HomeMy WebLinkAbout05 - Central Library Air Conditioning RehabCITY OF NEWPORT BEACH CITY COUNCIL STAFF REPORT Agenda Item No. 5 March 10, 2009 TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL FROM: Public Works Department Tom Sandefur, Associate Civil Engineer 949 - 644 -3312 or tandefur @city.newport - beach.ca.us SUBJECT: CENTRAL LIBRARY AIR CONDITIONING REHABILITATION- AWARD OF CONTRACT NO. 4138 Recommendations: 1. Approve the project plans and specifications. 2. Approve a budget amendment transferring $75,000 from project savings in Account 7015- C5100909 (Mariners Park Restroom), $72,000 from project savings in Account 7015- C5100817 (Mariners Park Improvements) and $13,000 from project savings in Account 7011- C5100809 (Newport Theatre Arts Center Entry) to Account No. 7019- C100202 for the capital purchase and repair of a new air conditioning unit for the Central Library. 3. Award Contract No. 4138 to BK Air Conditioning and Heating for the Total Bid Price of $135,391.00 and authorize the Mayor and the City Clerk to execute the contract. 4. Establish an amount of $20,300 (15% of Total Bid) to cover the cost of unforeseen work. Discussion: At 10:00 a.m. on February 26, 2009, the City Clerk opened and read the following bids for this project: BIDDER TOTAL BID AMOUNT Low BK Air Conditioning and Heating $135,391.00 2 Pardess Air, Inc. $140,000.00 3 F.M. Thomas Air Conditioning, Inc. $145,978.00 4 Western Allied Corporation $148,741.00 5 Magicool, Inc. $162,000.00 6 Dependable Graham Air Conditioning; Inc. $170,775.00 The low total bid amount is twenty -three percent below the Engineer's Estimate of $175,000.00. The difference between the engineer's estimate and the low bid amount may be related to the current down turn in the economy and the number of contractors looking for work. The low bidder, BK Air Conditioning and Heating, possesses a California State Contractor's License Classification "C -20" as required by the project specifications. A check of the contractor's references indicates that this Contractor has satisfactorily completed similar projects in the past. Central Library Air Conditioning Rehabilitation — Award of Contract No. 4138 March 10, 2009 Page: 2 The existing air conditioning chiller for the Central Library was installed in about 1992. Exposure to the elements has led to the deterioration of various components of the chiller. In particular, the chiller has developed a leak in the evaporator section rendering at least half the unit inoperable. In addition the condenser coils have deteriorated as well. The unit needs constant maintenance and service calls. A new chiller will not only negate the need for continuous repairs, but also the new compressors are up to 20% more energy efficient than the current compressors. In addition, the new unit uses a more environmentally friendly refrigerant. Pursuant to the Contract Specifications, the Contractor will have sixty -five consecutive working days to complete the construction. Liquidated damages in the amount of $200 per calendar day will be assessed if the Contractor fails to complete the construction within the allotted time. Environmental Review: The project was determined to be exempt from the California Environmental Quality Act (CEQA) pursuant to Section 15301 (Restoration or Rehabilitation) of the CEQA Implementation Guidelines. This Exemption covers the restoration or rehabilitation of deteriorated or damaged structures, facilities or mechanical equipment to meet current standards of public health and safety. Public Notice: The Notice Inviting Bids was advertised in the City's official publication. Funding Availability: Upon approval of the budget amendment, there will be sufficient funds available in the following account for this project: . Account Description Capital Purchase and Repair Proposed uses are as follows: Vendor BK Air Conditioning and Heating BK Air Conditioning and Heating Various Prepared by: . � ✓dam �% Tom Sandefur Associate Civil Engineer Account Number Amount 7019- C1002021 $ 160,000 Purpose Amount Construction Contract $135,391 Construction Contingency $ 20,300 Incidentals $ 4,309 Total: $ 160,000 geng. Badum lic Works Director City of Newport Beach NO. BA- 09BA -042 BUDGET AMENDMENT 2008 -09 AMOUNT: $1so,000.00 EFFECT ON BUDGETARY FUND BALANCE: Increase Revenue Estimates Increase in Budgetary Fund Balance Iq Increase Expenditure Appropriations AND �X Decrease in Budgetary Fund Balance Transfer Budget Appropriations No effect on Budgetary Fund Balance SOURCE: from existing budget appropriations from additional estimated revenues PX from unappropriated fund balance EXPLANATION: This budget amendment is requested to provide for the following: To transfer project savings from the Mariners Park Restroom, Mariners Park Improvements, and Newport Theatre Arts Center Entry accounts to the Central Library HVAC account for the capital purchase and repair of a new air conditioning unit for the Central Library. ACCOUNTING ENTRY: BUDGETARY FUND BALANCE Fund Account REVENUE ESTIMATES (3601) Fund /Division Account EXPENDITURE APPROPRIATIONS (3603) Description Description Amount Debit Credit Signed: City Council Approval: City Clerk Date Description Division Number 7015 Parks Account Number C5100909. Mariners Park Restroom /Storage Bldg $75,000.00 Division Number 7015 Parks Account Number C5100817 Mariners Park Improvements $72,000.00 Division Number 7011 Facilities Account Number C5100809 Newport Theatre Arts Center Entry $13,000.00 Division Number 7019 Capital Purchase & Repair Account Number C1002021 Central Library HVAC $160,000.00 Automatic System Entry . /J 2 Signed: Financial Approval: Administ tive Services Director Date S > �Z7 dT Signed: "'""� Administrative App val: ity Manager to Signed: City Council Approval: City Clerk Date