Loading...
HomeMy WebLinkAbout07 - Westcliff Street Light ReplacementCITY OF NEWPORT BEACH CITY COUNCIL STAFF REPORT Agenda Item No. 7 April 14, 2009 TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL FROM: Public Works Department Alfred Castanon, Associate Civil Engineer 644 -3314 or aaastanon@city.newport-beach.ca.us SUBJECT: WESTCLIFF STREET LIGHT REPLACEMENT —COMPLETION AND ACCEPTANCE OF CONTRACT NO. 3868 Recommendations: 1. Accept the completed work. 2. Authorize the City Clerk to file a Notice of Completion. 3. Authorize the City Clerk to release the Labor and Materials bond 35 days after the Notice of Completion has been recorded in accordance with applicable portions of the Civil Code. 4. Release the Faithful Performance Bond 1 year after Council acceptance. Discussion: On August 12, 2008, the City Council authorized the award of the Westcliff Street Light Replacement project to KDC, Inc., dba "Dynalectric, Inc." The contract provided for the replacement of obsolete street lights that were installed more than 40 years ago and the replacement of steel poles with standard concrete poles, as well as deteriorating conduits, conductors and concrete pull boxes. The contract has now been completed to the satisfaction of the Public Works Department. A summary of the contract cost is as follows: Original bid amount: $680,170.00 Actual amount of bid items constructed: $740,899.44 Total amount of change orders: $8,587.32 Final contract cost: $749,486.76 The increase in the actual amount of bid items constructed over the original bid amount resulted from extra conduit, conductors and additional concrete pull boxes. In addition, there were four change orders totaling $8,587.32. The change orders were for the following: Westcliff Street Light Replacement- Completion and Acceptance of Contract No. 3868 April 14, 2009 Page 2 Change Description Amount Order 1a Contractor re- routed street light conduit on Irvine $2,664.85 Avenue. 1b Contractor repaired street light conduit and installed $1,094.00 temporary wire at Dover Drive & Sussex Lane and at Dover Drive and Kent Lane. 2 Removal of street light foundations and 65 additional $2,678.74 working days added to contract due to rain delays and extra work requested by City staff. 3 Potholing on Coast Highway at Morning Canyon at City $2,149.73 Request. Total Project Change Orders $8,587.32 The final overall construction cost including four Change Orders was 10.2 percent over the original bid amount. A summary of the project schedule is as follows: Estimated completion date per June 08' schedule: March 20, 2009 Project award for construction: August 12,2008 Estimated completion date at award: December 10, 2008 Actual substantial construction completion date: March 13, 2009 All work was substantially completed by March 13th, five days ahead of the scheduled completion date of March 20, 2009. Environmental Review: The project was exempt from the Califomia Environmental Quality Act (CEQA) pursuant to Section 15301 of the CEQA Implementation Guidelines when the project was authorized by the City Council. This exemption covers the repair, maintenance and minor alteration of existing public facilities with negligible expansion. Funding Availability: In addition to the primary construction contract, this project involved other project expenses. Total project expenses are summarized as follows: Construction Engineering — JMD, Inc. Inspection — Willdan Engineering Incidentals Total Project Cost $749,486.76 $28,000.00 $2,970.00 $12,887.39 $793,344.15 Westcliff Street Light Replacement- Completion and Acceptance of Contract No. 3868 April 14, 2009 Page 3 Funds for the construction contract were expended from the following accounts: Account Description Account Number Amount Street Light Conversion Program 7013- C2202000 $747,337.03 Coast Highway Sidewalk 7254- C2002005 $2,149.73 Improvement Program Total: $749,486.76 Prepared by: AlfredvCastanon Associate Civil Engineer Submitted by: i { G. Badum Public Works Director