year GPD Gallons Per Day HCF or CCF Hundred Cubic Feet of metered water; 748 gallons; a cube of water 4.6 feet on edge I &I Inflow and Infiltration; stormwater runoff that enters collection systems through surface or subsurface connections, cracks, or other openings O &M Operations and Maintenance OCSD Orange County Sanitation District OCWD Orange County Water District PAYGo Pay -As- You -Go, in reference to funding capital improvements from cash rather than from borrowed sources of revenue SFR Single Family Residential SS3 -13 ACKNOWLEDGEMENTS City Council Edward Selich, Mayor Diane Dixon, Mayor Pro Tem Kevin Muldoon, Council Member Tony Petros, Council Member Duffy Duffield, Council Member Scott Peotter, Council Member Keith Curry, Council Member City Finance Commission: Diane Dixon, Mayor Pro Tem Keith Curry, Council Member Tony Petros, Council Member Larry Tucker, Appointed Finance Commission Member City Staff George Murdoch, Utilities General Manager Dan Matusiewicz, Deputy Finance Director Rachell Wilfert, Management Assistant HF &H Consultants, LLC John Farnkopf, Sr. Vice President Sima Mostafaei, Senior Associate SS3 -14 SS3 -95 SEWER AND RECYCLED WATER RATE STUDY SS3 -16 This page intentionally left blank SS3 -97 1. EXECUTIVE SUMMARY This report summarizes the analysis of the City's sewer and recycled water rates. The analysis represents a collaborative effort of the City's Staff and consulting team. HF &H prepared the financial plan model using the City's FY 2015 -16 preliminary operating budget for sewer, and the FY 2014 -15 preliminary operating budget for recycled water. FINDINGS AND RECOMMMENDATIONS Sewer 1. Key Assumptions. Rates were set to generate revenue sufficient to fund the City's collection system expenses, local capital improvements funded from cash, and to maintain the City's reserves. 2. Revenue Projections. The revenue increases enable the City to address collection and pump station improvement projects that were identified in the City's Sewer Master Plan. These increases enable the City to ramp up PAYGo funding for capital projects over the next five years; by the fifth year, the rates will enable the City to fund $1,300,000 per year on a pay -as- you -go cash basis without issuing debt. 3. Rate Design. The City's current sewer customers pay the sum of the following: a fixed monthly sewer use charge that is the same for all customers and a commodity charge based on metered water use during the monthly period. In addition, for meters 2 -inch or larger, a $10.00 monthly surcharge is assessed, and for connections servicing two or more dwelling units on the same connection, a $2.00 per unit per month surcharge is assessed for any additional dwelling units. We recommend combining the two surcharges into the monthly use charge, and maintaining the commodity charge. Under the revised rate structure, customers will pay the sum of only two charges: a monthly sewer use charge, graduated based on the capacity of the connection, and the commodity charge. 4. Projected Rates. Figure 1 -1 shows the sewer rates that are needed to cover the projected revenue requirements, and compares the revised structure to the current structure. In the revised rate structure, the service charges were graduated using an EMU multiplier that was based on the ratio of $4.50 to $14.50 (the current rate ratio), the effect of which is to increase the service charges for the larger services. The revised rate structure maintains the consumption charge, but includes the larger meter and additional dwelling unit surcharges as part of the monthly sewer use charge. SS3 -18 Figure 1 -1. Current and Proposed Sewer Rates Current Revised Structure Structure FY 2015 -16 FY 2016 -17 FY 2017 -18 FY 2018 -19 FY 2019 -20 Monthly Sewer Use Charge 5/8" or 3/4" $4.50 $5.97 $7.34 $8.22 $8.79 $9.41 $9.88 P $4.50 $5.97 $7.34 $8.22 $8.79 $9.41 $9.88 1 1/2" $4.50 $6.56 $8.07 $9.04 $9.67 $10.35 $10.87 2" $14.50 $8.95 $11.01 $12.33 $13.19 $14.11 $14.82 2 1/2" $14.50 $9.54 $11.74 $13.15 $14.07 $15.05 $15.81 3" $14.50 $10.14 $12.47 $13.97 $14.95 $16.00 $16.79 4" $14.50 $11.93 $14.68 $16.44 $17.59 $18.82 $19.76 6' $14.50 $13.42 $16.51 $18.49 $19.78 $21.17 $22.23 8" $14.50 $14.91 $18.34 $20.55 $21.98 $23.52 $24.70 10" $14.50 $19.09 $23.48 $26.30 $28.14 $30.11 $31.61 Monthly Sewer Use Charge (Sewer Only Customers) Rate per Account $6.25 $9.99 $12.28 $13.76 $14.72 $15.75 $16.54 Consumption Charge Rate per HCF $0.35 $0.35 $0.43 $0.48 $0.52 $0.55 $0.58 Sewer Surcharges Multi Unit surcharge (per DU) $2.00 Note 1 Note I Note l Note 1 Note 1 Note 1 Note 1: The surcharge has been incorporated into the Monthly Sewer Use Charge under the revised structure. 5. Customer Bills. Figure 1 -2 shows an average monthly residential and non- residential bill at the current rates, and the average bills over the five year projection period. In addition to paying the monthly sewer use charge based on the size of the connection, each customer's monthly bill includes a consumption charge that is determined by multiplying the consumption charge times the average monthly residential flow of 11.49 HCF and non - residential flow of 595 HCF, respectively. 1-Igure 3 -z. Average current ana vroposea nnonmiy sewer Isms Monthly Meter Flow Current Size (HCF) Structure FY 2015 -16 FY 2016 -17 FY 2017 -18 FY 2018 -19 FY 2019 -20 Single Family Residential 518" 11.49 $8.52 $12.28 $13.76 $14.72 $15.75 $16.54 Non Residential 4" 595.00 $224.75 $270.82 $303.32 $324.55 $347.27 $364.64 Recycled Water 1. Key Assumptions. Rates were set to generate revenue sufficient to fund the City's recycled water system's operations and maintenance expense, the cost of SS3 -19 purchasing recycled water from OCWD, and capital replacement expense related to pump stations and meters. 2. Rate Design. The City's current recycled water customers pay the sum of two charges: a monthly fixed charge that is based on the size of the connection, and a commodity charge based on metered water use during the monthly period. The commodity charge is based on 80% of the potable water rate. We recommend unlinking the recycled water rate from the potable water rate and aligning the recycled fixed and commodity charges with the fixed costs and the cost of purchased water from OCWD, respectively. In addition to the fixed and commodity charges, pump station users will be charged a pump station charge based on the cost to operate and maintain the stations and convey recycled water. 3. Projected Rates. The rate projections are shown in Figure 1 -3. Figure 1 -3. Current and Proposed Recycled Water Rates Current FY 2014 -15 FY 2015 -16 FY 2016 -17 FY 2017 -IS FY 2018 -19 Monthly Service Charge 5/8" or 3/4" $13.82 $18.91 $19.29 $19.68 $20.07 $20.47 1" $23.03 $31.53 $32.16 $32.80 $33.46 $34.13 1 1/2" $46.06 $63.05 $64.32 $65.60 $66.91 $68.25 2" $73.70 $100.88 $102.90 $104.95 $107.05 $109.19 3" $138.18 $189.15 $192.94 $196.80 $200.73 $204.75 4" $230.30 $315.25 $321.56 $327.99 $334.55 $341.24 6" $460.61 $630.50 $643.11 $655.98 $669.10 $682.48 8" $736.98 $1,008.81 $1,028.99 $1,049.57 $1,070.56 $1,091.97 Monthly Commodity Charge Rate per HCF $2.46 $0.86 $0.87 $0.89 $0.91 $0.93 Monthly Pump Station Charge Rate per HCF none $0.36 $0.37 $0.38 $0.38 $0.39 SS3 -20 2. INTRODUCTION STUDY PURPOSE The purpose of this study is to update the City's rates to ensure that they generate sufficient revenue and that the rate structures for sewer and recycled water reflect the City's current rate - making objectives. The study was commissioned by the City to evaluate the effect of certain rate structure modifications in response to input from its customers. RATE MAKING OBJECTIVES The City's current rate - making objectives include the following: • Provide revenue sufficiency and financial stability to cover the projected capital and O &M costs of providing recycled water and funding the City's Sewer fund. • Meet the City's operations and capital funds reserve targets for the sewer enterprise fund. • Rates should reflect equity of costs in proportion to the level of service. • Provide for efficient administration and execution of utility billing. • Minimize "rate shock" overall and to any specific customer class. • Rates should be clear and understandable to the customers. • The rates must comply with Proposition 218 and applicable State codes. BACKGROUND Sewer The City provides sewer service to approximately 64,465 customers. The City's existing sewer collection system consists of a network of forcemain and gravity sewers. This system is composed of approximately 197 miles of mainline gravity pipes, 4.7 miles of forcemains with 4,922 manholes and cleanouts, and 25,525 sewer laterals with an approximate length of 121 miles in the public- rights -of -way. The City's service area lies within the OCSD who is responsible for treating the City's sewer. The City also owns and operates 21 pump stations in various areas which lift sewer from the lower areas and several island communities for treatment at OCSD's treatment plant. Recycled Water The City currently has five recycled water customers totaling 14 water connections. The customers include Big Canyon and Newport Beach Country Club golf courses; East Bluff School, Our Lady Queen of Angels School, and the City which uses recycled water for irrigation of medians and parks. In 1991, the City entered into an agreement with OCWD for the distribution and sale of Green Acres Project water. The agreement stipulates the rules and regulations for the SS3 -21 City to provide recycled water. Included in this agreement is the stipulation that recycled water rates may not exceed 80% of the potable water rate. The agreement term is for 25 years with five 5 -year automatic extensions, with an estimated ending term year of 2041. The City subsequently entered into "End User Agreements' for the sale of recycled water to large customers in 1996 for a 10 -year term. These agreements, now expired, included provisions that OCWD and the City would provide funding to modify golf courses and construct pump stations to facilitate the use of recycled water. However, in 2011, the City and the Big Canyon Country Club entered into an agreement that provided for the delivery and sale of recycled water, and a pump station license agreement. SS3 -22 3. SEWER PROJECTED REVENUE INCREASES REVENUE REQUIREMENTS Rate analysis begins by determining the revenue requirements that must be met by rates. For purposes of this study, a ten -year rate projection period was developed using a spreadsheet model (see Appendix A). However, only the first five years are shown in Figure 3 -1 for rate - setting purposes. Figure 3 -1 summarizes the major categories comprised in the revenue requirements, indicating the annual change. Haure 3 -1. Annual Revenue Reauirement Components Salaries This cost category includes regular and overtime pay and is projected to increase gradually at about 3% per year during the projection period. No staff headcount increases are anticipated; the cost trend is driven primarily by cost of living adjustments set in labor agreements. Benefits This cost category includes health, dental, and vision as well as Other Post - Employment (OPEB) and Public Employment (PERS) retirement benefits. During the projection period these costs are projected to increase at about 5% per year. The cost trend is driven primarily by increases in health care benefit costs set in labor agreements. Operations & Maintenance This cost category includes non - personnel related operating and maintenance expenses, such as electrical utility costs, fuel, and non - capital materials and equipment. During the projection period, these costs are expected to increase gradually at about 1.73% per year, based on the five -year historical average of inflation for the Los Angeles area. SS3 -23 FY 2015 -16 FY 2016 -17 FY 2017 -18 FY 2018 -19 FY 2019 -20 Salaries $ 947,547 $ 975,973 $1,005,253 $1,035,410 $1,066,472 Benefits 575,693 604,478 622,612 641,290 660,529 Operations & Maintenance 995,721 989,549 1,006,668 1,024,084 1,041,800 Internal Services Allocation 670,581 682,182 693,984 705,990 718,203 Operating Reserve Expense 37,497 242,152 214,690 456,257 224,189 Capital Reserve Expense 500,000 750,000 1,000,000 1,000,000 1,300,000 Miscellaneous Costs 33,000 33,571 34,152 34,743 35,344 Total Revenue Requirement $ 3,760,039 $4,277,905 $4,577,358 $4,897,773 $5,046,538 Salaries This cost category includes regular and overtime pay and is projected to increase gradually at about 3% per year during the projection period. No staff headcount increases are anticipated; the cost trend is driven primarily by cost of living adjustments set in labor agreements. Benefits This cost category includes health, dental, and vision as well as Other Post - Employment (OPEB) and Public Employment (PERS) retirement benefits. During the projection period these costs are projected to increase at about 5% per year. The cost trend is driven primarily by increases in health care benefit costs set in labor agreements. Operations & Maintenance This cost category includes non - personnel related operating and maintenance expenses, such as electrical utility costs, fuel, and non - capital materials and equipment. During the projection period, these costs are expected to increase gradually at about 1.73% per year, based on the five -year historical average of inflation for the Los Angeles area. SS3 -23 Internal Services Allocation The City has historically transferred funds from the Sewer Enterprise Fund to the General Fund as reimbursement for governmental costs incurred by the General Fund on behalf of the Enterprise. Much of this funding reimburses the General Fund for salaries, equipment, and program costs associated with general services. During the projection period, these costs are expected to increase gradually at about 1.73% per year, based on the five -year historical average of inflation for the Los Angeles area. Operatino Reserve Expense The City transfers rate revenue to its Operating Reserve during the projection period to smooth out the annual revenue requirements and meet the minimum fund balance requirement. Please refer to the section titled 'minimum fund balance' in this report for further discussion of the fund policy. Capital Reserve Expense The City's 30 -year capital improvement program planned expenditures are summarized in Figure 3 -2. Figure 3 -2. Capital Projects The City plans to fund these capital improvements with cash from rate revenue. To accomplish this goal, the program is phased based upon the implementation cost of the facilities, and the quantity of work the City can reasonably administer each year. The programmed rate increases over the next five years allow the City to ramp up funding for capital projects and provide the City approximately $1.3 million annually by FY 2019 -20 with the additional revenue generated from the recommended rate increases. Miscellaneous Costs This cost category includes non - capital office and shop equipment. During the projection period, these costs are expected to increase gradually at about 1.73% per year, based on the five -year historical average of inflation for the Los Angeles area. REVENUE INCREASES To determine how much additional rate revenue is required, the projected revenue requirements are compared to the revenue from current rates. The revenue from SS3 -24 Project CIP Project Description Cost Collection System Capacity Improvements $1281391 Collection System Condition Improvements $16,648,060 Pump Station Improvements $11,088,000 Total $29,017,451 The City plans to fund these capital improvements with cash from rate revenue. To accomplish this goal, the program is phased based upon the implementation cost of the facilities, and the quantity of work the City can reasonably administer each year. The programmed rate increases over the next five years allow the City to ramp up funding for capital projects and provide the City approximately $1.3 million annually by FY 2019 -20 with the additional revenue generated from the recommended rate increases. Miscellaneous Costs This cost category includes non - capital office and shop equipment. During the projection period, these costs are expected to increase gradually at about 1.73% per year, based on the five -year historical average of inflation for the Los Angeles area. REVENUE INCREASES To determine how much additional rate revenue is required, the projected revenue requirements are compared to the revenue from current rates. The revenue from SS3 -24 current rates also reflects the impact of reduced water demand required of the City's customers to comply with the State Water Resources Control Board's emergency regulations. For the City's consumption charges, sewer flows from individual City customers are not metered; therefore water use data is the closest representation of flows that customers discharge to the City's system for conveyance and treatment. Estimating current rate revenue took into account 23,104 currently active meters whose flow equaled 3,932,915 HCF. We also included the annual surcharge revenue for meters 2" or larger, as well as the surcharge for multiple dwelling units serviced by the same meter. The resulting rate revenue for FY 2014 -15, prior to rate increases, but net of 0.4% of bad debt, was estimated at $3,105,332. Based on this estimate, annual revenue increases were projected as shown in Figure 3 -3. ure a -a. rrolecieu mevenue increases FY 2015 -16 FY 2016 -17 FY 2017 -18 FY 2018 -19 FY 201 Revenue Requirement $3,760,039 $4,277,905 $4,577,358 $4,897,773 $5,046,538 Revenue from Current Rates" 3,105,332 3,105,332 3,105,332 3,105,332 3,105,332 Difference (654,707) (1,172,574) (1,472,027) (1,792,442) (1,941,206) Fund Balance (before increase) 1,259,566 320,046 (972,663) (2,363,872) (4,180,01 Revenue from Increases 654,707 1,172,573 1,472,027 1,792,442 1,941,206 Fund Balance (after increase) 1,916,729 2,159,108 2,350,244 2,764,401 2,902,600 revenue based on conservation efforts FUND BALANCE revenue The FY 2014 -15 estimated year -end fund balance is projected to be $1,865,000, which is slightly higher than the minimum operations balance of $1,423,000. Figure 3-4 shows the fund climbing toward the target balance throughout the five year rate projection period, based on the projected revenue increases. Fluctuations in annual flow will affect revenue generation and the resulting fund balance. The City is advised to carefully monitor the fund balance in the event of downward fluctuations in flow. SS3 -25 Figure 3 -4. Fund Balance With and Without Rate Increases Minimum Fund Balance The minimum balance (red line) is the balance tNt is required to meet the City's operating expenses during the year. If this minimu balance were maintained, the Sewer Fund should be able to fund its monthly cash f%w over this extended period without relying on the General Fund for a short -term loan. When the Operations Reserve balance is below the minimum balance, the likelihood% increases that temporary funding from the General Fund will be required to meet casl�,flow needs. The City's reserve policy dictates that the minimum Operations Reserve balance be set equal to 50% of annual O &M expenses. Target Fund Balance The proposed revenue increases move the fund balance (solid grek line) upward toward the target balance (blue line). The target balance is the sum o?,,the minimum balance for operations (red line) plus an allowance for capital projects. A's allowance provides liquidity to fund construction for projects on a pay -as- you -go Yap is. With adequate capital reserves, the City is able to pay construction contractors without encroaching on the Operations Reserve. The allowance is based on the average annual budgeted capital improvement projects. SS3 -26 Target R,I, --e $3.50 (Operations + Capital) $3.00 w c 0 $2.50 c 119s with Rate "m Increase A $2.00 m c $1.50 Balance o. Orn- (Operations) m o $1.00 `� $0.50 $0.00 FY 2014-15 FY 2015 -16 FY 2016 -17', FY 2017 -18 FY 2018 -19 FY 2019 -20 Minimum Fund Balance The minimum balance (red line) is the balance tNt is required to meet the City's operating expenses during the year. If this minimu balance were maintained, the Sewer Fund should be able to fund its monthly cash f%w over this extended period without relying on the General Fund for a short -term loan. When the Operations Reserve balance is below the minimum balance, the likelihood% increases that temporary funding from the General Fund will be required to meet casl�,flow needs. The City's reserve policy dictates that the minimum Operations Reserve balance be set equal to 50% of annual O &M expenses. Target Fund Balance The proposed revenue increases move the fund balance (solid grek line) upward toward the target balance (blue line). The target balance is the sum o?,,the minimum balance for operations (red line) plus an allowance for capital projects. A's allowance provides liquidity to fund construction for projects on a pay -as- you -go Yap is. With adequate capital reserves, the City is able to pay construction contractors without encroaching on the Operations Reserve. The allowance is based on the average annual budgeted capital improvement projects. SS3 -26 4. SEWER RATE DESIGN CURRENT RATE STRUCTURE The City currently has 23,104 active accounts who pay the sum of two charges every month for Sewer service: a basic service charge of $4.50 per account plus a sewer consumption charge of $0.35 per HCF based on metered water use during the billing period. In addition to the charges specified above, customers with a water service connection of 2 "or greater pay a $10.00 monthly surcharge. Moreover, customers with more than one dwelling unit that is serviced by the same connection pay a surcharge of $2.00 for each additional dwelling unit. Lastly, the City's 485 sewer customers who do not purchase potable water from the City are charged $6.25 per account per month. PROPOSED RATE STRUCTURE The proposed rate structure is based on the revenue generated by the current rate structure and categorizes the revenue into two categories: fixed revenue and variable revenue. Fixed revenue is considered fixed because it does not vary based on flow, while variable costs vary because they are based on the amount of water purchased, or sewage produced and therefore, are solely comprised of the sewer consumption charge. For the purpose of rate design, the sewer use charge for customers who do not purchase water from the City was analyzed separately. Figure 4 -1 presents the breakdown of the current revenue by revenue category: Current Revenue xed Revenue Sewer Use Charge (per account) $1,247,616 Surcharge (2" meters or greater) $78,720 Surcharge (per additional DU) $378,492 rtal Annual Fixed Revenue $1,704,828 Variable Revenue Consumption Charge (per HCF) $1,376,520 Total Annual Variable Revenue $1,376,520 Subtotal $3,081,348 Sewer Use Charge (per account)* $36,375 Grand Total ** $3,117,723 *Sewer Revenue from customers who do not purchase potable water from the City of Newport Beach * *Gross revenues; does not account for bad debt SS3 -27 In order to determine the monthly charge by size of connection, we first converted the number of active meters to equivalent meter units (EMU) as shown in Figure 4 -2. The EMU multiplier by meter size is the same multipliers used to determine the fixed charge by meter size for the current sewer rates; in other words, it is the ratio between $4.50 to $14.50, or 1 to 3.2. The monthly charge for an EMU of 1.00 is derived by dividing the total fixed revenue of $1,704,828 by the total number of EMUS, or 23,815. This quotient was then divided by 12 to convert from an annual charge of $71.59 to a monthly charge of $5.97. The service charges were then graduated using the EMU multipliers, the effect of which is to increase the service charges for the larger services. Note the total annual revenue of $1,704,828 from fixed charges in Figure 4 -2 is equal to the total annual fixed revenue presented in Figure 4 -1. Figure 4 -2. Calculation of Monthly Fixed Charges The sewer consumption charge was derived using the monthly meter readings in HCF for all customers. Figure 4 -3 presents the derivation of the proposed sewer consumption charges. -i ure 4 -s. uaicwauon or newer uonsumpuon i,nar E Current Usage Charge Cost Category Revenue (HCF) per HCF Revenue $1,376,520 3,932,915 $0.35 For sewer customers who do not purchase potable water from the City, and therefore, do not have a proxy for their sewer flows, an average flow per account was derived by using average water use per single family residential account. The 11.49 HCF average SS3 -28 Total Monthly Annual Total Active EMU Total Service Fixed Meter Size Accounts Multiplier EMUS Charge Revenue a b a *b c a *c *12 5/8" or 3/4" 15,357 1.00 15,357 $5.97 $1,099,342 1" 6,276 1.00 6276 $5.97 $449,272 1 1/2" 364 1.10 400 $6.56 $28,663 2" 886 1.50 1,329 $8.95 $95,137 21/2" 1 1.60 2 $9.54 $115 3" 34 1.70 58 $10.14 $4,138 4" 119 2.00 238 $11.93 $17,037 6" 54 2.25 122 $13.42 $8,698 8" 11 2.50 28 $1491 $1,969 10" 2 3.20 6 $19.09 $458 23,104 23,815 $1,704,828 The sewer consumption charge was derived using the monthly meter readings in HCF for all customers. Figure 4 -3 presents the derivation of the proposed sewer consumption charges. -i ure 4 -s. uaicwauon or newer uonsumpuon i,nar E Current Usage Charge Cost Category Revenue (HCF) per HCF Revenue $1,376,520 3,932,915 $0.35 For sewer customers who do not purchase potable water from the City, and therefore, do not have a proxy for their sewer flows, an average flow per account was derived by using average water use per single family residential account. The 11.49 HCF average SS3 -28 use was determined using customer billing data and dividing total single family consumption by the number of single family accounts. Next, using the revised rate structure, the $9.99 charge shown in Figure 4-4 represents the average single family bill per month. It was calculated as the monthly sewer use charge of $5.97 per account plus the product of the $0.35 consumption charge times 11.49 HCF. Using the fixed and variable rates as calculated in Figure 4 -2 and Figure 4 -3, a five -year rate plan was prepared based on the City's Sewer revenue requirements as presented in Figure 3 -1. The rates included in the 5 -year plan reflect annual rate increases starting in FY 2015 -16 to keep pace with the increase in the revenue requirements. The proposed 5- year rate plan is shown in Figure 4-4. Figure 4 -4. Five Year Sewer Rate Projections Note I: The surcharge has been incorporated into the Monthly Sewer Use Charge under the revised structure. CURRENT AND PROPOSED CUSTOMER BILL COMPARISONS Figure 4 -5 presents a comparison of monthly customer bills using the current rate structure and the recommended revised rate structure. The rates used to calculate the revised bills are the FY 2015 -16 charges presented in Figure 4 -4. It is notable that current customers who are subjected to the multiple dwelling $2.00 monthly surcharge will experience a decrease in their monthly bill. This occurs based on the revisions to the SS3 -29 Current Revised Structure Structure FY 2015 -16 FY 2016 -17 FY 2017 -18 FY 2018 -19 FY 2019 -20 Monthly Sewer Use Charge 5/8" or 3/4" $4.50 $5.97 $7.34 $8.22 $8.79 $9.41 $9.88 1" $4.50 $5.97 $7.34 $8.22 $8.79 $9.41 $9.88 11 /2" $4.50 $6.56 $8.07 $9.04 $9.67 $10.35 $10.87 2" $14.50 $8.95 $11.01 $12.33 $13.19 $14.11 $14.82 2 1 /2" $14.50 $9.54 $11.74 $13.15 $14.07 $15.05 $15.81 3" $14.50 $10.14 $12.47 $1197 $14.95 $16.00 $16.79 4" $14.50 $11.93 $14.68 $16.44 $17.59 $18.82 $19.76 6" $14.50 $13.42 $16.51 $18.49 $19.78 $21.17 $22.23 8" $14.50 $14.91 $18.34 $20.55 $21.98 $23.52 $24.70 10" $14.50 $19.09 $23.48 $26.30 $28.14 $30.11 $31.61 Monthly Sewer Use Charge (Sewer Only Customers) Rate per Account $6.25 $9.99 $12.28 $13.76 $14.72 $15.75 $16.54 Consumption Charge Rate per HCF $0.35 $0.35 $0.43 $0.48 $0.52 $0.55 $nSs Sewer Surcharges Multi Unit surcharge (per DU) $2.00 Note 1 Note 1 Note 1 Note 1 Note 1 Notc 1 Note I: The surcharge has been incorporated into the Monthly Sewer Use Charge under the revised structure. CURRENT AND PROPOSED CUSTOMER BILL COMPARISONS Figure 4 -5 presents a comparison of monthly customer bills using the current rate structure and the recommended revised rate structure. The rates used to calculate the revised bills are the FY 2015 -16 charges presented in Figure 4 -4. It is notable that current customers who are subjected to the multiple dwelling $2.00 monthly surcharge will experience a decrease in their monthly bill. This occurs based on the revisions to the SS3 -29 monthly sewer use charge. The graduated rates, based on meter capacity, better reflect associated flow assumed per dwelling unit, and its equivalent. Figure 4 -5. Customer Bill Comparison COMPARISON WITH NEIGHBORING AGENCIES Based on available sources, Figure 4 -6 shows the recent charges for sewer service among similar Orange County agencies, specifically ones that charge a fixed monthly use charge coupled with a flow -based commodity charge. Larger agencies tend to have lower rates because they can take advantage of economies of scale and have a larger base of customers over which to distribute fixed costs. Figure 4-6 indicates that the City's current and proposed sewer rates track the trend line along with its neighbors (identified with red diamonds in Figure 4 -6). SS3 -30 Number of Average Current FY 15 -16 Dwelling Monthly Monthly Monthly Difference Customer Name Meter Size Units Flow(11CF) Bill Bill ($) Single Family Residential (low flow) 5/8"-1" 1 2 $ 5.20 $ 8.20 $3.00 Single Family Residential (avg flow) 5/8"-V 1 11 $ 8.35 $ 12.07 $3.72 Single Family Residential (high flow; 5/8"-V 1 16 $ 10.10 $ 14.23 $4.13 Multi Family Residential 3" 55 243 $ 209.55 $ 117.09 ($92.46) Commercial 4" 1 595 $ 224.75 $ 270.82 $46.07 Commercial 8" 141 2,074 $ 1,022.40 $ 911.20 ($111.20) Commercial 6" 1 1,584 $ 568.90 $ 698.42 $129.52 COMPARISON WITH NEIGHBORING AGENCIES Based on available sources, Figure 4 -6 shows the recent charges for sewer service among similar Orange County agencies, specifically ones that charge a fixed monthly use charge coupled with a flow -based commodity charge. Larger agencies tend to have lower rates because they can take advantage of economies of scale and have a larger base of customers over which to distribute fixed costs. Figure 4-6 indicates that the City's current and proposed sewer rates track the trend line along with its neighbors (identified with red diamonds in Figure 4 -6). SS3 -30 Fioure 4 -6. Neiohborino Aoencv Comparison $35 Irvine Ranch WD $30 $25 31 $20 i r e Buena Park Seal Beach ■ $15 ar rove Newport Beach - Proposed � �ntinglon Beach $10 ■ $5 La Habra ■ Fullerton Cosa Mesa SD $0 0 50,000 100,000 150,000 200,000 250,000 300,000 350,000 400,000 Population of Service Area SS3 -37 Cosa Mesa SD SS3 -37 S. RECYCLED WATER PROJECTED REVENUE INCREASES REVENUE REQUIREMENTS The City's FY 2013 -14 revenue requirement served as the basis for determining the revenue requirement projections through FY 2018 -19. Figure 5 -1 summarizes the sources and assumptions for the data as well as the projected expenditure trends: Figure 5 -1. Revenue Requirement Projections Operatina Expenses This cost category includes administration and overhead expenses that are calculated as 10% of the total recycled water revenue requirement and 1% of the budgeted general fund overhead charged to the water fund, respectively. During the projection period, the City's operating expenses are projected to increase gradually at about 1.73% per year, based on the five -year historical average of general inflation for the Los Angeles area. Purchased Recycled Water This cost category for FY 13 -14 was based on the actual water purchases in FY 12 -13 multiplied by the cost of purchased water from OCWD of $360 per acre foot. During the projection period, the City's purchased water costs are projected to increase gradually at about 1.88% per year, based on the five -year historical average of OCWD purchased water charges per acre foot. Pump Station Operating and Maintenance This cost category for FY 13 -14 was based on the actual cost of inspections, scheduled and corrective maintenance, source changeovers and pump station rehabilitation and maintenance as provided by the city. During the projection period, the City's pump station operating and maintenance costs are expected to increase gradually at about 1.73% per year, based on the five -year historical average of general inflation for the Los Angeles area. SS3 -32 FY 13 -14 FY 14 -15 FY 15 -16 FY 16 -17 FY 17 -18 FY 18 -19 Operating Costs $ 40,488 $ 41,188 $ 41,901 $ 42,626 $ 43,363 $ 44,114 Purchased Recycled Water 167,598 173,417 179,438 182,810 186,245 189,745 Pump Station Operating & Maintenance 39,408 47,218 48,104 49,007 49,927 50,864 Depreciation 17,500 17,543 17,587 17,632 17,678 17,724 Total Revenue Requirement $ 264,994 $ 279,366 $287,030 $ 292,075 $ 297,213 $ 302,446 Annual Change 5% 3% 2% 2% 2% Operatina Expenses This cost category includes administration and overhead expenses that are calculated as 10% of the total recycled water revenue requirement and 1% of the budgeted general fund overhead charged to the water fund, respectively. During the projection period, the City's operating expenses are projected to increase gradually at about 1.73% per year, based on the five -year historical average of general inflation for the Los Angeles area. Purchased Recycled Water This cost category for FY 13 -14 was based on the actual water purchases in FY 12 -13 multiplied by the cost of purchased water from OCWD of $360 per acre foot. During the projection period, the City's purchased water costs are projected to increase gradually at about 1.88% per year, based on the five -year historical average of OCWD purchased water charges per acre foot. Pump Station Operating and Maintenance This cost category for FY 13 -14 was based on the actual cost of inspections, scheduled and corrective maintenance, source changeovers and pump station rehabilitation and maintenance as provided by the city. During the projection period, the City's pump station operating and maintenance costs are expected to increase gradually at about 1.73% per year, based on the five -year historical average of general inflation for the Los Angeles area. SS3 -32 Depreciation This cost category includes replacement costs for pump station facilities and water meters. The annual pump station facility replacement cost was based on $600,000 in construction costs, amortized over 40 years. The annual meter replacement cost was based on the American Water Works Association's standard cost of $259 per meter per year, amortized over 15 years. During the projection period, the City's pump station facility replacement costs are held constant at $15,000 per year, while the meter replacement costs are projected to increase gradually at about 1.73% per year, based on the five -year historical average of inflation for the Los Angeles area. r SS3 -33 6. RECYCLED WATER RATE DESIGN The following section was previously submitted as a separate report dated April 24, 2014. The City Council subsequently adopted the recommended rates in compliance with Proposition 218, effective October 9, 2014. The following text summarizes the rates documented in the April 2014 report and subsequently adopted by the City Council. CURRENT RATE STRUCTURE The City currently has five recycled water customers totaling 14 connections. These customers pay the sum of two charges every month for water service: a basic service charge based on the size of the service connection plus a commodity charge based on metered water use during the billing period. In 1991, the City entered into an agreement with OCWD for the distribution and sale of recycled water. The agreement stipulated that the recycled water rate may not exceed 80% of the potable water rate. It is the City's current practice to charge customers 80% of the potable water rate based on that agreement. PROPOSED RATE STRUCTURE Under the new rate structure, the recycled water rates will no longer be linked to 80% of the potable water rates. The proposed rate structure is based on the FY 2014 -15 revenue requirement, and categorizes the expenses into three categories: fixed costs, variable costs and pump station - related costs. Fixed costs are considered fixed because they do not vary based on flow, and include the annual cost of meter reading and replacement, as well as administrative and overhead. Variable costs vary because they are based on the amount of water purchased, and therefore, are solely comprised of the annual cost of purchased water from OCWD. Pump station - related costs are comprised of inspections, maintenance, and rehabilitation & replacement that are directly related to the pump stations. Figure 6 -1 presents the breakdown of the FY 2014 -15 revenue requirement by cost category: SS3 -34 ure 6 -1. FY 2014 -15 Revenue Requirement by Cost i FY2014 -15 xed Costs Administration $25,433 Overhead $12,208 Meter Reading $1,514 Meter replacement $2,543 Other agency fees $2,035 )tal Fixed Costs $43,73- Variable Costs Purchased Water $173,417 Total Variable Costs $173,417 Station Costs Inspections $7,021 Maintenance $13,109 Rehab & Replacement $42,087 >talPump Station Costs $62,218 Total Revenue Requirement $279,366 In order to determine the monthly charge by size of connection, we first converted the number of active meters to equivalent meter units (EMU) as shown in Figure 3 -2. The EMU multiplier by meter size is the same multipliers used to determine the fixed charge by meter size for potable water rates. The monthly charge for an EMU of 1.00 is derived by dividing the total fixed costs of $43,732 by the total number of EMUs or 192.70. This quotient was then divided by 12 to convert from an annual charge of $226.94 to a monthly charge of $18.91. The service charges were then graduated using the EMU multipliers, the effect of which is to increase the service charges for the larger services. Note the total annual revenue of $43.732 from fixed charges in Figure 6 -2 is equal to the total fixed costs presented in Figure 6 -1. SS3 -35 Fiaure 6 -2. Calculation of Monthly Fixed Charaes The commodity and pump station charges were derived using the FY 2012 -13 monthly meter readings in HCF for all customers, and FY 2012 -13 monthly meter readings for pump station customers in HCF, respectively. Figure 6 -3 presents the derivation of the proposed commodity and pump station charges for FY 2014 -15: Figure 6-3. Calculation of Commoditv and Pump Station C Total FY14 -15 FY14 -15 Monthly FY 14 -15 Cost Category Costs Active EMU Total Service Annual Meter Size Accounts Multiplier EMUs Charge Revenue a b a *b c a *c *12 5/8" or 3/4" 0 1.00 0 $18.91 $0 1" 0 1.67 0 $31.53 $0 11/2" 0 3.33 0 $63.05 $0 2" 8 5.33 42.67 $100.88 $9,684 3" 3 10.00 30.01 $189.15 $6,810 4" 0 16.67 0 $315.25 $0 6" 2 33.34 66.68 $630.50 $15,132 8" 1 53.34 53.34 $1,008.81 $12,106 14 192.70 $43,732 The commodity and pump station charges were derived using the FY 2012 -13 monthly meter readings in HCF for all customers, and FY 2012 -13 monthly meter readings for pump station customers in HCF, respectively. Figure 6 -3 presents the derivation of the proposed commodity and pump station charges for FY 2014 -15: Figure 6-3. Calculation of Commoditv and Pump Station C :harges Using the FY 2014 -15 rates as calculated in Figure 6 -2 and Figure 6 -3, a five -year rate plan was prepared based on the City's recycled water revenue requirements as presented in Figure 5 -1. The rates included in the five -year plan reflect 2% annual rate increases across the board starting in Year 2 to keep pace with the increase in the revenue requirements. The proposed five -year rate plan is shown in Figure 6-4. SS3 -36 FY12 -13 FY14 -15 FY14 -15 Usage Charge Cost Category Costs (HCF) per HCF Variable Costs $173,417 202,793 $0.86 Pump Station Costs $62,218 172,426 $0.36 :harges Using the FY 2014 -15 rates as calculated in Figure 6 -2 and Figure 6 -3, a five -year rate plan was prepared based on the City's recycled water revenue requirements as presented in Figure 5 -1. The rates included in the five -year plan reflect 2% annual rate increases across the board starting in Year 2 to keep pace with the increase in the revenue requirements. The proposed five -year rate plan is shown in Figure 6-4. SS3 -36 Fioure 6 -4. Five Year Recvcled Water Rate Proiections Current FY 14 -15 FY 15 -16 FY 16 -17 FY 17 -18 FY 18 -19 Annual Rate Increases 2% 2% 2% 2% Monthly Service Charge 5/8" or 3/4" $13.82 $18.91 $19.29 $19.68 $20.07 $20.47 1" $23.03 $31.53 $32.16 $32.80 $33.46 $34.13 1 1/2" $46.06 $63.05 $64.32 $65.60 $66.91 $68.25 2" $73.70 $100.88 $102.90 $104.95 $107.05 $109.19 3" $138.18 $189.15 $192.94 $196.80 $200.73 $204.75 4" $230.30 $315.25 $321.56 $327.99 $334.55 $341.24 6" $460.61 $630.50 $643.11 $655.98 $669.10 $682.48 8" $736.98 $1,008.81 $1,028.99 $1,049.57 $1,070.56 $1,091.97 Monthly Commodity Charge Rate per HCF $2.46 $0.86 $0.87 $0.89 $0.91 $0.93 Monthly Pump Station Charge Rate per HCF none $0.36 $0.37 $0.38 $0.38 $0.39 CUSTOMER BILL COMPARISONS Figure 6 -5 presents a comparison of monthly customer bills using the current rate structure and the recommended revised rate structure. The rates used to calculate the revised bills are the Year 1 charges presented in Figure 64. It is notable that all current recycled water customers will experience no less than a 44% bill decrease with the recommended structure change. tourer Name vport Beach Country Club Lady Queen of Angels Canyon Country Club Canyon Country Club bluff School �izure o -5. customer nin kom Revised Monthly Difference Difference Bill Average ( %) $8,717 Monthly Current $230 Flow Monthly Meter Size (HCF) Bill 6" 6,650 $16,820 2" 151 $446 8" 5,256 $13,668 6" 2,463 $6,518 3" 321 $928 Revised Monthly Difference Difference Bill ($) ( %) $8,717 ($8,103) -48% $230 ($215) -48% $5,504 ($8,164) -60% $3,625 ($2,894) -440% $464 ($464) -50% SS3 -37 APPENDIX A. SEWER AND RECYLED WATER RATE MODEL SS3 -38 SS3 -39 SS3 -40 Al 8 I C I D I E I F F G H I I I J I K L I M I N 1 O City of Newport Beach Sewer Rate Study Table 1A, Summary _.L _.L 3 4 5 Projected 6 Fiscal Year.. FY 2015 -16 FY 2016 -17 FY 2017.18 FY 2018 -19 FY 2019 -20 FY 2020 -21 FY 2021 -22 FY 2022 -23 FY 2023 -24 FY 2024 -25 7 Revenue Increases Cumulative Increase - Sewer 23.0% 12.0% 7.0% 7.0% 5.0% 3.0% 23.0% 37.8% 47.4% 57.7% 65.6% 70.6% 3.0% 1.0% 1.0% 75.7% 77.4% 79.2% 1.0% 81.0% 8 10 11 Salaries & Benefits Operating Costs Miscellaneous Internal Service Allocation i r i FY 2020-21 $ 1,523,240 $ 1580,451 $ 1,627,865 $ 1,676,701 $ 1,727,002 $ 1,778,812 995,721 989,549 1,006,668 1,024,084 1,041,800 1,059,823 33,000 33,571 34,152 34,743 35,344 35,955 670,581 682,182 693,984 705,990 718,203 730,628 r i 2023-24 $ 1,832,176 $ 1887,141 $ 1,943,755 1,078,158 1,096,811 1,115,785 36,577 37,210 37,854 743,268 756,127 769,208 FY 2024-25 $ 2,002,068 1,135,088 38,508 782,515 12 13 14 15 16 Storm Drain Operating $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 17 Storm Drain Capital Sewer Operating Reserve Expense Sewer Capital Reserve Expense $0 $0 $0 $0 $0 $0 $37,497 $242,152 $214,690 $456,257 $224,189 $292,715 $500,000 $750,000 $1,000,000 $1,000,000 $1,300,000 $1,300,000 $0 $0 $0 $363,692 $330,122 $294,882 $1,300,000 $1,300,000 $1,300,000 $0 $257,919 $1,300,000 18 19 20 $ 3,760,039 $ 4,277,905 $ 4,577,358 $ 4,897,773 $ 5,046,538 $ 5,197,933 $ 5,353,871 $ 5,407,410 $ 5,461,484 $ 5,516,099 21 Annual increase 13.8% 7.0% 7.0% 3.0% 3.0% 3.0% 10% 1.0% 1.0% 22 23 24 zs Year End Fund Balances -Funds 530 and 540 26 $4.0 � 27 Reserves with Rate Target Balance Increase 28 79 30 $3.5 (Operations +Cap' 31 32 d c $3.0 O U 33 34 `♦ 35 36 � ♦♦ a$0.5 37 38 C $2.5 39 ♦ 40 � $2.0 m Re 41 42 inimum glance FV 2019 -20 FY 2020 -21 FV 2021 -22 43 44 00 �`♦ (Operations) 45 v C 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 Ti 62 63 64 65 fib SS3 -40 ♦x � LL d U `♦ N ♦♦ a$0.5 `1 Reserves without Rate ♦ Increase ♦ $0.0 FV 2014 -15 FV 2015 -16 FV 2016 -17 FV 2017 -18 FY 2018 -19 FV 2019 -20 FY 2020 -21 FV 2021 -22 FV 2022 -23 FV 2023 -24 FV 2024 -26 SS3 -40 SS3 -41 A I B C D E F G H I J K L M N 1 City of Newport Beach 2 Sewer Rate Study 3 Table 1B. General 5 For acted fi FY 2015 -16 FY 2016.17 FY 2017 -18 FY 2018 -19 FY 2019 -20 FY 2020 -21 FY 2021 -22 FY 2022 -23 FY 2023 -24 FY 2024 -25 Source Notes 7 Factors 8 a. Interest an Reserve Balance 0.75% 0.75% 0.75% 0.75% 0.75% 075% 0.75% 0.75% 0.75% 0.75% City Estimate To Table 4 9 b. General inflation Per Budget 1.73% 1.73% 1.73% 1.73% 1 ]3% 1.73% 1.73% 1.73% 1.73% US Statistics, LA Area &year average To Table 2 10 c. Personnel Increases Per Budget 3.0% 3.0% 30% 3.0 %. 3.0% 3.0% 30% 3.0% 30% Estimate To Table 11 d. Benefits cost increases Per Budget 5.0% 5.0% 5.0% 5.0% 5.0% 5.0% 5.0% 5.0% 5.0% Estimate To Table 12 e. Percent of Bad Debt 0.4% 0.4% 0.4% 0.4% 0.4% 0.4% 0.4% 0.4% 0.4% 0.4% Based on City's Fund Worksheet To Table 3A,3B 13 L Utilities Increases Per Budget 1.73% 1.73% 1.73% 1.73% 1 ]3% 1.73% 1.73% 1.73% 1.73% 14 g. Pct. increase in Sewer Accounts 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% To Table 3A 15 h. Pct. increase in Water Consumption (for flaw charge) 2.00% 0.00% 0.00% 0.00% 0.00% 040% 0.00% 0.00% 000% 0.00% To Table 2,8 16 1. Percentage increase in Recycled Water Use 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% 0.00% To Table 2,3B 17 j. Construction cost inflation Per Budget 2.00% 200% 2,00% 2.00% 200% 2.00% 2.00% 2.00% 2.00% City Estimate To Table 2B, 5 18 k. Percent increase in purchased recycled water rate 1.58% 3.47% 1.88% 1.88% 1.88% 188% 1.88% 1.88% 1.88% 1.88% OCWD$ /AF 5 -year Average To Table 28 19 20 21 Reserve Policies 22 Operations Fund Purpose Working capital for 08M cash flow during the year. 23 24 Funding priority Highest. If not maintained, interfund loans are needed. 25 Minimum balance 50% of annual 01 is 26 27 Infrastructure Replacement Funds Purpose For wastewater master plan construction projects. 28 29 Funding priority Second highest. 30 Target balance No Minimum or Maximum. Should be reviewed periodically 31 32 Model Tables Included 33 Table 1A. Summary 34 Table 1B. General 35 Table 2A. Revenue Requirement Projection - Sewer 36 Table 2B. Revenue Requirement Projection- Recycled Water 37 Table 3A. Revenue Increases - Sewer 38 Table 3B. Revenue Increases- Recycled Water 39 Table 4. Reserves 40 Table S. CIP 41 Table 7A. Rate Revenue -Sewer 42 Table 7B. Rate Revenue - Recycled Water SS3 -41 SS3 -42 A B C D E F G H I J K L N o 1 City of Newport Beach 2 Sewer Rate Study 3 Table 2A. Revenue Requirement Projection -Sewer 4 5 Table l8 Budgeted Projected 6 Factors FY 201546 FY 2016 -17 FY 2017 -18 FY 2018 -19 FY 2019 -20 FY 2020 -21 FY 2021 -22 FY 202243 FY 2023 -24 FY 2024 -25 Notes 7 OPERATING EXPENSES 8 Salaries 7000 and Benefits SALARIES - MISC C. $ 861,812 $887,666 $914,296 $941,725 $969,977 $999,076 $1,029,049 .$1,059,920 $1,091,718 $1,124,469 9 10 7020 SALARIES - PART TIME tl. - $0 $0 $0 $0 $0 $0 $0 $0 $0 11 7040 OVERTIME, MISC & 1/2 TIME c. 45,000 $46,350 $47,741 $49,173 $50,648 $52,167 $53,732 $55,344 $57,005 $58,715 12 7062 NIGHT DIFF, MISC d. - $0 $0 $D $0 $0 $D $0 $0 $0 13 7063 CERTIFICATION PAY C. 5,735 $5,907 $6,084 $6,267 $6,455 $6,648 $6,848 $7,053 $7,265 $7,483 14 7080 CALL BACK PAY c. 35,000 $36,050 $37,132 $38,245 $39,393 $40,575 541,792 $43,046 $44,337 545,667 15 7114 CELL PHONE STIPEND EXP d. 6,421 $6,742 $6,944 $7,153 $7,367 $7,588 $7,816 $8,050 $8,292 $8,541 16 7210 HEALTH /DENTALIVISION tl. 240,625 $252,656 $260,236 $268,043 $276,084 $284,367 $292,898 $301,685 $310,735 $320,057 17 7223 ANNUAL OPEB COST d. 41,826 $43,917 $45,235 $46,592 $47,990 $49,429 $50,912 $52,440 $54,013 $55,633 18 7227 RHS$2.50 CONTRIB d. 7,350 $7,718 $7,949 $8,187 $8,433 $8,686 $8,947 $9,215 $9,492 $9,776 19 7290 LIFE INSURANCE d. 1,260 $1,323 $1,363 $1,404 $1,445 $1,489 $1,534 $1,580 $1,627 $1,676 20 7295 EMPASSISTANCE PROGRAM d. 292 $307 $316 $325 $335 $345 $355 $366 $377 $388 21 7370 WORKERS' COMP, MISC d. 27,356 $28,724 $29,586 $30,473 $31,387 .$32,329 $33,299 $36,298 $35,327 $36,386 22 7373 COMPENSATED ABSENCES J. 30,163 $31,671 $32,621 $33,600 $34,608 $35,646 $36.716 $37,817 $38,952 $40,120 23 7425 MEDICARE FRINGES d. 13,739 $14,426 $14,859 $15,304 $15,764 $16,237 $16,724 $17,225 $17,742 $18,274 24 7439 PIERS MISC EE CNTRBN d. 69,326 $72,792 $74,976 $77,225 $79,542 $81,928 $84,386 $86,918 $89,525 $92,211 25 7440 PERS MISC ER CNTRBN d. 70,255 $73,768 $75,981 $78,260 $80,608 $83,026 $85,517 $88,083 $90,725 $93,447 26 7445 EE RET CNTRBN MISC d. (107,277) (5112,641) ($116,020) ($119,501) ($123,088) ($128,778) ($130,582) ($134.499) ($138,534) ($142,690) 7 7446 PIERS UNFND LIAR MISC d. 174,357 $183,075 $188,567 $194,224 $200,051 $206,052 $212,234 $218,601 $225,159 $231,914 28 Total Salaries and Benefits 1,523,240 1,580,451 1,627,865 1,676,701 1,727,002 1,778,812 1,832,176 1,887,141 1,943,755 2,002,068 29 38% 30% 30% 3D% 3.0% 3.0% 30% 30% 3.0% 30 Ooeratine 8003 Costs GENRATR MAINT&REPR b. $ 17,500 $17,803 $1 8,111 $18,424 $18,743 $19,067 $19,397 $19,732 $20,074 $20,421 31 32 8004 CERT & MEMBERSHIP b. 5,500 $5,595 $5,692 $5,790 $5,891 $5,992 $6,096 $6,202 $6,309 $6,418 33 8D20 AUTOMOTIVE SERVICE b. 45,000 $45,779 $46,570 $47,376 $48,196 $49,030 $49,878 $50,741 $51,618 $52,511 34 8030 MAINT & REPAIR - EQUIP b. 4,000 $4,069 $4,140 $4,211 $4,284 $4,358 $4,434 $4,510 $4,588 $4,668 35 8040 MAINT& REPAIR - BUILDING b. 4,662 $4,743 $4,825 $4,908 54,993 $5,079 $5,167 $5,257 $5,348 $5,440 36 8060 PUBLICATIONS & DUES NOC b. 1,000 $1,017 $1,035 $1,053 $1,071 $1,090 $1,108 $1,128 $1,147 $1,167 37 8070 RENTAVPROP & EQUIP NOC b. 1,000 $1,017 $1,035 $1,053 $1,071 $1,090 $1,108 $1,128 $1,147 $1,167 38 8080 SERVICES -PROF & TECH NOC b. 31,084 $31,622 $32,169 $32,725 $33,291 $33,867 $34,453 $35,049 $35,656 $36,273 39 8100 TRAVEL & MEETINGS NOC b. 1,000 $1,017 $1,035 $1,053 $1,071 $1,090 $1,108 $1,128 $1,147 $1,167 40 8105 TRAINING b. 9,250 $9,420 $9,583 $9,749 $9,91B $10,089 $10,254 $10,441 $10,622 $10,806 41 8112 UTILITIES - TELEPHONE f. 8,700 $8,851 $9.004 $9,159 $9,318 $9,479 $9,643 $9,610 $9,980 $10,152 42 8114 UTILITIES - NATURAL GAS f. 1,000 $1,017 $1,035 $1,053 $1,071 $1,090 $1,108 $1,128 $1,147 $1,167 43 8116 UTILITIES - ELECTRICITY f. 68,000 $69,176 $70,373 $71,591 $72,829 $74,089 $75,371 $76,675 $7B4O01 $79,351 44 8118 UTILITIES - WATER f. 20,000 $20,346 $20,698 $21,056 $21,420 $21,791 $22,168 $22,551 $22,942 $23,338 45 8140 SUPPLIES - OFFICE NOC b. 350 $356 $362 $368 $375 $381 $388 $395 $401 $408 46 8155 WASTEWATER ROOT CUTTING b. 16,601 $16,888 $17,180 $17,478 $17,780 $18,088 $18,400 $18,719 $19.43 $19,372 47 8158 CCTV MAINTENANCE PROGRAM b. 67,036 $88,542 $90,073 $91,632 $93,217 $94,830 $96,470 $98,139 $99,837 $101,564 48 8159 GREASE CNTRL DEVIINSPEC b. 79,544 $80,920 $82,320 $83,744 $85,193 $86,667 $88,166 $89,691 $91,243 $92,822 49 8160 MAINT & REPAIR NOC b. 211,007 $214,657 $218,371 $222,149 $225,992 $229,902 $233,879 $237,925 $242,041 $246,228 50 8184 MAINT - SCADA b. 25,252 $25,689 $26,133 $26,585 $27,045 $27,513 $27,989 $28,473 $28,966 $2%467 51 8185 SEWER MANHOLE LINING PRGM b. 75,000 $76,298 $7/,617 $78,960 $80,326 $81,716 $83,130 $84,568 $86,031 $87,519 52 8186 PUMP STATION MAINTENANCE b. 13,000 $13,225 $13,454 $13,686 $13,923 $14,164 $14,409 $14,658 $14,912 $15,170 53 8187 ALLEY LATERAL REPL PRGM. b. 43,500 $44,253 $45,018 $45,797 $46,589 $47,395 $48,215 $49,049 $49,898 $50,761 54 8188 SEWER MANHOLE MINT PRGM b. 37,601 $38,251 $38,913 $39,586 $40,271 $40,968 $41,677 $42,398 $43,131 $43,877 55 8189 TREE ROOT FOAMING b. 85,000 $86.471 $87,966 $89,488 $91,036 $92,611 $94,214 $95,843 $97,501 $99,188 56 8197 UTILITIES FAC MAIN PROGM b. 20,375 $20,727 $21,086 $21,451 $21.822 $22,199 $22,584 $22,974 $23,372 $23,776 57 8200 SPECIAL DEPT SUPPLIES NOC b. 15,000 $15,260 $15,523 $15,792 $16,065 $16,343 $16,626 $16,914 $17,206 $17,504 58 8204 UNIFORM EXPENSE b. 5,000 $5,087 $5,174 $5,264 $5,355 $5,448 $5,542 $5,638 $5,735 $5,835 59 8239 CONCRETE MATERIALS b. 2,000 $2,035 $2,070 $2,106 $2,142 $2,179 $2,217 $2,255 $2,294 $2,334 60 8240 TOOLS, INSTRUMENTS, ETC b. 2,500 $2,543 $2,587 $2,632 $2,678 $2,724 $2,771 $2,819 $2,868 $2,917 61 8298 OTHER AGENCY FEES b. 30,000 $30,519 $31,047 $31,584 $32,130 $32,686 $33,252 $33,827 $34,412 $35,008 62 8310 SOFTWARE LICENSE RENEWAL b. 29,249 $29,755 $30,270 $30,793 $31,326 $31,868 $32,419 $32,980 $33,551 $34,131 63 Total Operating Casts 995,721 989,549 1,006,668 1,024,084 1,041,800 1,059,823 1,078,158 1,096,811 1,115,785 1,135,088 64 -06% 1.I% 1.7% 1.7% 1.7% 1.7T. 1.7% 1.7% 1.7% 65 Internal 8022 Service Allocations EQUIP MAINT ISF h. $ 144,204 $146,699 $149,237 $151,818 $154,445 $157,117 $159,835 $162,600 $165,413 $168,275 66 67 8024 VEHICLE REPLACE ISF b. 206,622 $210,197 $213,B33 $217,532 $221,296 $225,124 $229,019 $232,981 $237,011 $241,112 68 8318 IT ISF OPERATING CHARGE b. 68,252 $69,433 $70,634 $71,856 $73,099 $74,364 $75,650 $76,959 $78,290 $79,645 69 83191T ISF STRATEGIC CHARGE b. 17,874 $18,183 $18,498 $18,818 $19,143 $19,475 $19,811 $20,154 $20,503 $20,858 70 8330 SVC CHARGE- ADMINISTRATIVE b. 223,084 $226,943 $230,869 $234,864 $238,927 $243,060 $247,265 $251,543 $255,894 $260,321 71 8340 GENERAL INSURANCE b. 10,545 $10,727 $10,913 $11,102 $11,294 $11,489 $11,688 $11,890 $12,096 $12,305 72 Total ISF Allocation 670,581 682,182 693,984 705,990 718,203 730,628 743,268 756,127 769,208 782,515 SS3 -42 SS3 -43 Al B I C D I E I F I G I H I I I J I K I L I M I N 1 0 1 City of Newport Beach 2 Sewer Rate Study 3 Table 2A Revenue Requirement Projection -Sewer 4 5 Table I Budgeted Projected 6 Factors FY 2015 -16 FY 2016 -17 FY 2017 -18 FY 2018 -19 FY 2019 -20 FY 2020 -21 FY 2021 -22 FY 202243 FY 2023 -24 FY 2024 -25 Notes 73 Miscellaneous 9000 OFFICE EQUIPMENT b. 2,000 $2,035 $2,070 $2,106 $2,142 $2,179 $2,217 $2,255 $2,294 $2,334 74 75 9010 COMPUTER EQUIPMENT b. 5,000 $5,087 $5,174 $5264 $5,355 $5,448 $5,542 $5,638 $5,735 .$5,835 76 9200 SHOP EQUIPMENT b. 1,000 $1,017 $1,035 $1,053 $1,071 $1,090 $1,108 $1,128 $1,147 $1,167 77 9300 EQUIPMENT, N.O.C. b. 25,000 $25,433 $25,872 $26,320 $26,775 $27,239 $27,710 $28,189 $28,677 $29,173 78 Total Miscellaneous Expenses 33,000 33,571 34,152 34,743 35,344 35,955 36,577 37,210 37,854 38,508 ]9 80 Non -0Op.nd'na Revenue 5860 DAMAGE TO CITYPROPERTY b. $ - $0 $0 $0 $0 $0 $0 $0 $0 $0 81 82 5870 REVENUE, NO C. b. $0 $0 $0 $0 $0 $0 $0 $0 $0 83 Total Non - Operating Revenue 84 Net Revenue Requirement (before Reserve Expense) $ 3,222,542 S 3,285,753 $ 3,362,668 $ 3,441,516 $ 3,522,349 $ 3,605,218 $ 3,690,179 $ 3,777,288 S 3,866,602 $ 3,958,180 85 20% 23% 2.3% 2.3% 2.4% 24% 24% 24% 2.4% 66 RESERVE EXPENSE Tol(From) 87 Ops Support- Storm Orain Budget 88 Operations b. $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 Fmm Tads 1A 89 Capital Projects $0 $0 $0 $0 $0 $0 $0 $0 $0 $0 From T.W. to 90 Operating Reserve 37,497 242,152 214,690 456,257 224,189 292,715 363,692 330,122 294,882 257,919 Fmm T.a.4 91 Infrastructure Replacement 500,000 750,000 1,000,000 1,000,000 1,300,000 1,300,000 1,300,000 1,300,000 1,300,000 1,300,000 Fmm Taels4 92 Subtotal, Reserve Expense $ 537,497 $ 992,152 $ 1,214,690 $ 1,456,257 $ 1,524,189 $ 1,592,715 $ 1,663,692 $ 1,630,122 $ 1,594,882 $ 1,557,919 93 94 Net Revenue Requirement $3,760,039 $4,277,905 $4,577,358 $4,897,773 $5,046,538 $5,197,933 $5,353,871 $5,407,410 $5,461,484 $5,516,099 To T.ele an 95 tae% 70% 7 u 10% 3p% 3.0% 10% 10% fo% SS3 -43 Rate Study 2B. Revenue Requirement Projection - Recycled Water Inpecu es Table l6 Budget $3,511 $3,571 $3,633 $3,696 $3,760 Projected $3,891 $3,959 $4,027 Scheduled Production Maintenance b. Factions FY 2015 -i6 FY 2016.17 FY 2017-18 FY 2019.19 FY 2019.20 FY 2020 -21 FY 2021.22 FY 2022.23 FY 2023 -N FY 2024.25 F ared Recycled Water Coats 1,579 $1606 $1.634 $1662 $1691 $1 ]20 $1,750 $1,780 51,611 $18,13 Conective Maintenance b. Purchased Water -OCWO i,k $ 167,598 $ 173,417 $179,438 $182,810 $4,268 $106,245 $169,745 $193,311 $196,943 $200,644 $204,414 Other agency fees b. $ 2000 $2935 $2,070 $$106 $789 $2,142 $2,179 $2,217 $2,255 $2,294 $2,334 Administration d 25,000 $25,433 $25,872 $26,320 $21348 $26,775 $27,239 $27,710 $28,189 $28,677 $29,173 Overhead b. 12,000 $12,208 $12419 $12,634 35,145 $12,852 $13,075 $13,301 $13,531 $13,765 $14,003 Meter Reading b. 1,488 $1514 $1,540 $1.567 $1 594 $1621 $1,649 $1678 $1 707 $1,736 4 hourelmoMh Q$31Ihr Total - Shared Recycled Water COSts 208,086 214,605 221,339 225.436 229,609 233859 238,187 242,596 247,087 251,661 Inpecu es b. $ 3,451 $3,511 $3,571 $3,633 $3,696 $3,760 $3,825 $3,891 $3,959 $4,027 Scheduled Production Maintenance b. 1,877 $1,909 $1.943 $1,975 $2,1110 $2,045 $2,080 $2,116 $2.153 $2,190 Scheduled SCACA Maintenance b. 1,579 $1606 $1.634 $1662 $1691 $1 ]20 $1,750 $1,780 51,611 $18,13 Conective Maintenance b. 3.851 $3,918 $3,985 $4,054 $4,124 $4,196 $4,268 $4,342 $4,417 $4,494 Source Changeovers b. 700 $712 $724 $737 $750 $763 $776 $789 $803 $817 Pump Station RehablMaimenance( pumper motors) j. 11,280 $18,11 $18,956 $19,335 $19,722 $20,116 $20,519 $20,929 $21348 $21775 (pumps,motors) Teal - Big Canyon Country Club 22,738 30,241 30,814 31,398 31,994 32,600 33,219 33,849 34,491 35,145 93.0% 1.8% 19% 1.9% 1.8% 1H% 1.B% 1.9% 18% Inpec0on, b. $ 3,451 $3,511 $3,571 $3,633 $3,696 $3,760 $3,825 $3,891 $3,959 $4,027 Scheduled Production Maintenance b. 1,468 $1,432 $1,457 $1,482 $1,508 $1,534 $1,561 $1,588 $1,615 $1,643 Scheduled SCACA Maintenance b. 1,184 $1204 $1,225 $1247 $1268 $1,290 $1,312 $1335 $1358 $1382 Cm -narbe Maintenance b. 2987 $3,039 $3,091 $3,145 $3,199 $3,254 $3,311 $3,368 $3,426 $3,486 Source Changeovers b. 700 $712 $724 $737 $750 $763 $776 $789 $803 $817 Pump Station RabablMaintemme. (pumps motors) j. 6,9ag $7.079 $7,220 $7,365 $7,512 $7,662 $7,816 $7,972 $6,131 $8294 (pumps, motor.) Total- Newport Beach Country Club 16,670 16,977 17,290 17,609 17,933 18,264 18,600 18,943 19,292 19,648 I.. f.a% I.. 1.a% f.a% 18% I.. 1.9% 18% Subtotal: Opera0nR Expenses S 247.494 S 261.80 $ 269.443 $ 274.443 S 279.535 $ 284,723 $ 290.006 S 295.308 $ 300,870 $ 306.454 SB% 26% 19% 1.9% 1.9% iH% I.. Pump Station Facility Replacement $15,000 $15,000 $15,000 $15,000 $15,000 $15,000 $15,000 (mot, walls, concrete) $2,917 $259lmeter year -City estimate (15- yr servlce lire) 1.36 SS3 -44 SS3 -45 A B C D E F G H I J K L M N 1 City of Newport Beach 2 Water Rate Study 3 Table 3A. Revenue Increases - Sewer 4 Months 5 in 1st FY of Est. Actual Projected 6 rate increase' FY 2013.14 FY 201546 FY 2016 -17 FY2017d8 FY 2018.19 FY2019 -20 FY 2020.21 FY 2021 -22 FY2022 -23 FY 2023.24 FY 2024 -25 Notes 7 8 Revenue from Rates without Rate Increases Revenue from Cpthnnt Rates $3,117.723 $3,117,723 $3,117,723 $3,117,723 $3,117,723 $3,117,723 $3,117.723 $3,117,723 $3,117,723 $3, 117,723 FYlV4 from Table 7A', Table 16, g. 9 10 Bad Debt Expense ($12,391) ($12,391) ($12,391) ($12,391) ($12,391) ($12,391) ($12,391) ($12,391) ($12,391) ($12,391) 11 Net Revenue 5 3,105,332 $ 3,105,332 S 3,105,332 5 3,105,332 $ 3,105,332 S 3,105,332 5 3,105,332 $ 3,105,332 S 3,105,332 5 3,105,332 12 Net Revenue Requirements $3,760,039 $4,277,905 $4,577,358 $4,897,773 $5,046,538 $5,197,933 $5,353,871 $5,407,410 $5,461,484 $5,516,099 From Table 135urplus1(Deficit) before rate increase ($854,707) ($1,172,574) ($1,472,027) ($1,792,442) ($1,941,208) ($2,092,802) ($2,248,540) ($2,302,079) ($2,356,1521 ($2,410,767) To Table 14 15 Revenue from Rates with Rate Increases 16 Increase In Revenue from Rates 23.0% 12.0% 7.00% 7.0% 5.0% 3.0% 3.0% 1.0% 1.07. 1.0% From Table 1A 17 Cumulative Increase 206% 372% 468% 571% 61.9% 667% 71.74 734% 75.2% 769i% To Table 1A 18 Total Revenue from Existing Rates 19 Revenue from Cunent Rates $ 3,105,332 $ 3,105,332 $ 3,105,332 $ 3,105,332 $ 3,105,332 $ 3,105,332 $ 3,105,332 $ 3,105,332 $ 3,105,332 $ 3,105,332 20 Revenue from Rate Increases 21 FYI 5- 16(edective 811115) 11 $654707 $714,226 $714,226 $714,226 $714,226 $714.226 $714,226 $714,226 $714.226 $714,226 22 FY16- 17 (effective 711116) 12 $458,347 $458,347 $458,347 $458,347 $458,347 $458,347 $458,347 $458,347 $458,347 23 FY17- 18 (effective 711117) 12 $29 %453 $299,453 $299,453 $299453 $299,453 $299,453 $299,453 $299,453 24 FY18- 19 (efective 711118) 12 $320,415 $228,868 $228.868 $228,868 $228,868 $228,868 $228.868 25 FY19- 20(e1fective 711119) 12 $240,311 $240,311 $240,311 $240,311 $240,311 $240,311 26 FY20 -21 (effective 711120) 12 $151,396 $151,396 $151,396 $151,396 $151,396 27 FY21- 22 (effective 71121) 12 $155,938 $155,938 $155,938 $155,938 28 FY22- 23 (egective 71122) 12 $53,539 $53,539 $53,539 29 FY23 -24 (e1fective 711123) 12 $54,074 $54,074 30 FY24 -25 (effective 711124) 12 $54,615 31 Subtotal- Revenue from Rate Increases $654,707 $1,172,573 $1,472,027 $1,792,442 $1,941,206 $2,092,602 $2,248,540 $2,302,079 $2,356,153 $2,410,768 32 Total Rate Revenue $ 3,117,723 $3,760,039 $4,277,905 $4577,358 $4,897,773 $5,045537 $5,197,933 $5,353,871 $5407,410 $5,461,484 $5,516,099 FY13-14from Table7A 33 Net Revenue Requirements $ 2,845,911 $3,760,039 $4277,905 $4,577.358 $4,892773 $5046.538 $5,197.933 $5,353.871 $5.407,410 $5,461,484 $5,57099 From Table2 34 Surplual(Deficit) after Rate Increase $271,012 (so) ($0) ($0) (so) ($0) $0 (so) (so) $0 $0 To Table4 35 36 - Estimated k ofmon(hs of collections in FYin which ate increase takes place 37 SS3 -45 SS3 -46 A 8 I C I D I E I F I G I H I I I J I K I L I M I N I G 1 City of Newport Beach 2 Water Rate Study 3 Table 3B. Rise enua Increases - go ... led Water Month. 5 In 1st FY of Est Actual Projected, 6 rat, increase' FY 2012 -13 FY 2015 -16 FY 2016 -17 FY 209 -18 FY 2018 -19 FY 2019 -20 FY 2020 -21 FY 2021 -22 FY 202233 FY 2023 -24 FY 202485 #REFI Note. 7 8 Revenue from Rates without Rate Increases Revenue from Current Rates $522,123 $522,123 $522,123 $522,123 $522,123 $522,123 $522,123 $522,123 $522,123 $522123 #REFI Fb,12-13 fm. Table IS; Table 18. 1. 9 10 Bad Debt Expense $0 $0 $0 $o $0 $0 $o $0 $0 $0 #REFI 11 Net Revenue 3 522,123 $ 522,123 11 522,123 $ 522,123 $ 522123 $ 522,123 $ 522123 $ 522.123 $ 522,123 $ 522,123 #REFI 12 Net Revenue Requirements $264,994 $279,366 $287.030 $292075 $297,213 $302,446 8307,777 $313,207 $318,738 $324,371 #REFI F(13 -14 from City, escalated, by CPI 13 Surplusl(Defcft) before rate increase $257,129 $242,758 $235,092 $230,048 $224,910 $219,676 $214,346 $208,916 $203,385 $197,752 #REF! 14 15 Revenue from Rates with Rate Increases 16 Increase in Revenue from Rates 0.D% .50.0% 0.0% 0.0% 0.0% 0.0% D.0% 0.0% 0.0% D.0% 0.0% 17 Cumulative lectures 00% .5001% -500% -500% -5001t -500% -500% 500% -500% -500% #REF' 18 Total Revenue from Existing Rates 19 Revenue from Current Rate. $ 522,123 $ 522,123 $ 52$123 $ 522,123 $ 522,123 $ 522,123 3 522,123 $ 522123 $ 522,123 3 522,123 #REF! 20 Revenue from Rate Increases 22 FY14.15(effective 711114) 12 ($261.061) (5261081) ($261.081) ($261 061) ($261061) (V61,051) ($261 061) ($261.061) ($261 081) #REF! 23 F(15- 16(effectew 711115) 12 $0 $0 $0 $0 $0 $0 $0 $0 #REFI 24 FY16- 17(effective 711116) 12 $0 $0 $0 $D $o $0 $D #REFI 25 Fill 7- 18(affective Vill 7) 12 $0 $0 $0 $o $0 $D PRIDE! 26 FY18- 19(effective 711118) 12 $0 $0 $0 $0 $0 #REF. 27 FY19- 20(effective 711119) 12 $0 $0 $0 $0 #REF! 28 FUC-21 (e6esty. 711120) 12 $0 $0 $0 6RER 29 FY21- 22 (egeviive Ili l2l) 12 $0 $0 #REFI 30 FY22- 23 (effective 711 M) 12 $D #REF! 31 FY23- 24 (effective 711 23) 12 #REF! 32 Subtotal - Revenue from Rate Increases $0 ($261,061) ($261,061) ($261,061) ($261,061) ($281,081) ($261,061) ($261,061) ($261,061) ($261,081) #REFI 33 Total Rata Revenue $ 51 $522,123 $281,061 3261061 $261,061 $261,061 $261,061 $261,061 $261,061 $261,061 $261,061 #REF! 34 Net Revenue Requirements $264,994 $279366 5287,030 $292075 $297213 $302046 5307,777 $313207 $318,738 $324,371 41REFI 35 Surplu.l(Deficit) after Rata Increase $522,123 $257,129 ($18,305) ($25,969) ($31,013) ($36,152) ($41,385) ($46,718) ($52.140) ($57,678) ($63,310) #REFI To Table 36 37 - Estimated #ofmonths of collections In FY in which sale Increase takes place 38 SS3 -46 SS3 -47 B1 C D I E I F I G I IT I I I J I K I L I M I N 1 O 1 City of Newport Beach Sewer Rate Study Table 4. Reserves Budgeted FY 2014.15 FY 2015 -16 FY 2016 -17 FY 2017.18 FY 2018 -19 Projected FY 2019 -20 FY 2020.21 FY 2021 -22 FY 2022 -23 FY 2023.24 FY 2024 -25 Notes 2 3 4 5 6 Sewer Operating Reserve Funds With Rate Revenue Increase Annual increases Cumulative increase Operations Fund Beginning Balance Surplusl(Defidt) Transfers (to) /from Revenue Requirement Infrastructure Replacement Fund Subtotal - Transfers Subtotal- Fund Balance Estimated Interest Earnings Increase (5301 23.0% 23.0% $1,170,008 ($0) 37,497 $37,497 $1,207,505 $8,916 12.0% 37.8% $1,216,421 ($0) 242,152 $242,152 $1,458,572 $10,031 7.0% 47.4% $1,468,604 (SO) 214,690 $214,690 $1,683,293 $11,820 7.0% 57.7% $1,695,113 ($0) 456,257 ($400,000) $56,257 $1,751,370 $12,924 5.0% 65.6% $1,764,294 (SO) 224,189 ($250,000) ($25,811) $1,738,482 $13,135 3.0% 70.6% $1,751,618 $0 292,715 ($300,000) ($7,285) $1,744,333 $13,110 3.0% 75.7% $1,757,443 ($0) 363,692 ($300,000) $63,692 $1,821,135 $13,420 1.0% 77.4% $1,834,554 ($0) 330,122 ($300,000) $30.122 $1,864,676 $13,872 1.0% 79.2% $1,878,549 $0 294,882 ($225,000) $69,882 $1,948,431 $14,351 1.0% 81.0% $1,962,782 $0 257,919 ($225,000) $32,919 $1,995,701 $14,844 From Table lA From Table 3A To Table 2 (to) /from below 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 Ending Balance Minimum Balance 1,170,008 51422956 $1,216,421 $1,611,271 $1,468,604 $1,642,877 $1,695,113 $1,681,334 $1,764,294 $1,720,758 $1,751,618 $1,761,174 $1,757,443 $1,802,609 $1,834,554 $1,845,090 $1,878,549 $1.888,644 $1,962,782 $1,933,301 $2,010,545 $1.979,090 50 %of annual O&M 22 23 Sewer Infrastructure Replacement Reserve Beginning Balance Capital Improvement Projects Transfers (to)lfrom Revenue Requirements Operations Fund Subtotal - Transfers Subtotal- Fund Balance Estimated Interest Earnings (540) $695,095 ($500,000) $500,000 $0 $500,000 $695,095 $5,213 $700,308 ($765,000) $750,000 $0 $750,000 $685,308 $5,196 $690,504 ($1,040,400) $1,000,000 $0 $1,000,000 $650,104 $5,027 $655,132 ($1,061,208) $1,000,000 $400000 $1,400,000 $993,924 $6,184 $1,000,108 ($1,407,162) $1,300,000 $250,000 $1,550,000 $1,142,946 $8,036 $1,150,982 ($1,435,305) $1,300,000 $300,000 $1,600,000 $1,315,677 $9,250 $1,324,927 ($1,464,011) $1,300,000 $300,000 $1,600,000 $1,460,916 $10,447 $1,471,363 ($1,493,291) $1,300,000 $300,000 $1,600,000 $1,578,071 $11,435 $1,589,507 ($1,523,157) $1,300,000 $225,000 $1,525,000 $1,591,350 $11,928 $1,603,278 ($1,553,620) $1,300,000 $225,000 $1,525,000 $1,574,658 $11,917 From Table 5 From Table 1A (to)Rrom above 24 25 26 27 28 29 30 31 32 33 Ending Balance Target Balance 695,095 51500.000 $700,308 $1,500,000 $690,504 $1,500000 $655,132 $1.500,000 $1,000,108 $1,500,000 $1,150,982 $1,500,000 $1,324,927 $1.500,000 $1,471,363 $1,500,000 $1,589,507 $1500,000 $1,603,278 $1.500,000 $1,586,575 $1,500,000 Average Annual CIP(per 20-Y 341 35 Recycled Water Infrastructure Replacement Revenue Increase Annual increases Cumulative increase Beginning Balance Surplus/(Deficit) Reimbursement to Water Fund Subtotal - Funtl Expenditures Subtotal- Fund Balance Estimated Interest Earnings Reserve 0.0% - $257,129 $0 257,129 $964 - 60.0% 258,094 ($18,305) $0 239,789 $1,867 -- 0.0% 241,656 ($25,969) $0 215,687 $1,715 0.0% 217,402 ($31,013) $0 186,388 $1,514 0.0% 187,902 ($36,152) $0 151,751 $1,274 0.0% 153,025 ($41,385) $0 111,640 $992 0.0% 112,632 ($46,716) $0 65,916 $670 0.0% 66,586 ($52,146) $0 14,440 $304 0.0% 14,744 ($57,676) $0 (42,932) $0 0.0% (42,932) ($63,310) $0 (106,242) $0 From Table 3B From Table 3B 36 37 38 39 40 41 42 43 44 45 46 47 48 49 Ending Balance $258,094 $241,656 $217,402 $187,902 $153,025 $112,632 $66,586 $14,744 $42,932 $106,242 SS3 -47 SS3 -48 A I B C D E F G H I J K L M 1 City of Newport Beach Water Rate Study Table 5. CIP Project # Project Name FY 2015.16 FY 2016.17 FY 2017.18 FY 2018.19 FY 2019.20 FY 2020 -21 FY 2021 -22 FY 2022.23 FY 2023.24 FY 2024.25 Total Cost 2 3 4 _.L 6 C2002049 Grade Adjustments: Sewer Manhole Covers C7002005 Saint James Rd. Sewer Relocation C6002016 SCADA System Upgrade C7001003 WW Master Plan Improvements Additional Capital Funding Total Projects Total Operating Total Replacement Total Unfunded Total Annual Project Cost Construction COST Inflation Inflated Operating Total Inflated Replacement Total Inflated Unfunded Total Source: City of Newport Beach WW CIP 13 -14 $100,000 $225,000 $100,000 $75,000 $0 $500,000 $0 $500,000 $0 $500,000 0.0% $0 $500,000 $0 $750,000 $750,000 $0 $750,000 $0 $750.000 2.0% $0 $765,000 $0 $1,000,000 $1,000,000 $0 $1,000,000 $0 $1,000,000 2.0% $0 $1,040,400 $0 $1,000,000 $1,000,000 $0 $1,000,000 $0 $1,000,000 2.0% $0 $1,061,208 $0 $1,300,000 $1,300,000 $0 $1,300,000 $0 $1,300.000 2.0% $0 $1,407,162 $0 $1,300,000 $1,300,000 $0 $1,300,000 $0 $1,300,000 2.0% $0 $1,435,305 $0 $1,300,000 $1,300,000 $0 $1,300,000 $0 $1,300,000 2.0% $0 $1,464,011 $0 $1,300,000 $1,300,000 $0 $1,300,000 $0 $1,300,000 2.0% $0 $1,493,291 $0 $1,300,000 $1,300,000 $0 $1,300,000 $0 $1,300,000 2.0% $0 $1,523,157 $0 $ 100,000 $ 225,000 $ 100,000 $ 75,000 $1,300,000 $ 10,550,000 $1,300,000 $11,050,000 $0 $ - $1,300,000 $ 11,050,000 $0 $ $1,300,000 $11,050,000 2.0% $0 $ - $1,553,620 $ 12,243,155 $0 $ - 7 6 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 SS3 -48 Rate Study 7A. Rate Revenue - Sewer Source: SWR_RCY study_meter count - Service 980 Meters Only - Active Accounts FY11 -12 FY11 -12 FYI 1-12 customer Class No Of Acct. Charge /acct Annual Revenue SWR 485 $ 6.25 $ 36,375 Source: SWR_RCY study_meter count - SWR Accounts Only FY11 -12 FY11 -12 FY11 -12 FY11 -12 FYI 1-12 FY11 -12 FY11 -12 Charge /DU FY11 -12 customer Class Meter Count Charge /meter Annual Revenue Meter Count WW Surchg Annual Revenue 5/8" 15,354 $ 4.50 $ 829,116 $ 2.00 $ 1,008 $ 48,746 3/4" 3 $ 4.50 $ 162 'LE FAMILY RES 81 $ 2.00 $ 1" 6,276 $ 4.50 $ 338,904 15,648 $ 15,768 - 10960 1.5" 364 $ 4.50 $ 19,656 0.35 $ - No Sewer Charge 2" 886 $ 4.50 $ 47,844 478 $ 10.00 $ 57,360 2.5" 1 $ 4.50 $ 54 0 $ 10.00 $ - 3" 34 $ 4.50 $ 1,836 35 $ 10.00 $ 4,200 4" 119 $ 4.50 $ 6,426 90 $ 10.00 $ 10,800 6" 54 $ 4.50 $ 2,916 47 $ 10.00 $ 5,640 8" 11 $ 4.50 $ 594 6 $ 10.00 $ 720 10" 2 $ 4.50 $ 108 0 $ 10.00 $ 23,104 $ 1,247,616 656 $ 78,720 Source: SWR_RCY study_meter count - Service 980 Meters Only - Active Accounts FY11 -12 FY11 -12 FYI 1-12 customer Class No Of Acct. Charge /acct Annual Revenue SWR 485 $ 6.25 $ 36,375 Source: SWR_RCY study_meter count - SWR Accounts Only FY 11 -12 Customer Billing Analysis Service 901, 903- Sewer Svc Multi/Bi- monthly, Sewer Svc MulWonthly and 904,910 SWR SRV HOSP- HOT /Bi-MO and Monthly FY11 -12 FY11 -12 FY11 -12 FY11 -12 FY11 -12 !omer Class NO of DUs Charge /DU Annual Revenue Annual Revenue TI FAMILY RES 8477 $ 2.00 $ 203,448 $ 1,327 IMERICAL 759 $ 2.00 $ 18,216 $ 48,746 'METER 42 $ 2.00 $ 1,008 $ 48,746 ISOLIDATED 949 $ 2.00 $ 22,776 $ 816 'LE FAMILY RES 81 $ 2.00 $ 1,944 $ 48 IER ONLY 652 $ 2.00 $ 15,648 $ 15,768 - 10960 0.35 $ 263,040 $ 115,452 FY 11 -12 Customer Billing Analysis Service 901, 903- Sewer Svc Multi/Bi- monthly, Sewer Svc MulWonthly and 904,910 SWR SRV HOSP- HOT /Bi-MO and Monthly ce: Email from George Murdoch dated 412712015 for FY13 -14 metered water use Calculated Revenue from Customer Billing Data $ 3,576,563 To Table 3A $ 12.90 $ 3,321,344 $ 255,219 SS3 -49 FY 2013 -14 FY11 -12 FY 2013 -14 :omer Class Consumption Charge /CCF Annual Revenue ;LE FAMILY RES 2,982,858 $ 0.35 $ 1,044,000 TI FAMILY RES 919,160 $ 0.35 $ 321,706 'METER - $ 0.35 $ - No Consumption Charge - Only Fixed Fee 1MERICAL 1,312,620 $ 0.35 $ 459,417 IL 29,248 $ 0.35 $ 10,237 SOLIDATED - $ 0.35 $ - T DOCK - $ 0.35 $ - No Sewer Charge INKLER - $ 0.35 $ - No Sewer Charge - $ 0.35 $ - No Sewer Charge IP STATION $ 0.35 $ No Sewer Charge 5,243,886 $ 1,835,360 Mandatory Cutbacks @25% (1,310,972) $ 0.35 $ (458,840) Consumption Revenue (estm.) 3,932,915 $ 1,376,520 0.35 ce: Email from George Murdoch dated 412712015 for FY13 -14 metered water use Calculated Revenue from Customer Billing Data $ 3,576,563 To Table 3A $ 12.90 $ 3,321,344 $ 255,219 SS3 -49 SS3 -50 A B C D E F G H I J K L M N O 1 City of Newport Beach Sewer Rate Study Table 7B. Rate Revenue - Recycled Water Breakdown of Recycled Water Costs Fixed Costs (borne regardless of flow) Variable Costs (related to flow) Pump Station Costs Total - Recycled Water Costs Total Metered Flow Total Pump Station Flow Charge per HCF - All Customers Charge per HCF - Pump Station Mo. Service Charge 5/8" or 3/4" 1" 11/2" 2" 3" 4" 6" 8" Newport Beach Commodity Charge (per HCF) Pump Station Charge (per HCF) Total Recycled Water Revenue IPer GAP Workbooks - Monthly Meter Reads July August September October November December January February March April May June Total Active Accounts (excid City) 0 0 0 1 1 0 2 1 5 202,793 Total FY12 -13 31,828 31,058 13,620 11,962 6,881 675 4,032 6,369 12,458 26,488 29,488 27,934 202,793 Current Monthly Service Annual Charge Revenue $ 13.82 $ - $ 2103 $ - $ 46.06 $ - $ 73.70 $ 884 $ 138.18 $ 1,658 $ 230.30 $ - $ 460.61 $ 11,055 $ 736.98 $ 8,844 $ 22,441 $ 2.46 $499,682 $522,123 CC Usage Total FY12 -13 FY11 -12 27,605 30,285 26,326 31,311 10,963 11,132 9,778 8,502 5,541 3,082 579 3,188 6,156 5,282 7,140 10,791 9,481 22,844 12,562 25,733 29,175 23,796 28,180 172,426 177,006 85% FY14 -15 $43,732 From Table 7B 173,417 From TableP 62,218 From Table 2B $279,366 202,793 From Bro. 172,426 From Below $0.86 $0.36 Revised Total Monthly Active EMU Total Service Annual Accounts Multiplier EMUS Charge Revenue 0 1.00 0 $18.91 $0 0 1.67 0 $31.53 $0 0 3.33 0 $63.05 $0 8 533 42.673 $100.88 $9,684 3 10.00 30.005 $189.15 $6,810 0 16.67 0 $315.25 $0 2 33.34 66.677 $630.50 $15,132 1 53.34 53 $1,008.81 $12,106 14 193 $43,732 $0.86 $173,417 $0.36 $62,218 $279,366 To Table 3B To Table 2B Water Rates $ 17.27 $ 28.79 $ 57.58 $ 92.12 $ 172.73 $ 287.88 $ 575.76 $ 921.22 Water Multiplier 1.00 1.67 3.33 5.33 10.00 16.67 33.34 53.34 _L 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 SS3 -50 IV HF.H HF &H Consultants, LLC 201 N. Civic Drive, Suite 230 Walnut Creek, CA 94596 SS3 -51 c1ir_TyOW1614,r9:3 Meter Size r 1 5/8 in 11111111111111W 2 in 6 in 6 in Usage(HCF) 15 446 Fixed Fee Charge $ 1608 Fixed Fee Charge $ 4.50 $ 14.50 $ 14.50 Variable Fee Charge $ 0.35 $ 0.35 $ 0.35 Total Monthly Charge $ 9.75 $ 170.60 $ 577.30 Total Bi- Monthly Charge $ 19.50 $ 341.20 Meter Size 1 5/8 in 2 in 2 in 6 in ii Usage(HCF) 15 446 Fixed Fee Charge $ 1608 Fixed Fee Charge $ 7.34 $ 11.01 $ 16.51 Variable Fee Charge $ 0.43 $ 0.43 $ 0.43 Total Monthly Charge $ 13.79 $ 202.79 $ 707.95 Total Bi- Monthly Charge $ 27.58 $ 405.58 Meter Size Ir 5/8 in 2 in 2 in 6 in 6 in Usage(HCF) 15 446 Fixed Fee Charge $ 1608 Fixed Fee Charge $ 8.47 $ 13.19 $ 19.78 Variable Fee Charge $ 0.52 $ 0.52 $ 0.52 Total Monthly Charge $ 16.27 $ 245.11 $ 855.94 Total Bi- Monthly Charge $ 32.54 $ 490.22 Meter Size I= 5/8 in 2 in 6 in Usage(HCF) 15 446 1608 Fixed Fee Charge $ 9.34 $ 14.82 $ 22.23 Variable Fee Charge $ 0.58 $ 0.58 $ 0.58 Total Monthly Charge $ 18.04 $ 273.50 $ 954.87 Total Bi- Monthly Charge $ 36.08 $ 547.00 SS3 -52