HomeMy WebLinkAbout16 - Mariners Park Restroom ConstructionCITY OF NEWPORT BEACH CITY COUNCIL STAFF REPORT Agenda Item No. 16 January 13, 2009 TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL FROM: Public Works Department Frank Tran, Project Engineer 949 -644 -3340 or ftran @city.newport- beach.ca.us SUBJECT: MARINERS PARK RESTROOM CONSTRUCTION - COMPLETION AND ACCEPTANCE OF CONTRACT NO. 3992 Recommendations: 1. Accept the completed work. 2. Authorize the City Clerk to file a Notice of Completion. 3. Authorize the City Clerk to release the Labor and Materials bond 35 days after the Notice of Completion has been recorded in accordance with applicable portions of the Civil Code. 4. Release the Faithful Performance Bond 1 year after Council acceptance. Discussion: On May 13, 2008, the City Council authorized the award of Mariners Park Restroom Construction to NILE Advanced Construction, Inc. Under this contract, NILE constructed a new restroom building including 2 -in water service and other utilities, sidewalks, hardscape, landscape, and fire hydrant relocation. The contract has now been completed to the satisfaction of the Public Works Department. A summary of the contract cost is shown in the following table: Original bid amount: $543,000.00 Actual amount of bid items constructed: $543,000.00 Total amount of change orders: $ 2,500.00 Final contract cost: $545,500.00 One change order was needed for a special mold to expedite the concrete block order. The final overall construction cost including this change order was less than one -half percent over the original bid amount. Based on excellent City staff support of this project, NILE constructed the pedestal for the dedication plaque at no charge to the City. Manners Park Restroom Construction - Completion and Acceptance of Contract No. 3992 January 13, 2009 Page 2 A summary of the project schedule is as follows: Estimated completion date per June '07 schedule: April 3, 2009 Project award for construction: May 13, 2008 Estimated completion date at award: September 16, 2008 Actual substantial construction completion date: September 16, 2008 The schedule was advanced to accommodate the wishes of Council and the community. This successful project was completed on schedule (including removal of the temporary restroom, utilities and turf repair performed under a separate contract), and was ready for the Mariners Park Renewal Ceremony on October 30, 2008. Environmental Review: This project was categorically exempt from the provisions of CEQA per Section 15301(c), since the project consists of making repairs to existing sidewalks and other improvements that do not expand their current use. A Notice of Exemption was filed with the County Clerk. Public Notice: The Notice Inviting Bids was advertised in the City's official publication and in construction industry publications. Prior to starting work, two City- prepared construction informational notices were distributed by the contractor to residents within distributed ten days prior to the scheduled work. hours before the work commenced. Funding Availability: the Work vicinity. The first notice was The second notice was distributed 48 In addition to the primary construction contract, this project included for material testing, printing and incidentals: Construction $545,500.00 Design 34,398.50 Geotechnical & Material Testing 8,034.10 Construction Inspection 1,834.65 Printing and Incidentals 3,053.67 Total Project Cost $592,820.92 Funds for the construction contract were expended from the following account: Account Description Account Number Amount General Fund 7015- C5100909 $545,500.00 Total: $545,500.00 Mariners Park Restroom Construction - Completion and Acceptance of Contract No, 3992 January 13, 2009 Page 3 Prepared by: Subm Frank Tranen G. Badum Project Engineer lic Works Director