HomeMy WebLinkAbout04 - Community Youth Center Parking Lot RehabCITY OF NEWPORT BEACH
CITY COUNCIL STAFF REPORT
Agenda Item No. 4
March 10, 2009
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: Public Works Department
Fong Tse, Principal Civil Engineer
949- 644 -3321 orftse @city.newport- beach.ca.us
SUBJECT: COMMUNITY YOUTH CENTER PARKING LOT REHABILITATION -
AWARD OF CONTRACT NO. 4132
Recommendations:
1. Approve the project plans and specifications.
2. Award Contract No. 4132 to L.M.T. Enterprises, Inc., dba Tyner Paving Company
for the Total Bid Price of $107,830.00 and authorize the Mayor and the City Clerk
to execute the contract.
3. Establish an amount of $7,170.00 (6.6 %) to cover the cost of unforeseen work.
Discussion:
At its January 27, 2009 regular meeting, the City Council rejected all bids previously
received for this project due to a clerical error made by City staff and directed staff to re-
advertise the work.
At 10:00 a.m. on February 12, 2009, the City Clerk opened and read the following bids
for this project:
BIDDER
TOTAL BID AMOUNT
Low
L.M.T. Enterprises, Inc., dba Tyner Paving Company
$107,830.00
2
D & L Paving
$107,905.00
3
All American Asphalt
$108,298.00
4
Hillcrest Contracting
$111,495.00
5
E.C. Construction Company
$123,927.00
6
Golden State Constructors, Inc.
$126,471.00
7
Elite Bobcat Services, Inc.
$127,300.00
8
GMC Engineering, Inc.
$128,000.00
9
Century Paving, Inc.
$128,787.00`
Community Youth Center Packing Lot Rehabilitation —Award of contract No. 4132
March 10, 2009
Page: 2
10 NPG Corporation
11 Haitbrink Asphalt Paving, Inc.
12 Hardy & Harper, Inc.
13 Excel Paving Company
$137,999.00
$138,217.70
$149,000.00
$149,958.00
Corrected Bid Amount is $128,727.00
The low total bid amount is two percent (2 %) percent below the $110,000 Engineer's
Estimate. The low bidder, Tyner Paving Company, possesses a California State
Contractor License Classification "A" as required by the project specifications. A check of
the Contractor's references indicates they have satisfactorily completed similar paving
projects for other local public agencies.
The existing Community Youth Center (CYC) parking lot is heavily used by Harbor View
Elementary School students and parents and CYC users. Although the existing parking
lot has served its purposes for many years, its perpendicular parking configuration is not
the most efficient design for high volume student drop -off and pick -up queuing on
schooldays.
This rehabilitation project will extend the existing parking lot pavement eastward to
accommodate a circular drive aisle for improved traffic flow and curb -side loading and
unloading. The existing pavement ribbon gutter will be eliminated for improved surface
drainage. The portion of Iris Avenue roadway adjacent to the Grant Howald Park
athletic field will be striped to maintain the current overall number of parking spaces
available at the site. With improved traffic circulation and ease of use, staff is hopeful
that parents will use this parking lot as an alternate drop -off and pick -up location which
could potentially reduce some of the routine congestion on Goldenrod Avenue during
peak periods on school days.
Pursuant to the Contract Specifications, Tyner will have twenty -five consecutive working
days to complete the construction. Since the parking lot must be completed when the
CYC reopens, the contract allows Tyner to work after -hours to expedite work
completion. Liquidated damages in the amount of $1,000 per calendar day will be
assessed if Tyner fails to complete the work within the allotted time.
Environmental Review:
The project is Categorically Exempt from the California Environmental Quality Act
(CEQA) pursuant to Section 15301 of the CEQA Implementing Guidelines. This
exemption covers the repair, maintenance and minor alteration of existing public
facilities with negligible expansion.
Community Youth Center Parking Lot Rehabilitation —Award of Contract No. 4132
March 10, 2009
Page: 3
Public Notice:
The Notice Inviting Bids was advertised in the City's official publication and in
construction industry publications. Prior to starting work two City prepared notices are
distributed by the contractor to both residents and the nearby elementary school. The
first notice will be distributed ten days before work and the second notice 48 hours prior
to starting work.
Other Costs:
In addition to the contract costs, $1,000 is included for printing and other incidentals.
Surveying, geotechnical engineering, and consultant inspection services are not
required for this project.
Funding Availability:
There are sufficient funds available in the following account(s) for the project:
Account Description
General Fund
Proposed uses are as follows:
Vendor
Tyner Paving Company
Tyner Paving Company
Various
Prepared
Account Number
7011- C4120806
Total:
Amount
$ 116,000.00
$ 116,000.00
Purpose Amount
Construction Contract $ 107,830.00
Construction Contingency $ 7,170.00
Printing and Incidentals $ 1,000.00
Total: $ 116,000.00
Submitted
Fcfng Jr;#e -�S hen G. Badum
Princoal Civil Engineer ublic Works Director
Attachment: Project Location Map
January 13, 2009 Reject All Bids Council Report
A PP OV (.
CITY OF NEWPORT BEACH
CITY COUNCIL STAFF REPORT
dyt CNity Council
Ageri�a Itearr,o.ge io
January 27, 2009
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: Public Works Department
Fong Tse, Principal Civil Engineer
949- 644 -3321 orftse @city.newport- beach.ca.us
SUBJECT: COMMUNITY YOUTH CENTER PARKING LOT REHABILITATION —
REJECT ALL BIDS FOR CONTRACT NO. 4132
Recommendations:
1 _ Reject all received bids_
2. Direct staff to re- advertise the project for bids.
3. Direct staff to return the Cashier's Check (Bid Bond) in the amount of $12,500.00
submitted by Frank Shariat General Engineering_
Project Description:
The existing Community Youth Center (CYC) parking lot is used by Harbor View
Elementary School students, parents and CYC users. This parking lot, with its
perpendicular parking configuration and dead -end design, does not efficiently serve the
center in accommodating the high volume of student drop -off and pick -up queuing on
school days. A rehabilitation project has been developed to extend the existing parking
lot pavement eastward to accommodate a circular drive aisle for improved traffic flow
and curb -side loading and unloading.
The portion of Iris Avenue roadway adjacent to the Grant Howald Park athletic field will
be striped to maintain the current overall number of parking spaces available on site.
With improved traffic circulation and ease of use, staff is hopeful that parents will use
this parking lot as an alternate drop -off and pick -up location which could potentially
reduce some of the routine congestion on Goldenrod Avenue during peak periods on
schooldays.
Discussion on Bid Rejection:
Two projects were scheduled to bid on January 12, 2009, one at 10:00 am and one at
11:00 am. The CYC Parking Lot Rehabilitation was scheduled for 10:00 am. Due to
duplicate printing of the above bid package, an error in submittal times occurred.
After the 10:00 am bid opening, the City Clerk's Office notified Public Works that two
contractors submitted bids on the CYC Parking Lot Rehabilitation for an 11:00 bid
opening. Upon consultation with the City Attorney's Office, these two bids were opened.
Community Youth Center Parking Lot Rehabilitation - Reject All Bids For Contract No. 4132
January 27, 2009
Page: 2
NPG, Inc. (NPG) who submitted the bid at 11:00 am was the apparent low bidder with a
bid of $99,534.00.
Staff spoke to NPG and NPG admitted attending the 10:00 am bid opening. While NPG
did not confirm nor deny hearing the bid prices read during the 10:00 am bid opening, Staff
could not confirm NPG's claim that its bid package was sealed before the 10:00 am bid
opening as it was time stamped by the City Clerk's office at 10:29 am. NPG's bid package
did contain a "Notice Inviting Bids" page that showed an 11:00 am bid opening. In light of
the confusion over the bid opening time and the inability of Staff to prove conclusively that
NPG's bid was not revised before it was accepted by the City Clerk's Office, Staff
recommends that all bids be rejected to avoid any sense of impropriety and the project be
re- advertised.
The reason for this highly unusual situation is as follows: the draft copy of the bid package
originally called for an 11:00 am opening. When it was discovered that another project
had a bid opening on the same day and time, the CYC bid packages were hand corrected
to change the bid opening to 10:00 am. Unfortunately, five bid packages with the 11:00
am bid opening that were stored in a back area were'overtooked. When additional bid
packages were needed, these uncorrected bid packages were released to bidders.
Staff believes that with a two week re- advertisement, the project can still be completed
around the time of the CYC reopening.
Prepared by: Submitted by:
Fon T e Stephen G. adum
Prin .i al Civil Engineer Public Works Director
GRANT HOWALD PARK
PROJECT
rn
J
u+
ZP
LOCATION MAP
NOT TO SCALE
COMMUNITY YOUTH CENTER PARKING LOT REHABILITION
3000 FIFTH AVENUE, CORONA DEL MAR
C -4132