HomeMy WebLinkAbout18 - City Council 2009 PrioritiesCITY OF NEWPORT BEACH
CITY COUNCIL STAFF REPORT
Agenda Item No. 18
April 28, 2009
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: City Manager's Office
Homer Bludau, City Manager
949/644 -3000 or hbludau @city.newport- beach.ca.us
SUBJECT: Council Review of Staff Status Report on Six of the City Council's
2009 Priorities
ISSUE:
Does the City Council have any comments or questions regarding the status of the
seven Council priorities reported on by staff?
RECOMMENDATION:
Review and comment, as desired.'
DISCUSSION:
Background:
The City Council held a Special City Council meeting on Saturday, January 10, 2009, to
discuss and establish its priorities for 2009. This was the third consecutive year the City
Council has met early in the calendar year to set its priorities. A total of thirteen (13)
priorities were settled on, but in no particular order. As in the past, the City Manager
was asked to provide draft priority statements, actions steps and schedules for the City
Council to review, make revisions to and finalize.
The status of priority implementation will be reviewed each month starting in March.
Status reports on seven priorities were provided at the March 24, 2009. This status
report provides current information on the remaining six priorities. This is the second
status report of the year. The six priorities being reported on in no particular order are
as follows:
• Continue to implement an effective traffic management plan by a variety of projects
which improve traffic flows throughout the City.
City Council Priorities
April 28, 2009
Page 2
• Complete the Schematic Design Phase and the EIR for the new city hall and park
site.
• Provide more public parks and recreation facilities, with emphasis on active facilities
where appropriate. Construct a new OASIS facility for our seniors.
• Continue with the process to determine the eventual land use for the Banning Ranch
property, pursuing both open space and development options outlined in the
General Plan.
• Continue to implement water quality improvement projects, while at the same time,
assessing the need to adopt a tiered water rate structure to assist in water
conservation efforts.
• Develop and implement a strategy, including a funding component, for the dredging
of the Lower Bay
Additional status reports will be provided at the second City Council meeting of each
month for the remainder of the calendar year. These reports will always be placed on
the Consent Calendar, which will provide Council the opportunity to pull the item and
discuss any or all of the six priorities being covered by the report.
Environmental Review: The City Council's approval of this Agenda Item does not
require environmental review.
Public Notice: This agenda item has been noticed according to the Brown Act (72 hours
in advance of the meeting at which the Council considers the item).
Submitted by
HOMER L. BLUDAU
City Manager
Attachments: 2009 Council Priorities Indicator Tracker
City of Newport Beach
kv
\<<FO R� ;
2009 Council Priorities Indicator
Tracker
Status Report
Date published: April 28, 2009
Presented by: Homer L. Bludau
CONTINUE TO IMPLEMENT AN EFFECTIVE TRAFFIC MANAGEMENT
PLAN BY A VARIETY OF PROJECTS WHICH IMPROVE TRAFFIC
FLOWS THROUGHOUT THE CITY
Phase 1 signal project completed and
March 15, 2009
Project was completed and
operational
operational on March 15, 2009
Phases 2 and 3 signal project designs
March 30, 2009
Design Complete.
completed, work begins
Construction contract awarded
April 14, 2009
Phases 2 and 3 — Completed and
December 31, 2009
operational
Council discussion on Phases 4 -8 as
March 24, 2009
FY 09 -10 currently includes
whether to accelerate design and
funding for design and
construction
construction of Phases 4 & 7
Staff recommends projects which facilitate
May 12, 2009
FY 09 -10 currently includes
traffic flows in FY 09 -10 CIP budget
the Jamboree/73 Bridge
widening and Improvements to
the Jamboree/MacArthur
Intersection
Council approves new CIP budget with
June 23,2009
project schedules
Staff reports to Council as to status of CIP
November 24, 2009
traffic related projects
Comments: As discussed at the Council's priority setting meeting, to accelerate the design and
construction of Phases 4-8 would cost approximately $4M, so Council may want to consider accelerating
some or all of the Phases, depending on how funding could be accommodated.
This priority includes staff proposing CIP projects which might result in additional turn lanes, street
widening, tum -outs and other measures which could translate into improved traffic circulation for
particular problematic locations.
Staff: Steve Badum; Dave Webb
71
COMPLETE THE SCHEMATIC DESIGN PHASE AND THE EIR FOR THE
NEW CITY HALL AND PARK SITE
Hire City Hall & Park architect (BCJ)
January 2009
Achieved
Hire City Hall & Park Project Management
Firm (CW Driver)
January 2009
Achieved
Hire City Hall & Park EIR Consultant (LSA)
January 2009
Achieved
Complete Concept Plan Phase
April 15, 2009
Achieved
Complete Schematic Design Phase and
adopt Final EIR
November 24, 2009
i
Comments: The City Hall and Park Design project is well underway in 2009, with design team meetings
held weekly. City staff and the design team presented a concept plan for the City Hall and Park to City
Council on April 14, 2009. The rest of 2009 will be the Schematic Design phase, including at least one
public meeting during summer 2009. 2010 will include the "Design Development" and construction
documentation phases, which precede bidding and construction itself. Completion of the project is
generally estimated at summer 2012, with an up to 18-month construction period.
As to the EIR, LSA Associates, Inc., the City's environmental consultant, has completed the Initial Study
(IS) for the proposed City Hall and Park Development Plan project. The Notice of Preparation was
distributed on April 1, 2009. The purpose of the NOP is to notify all responsible agencies and interested
parties of the City's intent to prepare an Environmental Impact Report (EIR) for the project and to solicit
comments and suggestions regarding the preparation of the EIR. The required 30-day public comment
period will conclude on April 30, 2009. The next step of the process is the preparation of the Draft EIR,
which will include a detailed and thorough analysis of all environmental aspects of the project consistent
with the requirements of the California Environmental Quality Act (CEQA). It is anticipated that the Draft
EIR will be distributed for public review and comments by September 1, 2009 to meet the November 24,
2009 planned certification date.
Staff: Dave Kiff, Steve Badum, Sharon Wood, Jaime Murillo
PROVIDE MORE PUBLIC PARKS AND RECREATION FACILITIES,
WITH EMPHASIS ON ACTIVE FACILITIES WHERE APPROPRIATE;
CONSTRUCT A NEW OASIS FACILITY FOR OUR SENIORS
Sunset Ridge Park — obtain PB &R and June 24, 2008
PB &R approved May 20,
Council conceptual approvals
2008; Council approved June
10, 2008
Begin CEQA and final design processes
November 25, 2008
Awarded contract to EIR
consultant and architect; in
process
Determination of MND or EIR process
March 15, 2009
City will process an EIR
Environmental clearance for park based on
June 2010
On Target
EIR
Coastal Commission permit approval
February 2011
expected (after EIR finalized)
Award bid after preparation of construction
June 2011
documents and bidding
Park open for public use
December 2012
Marina Park — conceptual plans prepared
June 31, 2008
Council approved on Nov. 13,
and approved by PB &R, City Council
2007; PB &R approved
December 14, 2007
EIR public review period
Feb. 23 -April 2, 2009
Achieved
City Council EIR hearing
May -June, 2009
On Target
Environmental clearance expected
September, 2009
i Completion of construction plans and
August 2010
specs, all water quality permits, Army
Corps, etc.
Advertise, bid and award multiple
November 2010
construction contracts for specialized
contractors
Construction completed and open for
December 2014
public use
k ParFcompany rmits
February 10, 2008
Approved February 5, 2008
perioMay
Edayconstruction
-March 2009
Construction complete
ersee
structiMarch
-June 2009
On Target
maintenance p eriod
City assumes ownership of park and June 2009
continues maintenance period
Open to public use
September 2009
OASIS Rebuild - construction out to bid
Jan. 12 - Feb. 12, 2009
Bid opening Feb. 12, 2009
Award construction bid
March 10, 2009
Awarded March 10, 2009
Construction of project
March 2009 -Oct. 2010
Currently under Construction
Construction completed and open for
October 2010
public use
Banning Ranch Community Park—
Sept. 2008
Application submitted
development application submitted
Discuss Community Park plans including
Ongoing
Ongoing
size, location and improvements with
developer
Synthetic Turf Study — RFP for
December 2008
Proposals received Dec. 19,
consultant services
2008
Award of consultant contract for $23,000
February 2009
Study Awarded to CMX Sports
Engineers on April 2, 2009
Phase I- study of existing park sites for
February-April 2009
Revise to April — June 09
usage recommendations
PB &R Commission — presentation of study
May 2009
Revise to July 09
findings
Presentation to Council of study findings
June 2009
Revise to August 09
and determination of whether to proceed
with plans and specs
CYC- Renovation — project out to
December 2008
Bids received January 6, 2009
construction bid
Award construction bid
January 2009
Bid awarded January 27, 2009
Construction of project
February -June 2009
Currently under construction
Construction completed and open for
June 22, 2009
public use
Comments: Most of these projects are continuations of the related 2008 Council priority and most involve
multi -year planning, processing and construction.
Staff: Laura Detweiler, Dave Webb
CONTINUE WITH THE PROCESS TO DETERMINE EVENTUAL
LAND USE FOR THE BANNING RANCH PROPERTY,
PURSUING BOTH OPEN SPACE AND DEVELOPMENT OPTIONS
OUTLINED IN THE GENERAL PLAN
Open Space
City Council receipt of appraisal report
January 27, 2009
Provided January 27, 2009
Resource Opportunity Group report to Ad
May 8, 2009
to begin environmental review,
Hoc Committee on funding availability
and will be supplemented as
Meeting with interested parties to discuss
April 23, 2009
ROG met with representatives
funding availability
March 9 - April 9, 2009
of Banning Ranch
Conservancy
City Council receipt of funding availability
May 26, 2009
2009
report, and direction to Ad Hoc Committee
November 2 - December
on next steps
16, 2009
Comments: Interested parties have been slow to arrange meetings with ROG, as provided by City
Council in January. Both City and Conservancy submitted requests for Measure M environmental funding
to OCTA, and City supported Conservancy's request as consistent with our own.
Development
City receipt of complete application
January 21, 2009
Application material sufficient
material
to begin environmental review,
and will be supplemented as
review process proceeds
NOP public review period
March 9 - April 9, 2009
NOP released March 16;
review period ended April 17,
2009
Draft EIR public review period
November 2 - December
16, 2009
Planning Commission recommendations
April 22, 2010
on development application
Final City Council action on development
June 8, 2010
application
Comments: The two processes — determining whether Banning Ranch can be purchased and preserved
for open space and the development of Banning Ranch as a residential project — are being processed
concurrently in order to determine at the end of both processes which alternative is most feasible.
Development schedule depends on receipt of final project information from applicant and amount of
required review by outside agencies.
Staff: Sharon Wood
L,
CONTINUE TO IMPLEMENT WATER QUALITY IMPROVEMENT
PROJECTS, WHILE AT THE SAME TIME ASSESSING THE NEED TO
ADOPT A TIERED WATER RATE STRUCTURE TO ASSIST IN WATER
CONSERVATION EFFORTS
Bring forth a draft Water Quality
March 2009
Not completed yet. Key to
Management Plan (WQMP) to City
plan's completion is Federal
Council which identifies fiscal impacts
government's pending
determination on Stimulus
funding for Upper Newport
Bay.
Establish Council ad hoc Committee on
March 2009
Not completed yet. Planned
Water Use. Purpose is to assistfreview
for May 2009. However, City
staff action relating to potable water
staff has been able to attend
purchases and use in the city (with OCWD
all relevant OCWD and
and MWDOC).
MWDOC Water Producers
meetings.
Consider certain aspects of the WQMP in
May 2009
the context of the 2009 -2010 Fiscal Year
Budget.
Update the City's Water Master Plan (for
May 2009
Update of Water Master Plan
potable water delivered to homes, city
Completed
facilities, and businesses). Determine if
existing rate structure will accomplish the
Plan, including likely increases in water
purchasing costs. If not, recommend rate
changes.
Continue City's water conservation efforts
Ongoing
via Water Conservation Coordinator.
Direct WCC and Utilities Director to follow
and update City on other jurisdiction's
actions relating to tiered rate structures.
Implement any rate changes based on the
July 2009
Water Master Plan's needs. Evaluate the
city's obligations relating to rate changes
under Proposition 208.
Study how the updated Water Master
May 2009 to October
Plan's needs could be addressed with a
2009
tiered -rate structure (to encourage
conservation).
Determine whether to implement a Tiered
October 2009
Rate structure, and suggest the timing
thereof.
VA
Comments: At first glance, these are two separate goals. But because excessive water use outside of
homes and businesses causes urban runoff, and urban runoff has a major impact on water quality in our
Bay and Ocean, the two issues are tied together.
One challenge in this Priority is to analyze the pros and cons of a Tiered Water Rate (a rate structure that
rewards conservation but penalizes overuse) while the City enters a year of water supply uncertainty.
Many believe that prolonged drought will force our water suppliers (the Orange County Water District and
the Metropolitan Water District of Orange County) to ration water. At the same time, rates charged to the
City for water purchases have gone up and will continue to go up. City staff believes that a current review
of the Water Master Plan, a plan that tells the City what water distribution facilities need upgrading and
recommends an order for these upgrades, will tell us that we cannot sustain the WMP's needs with the
current water rates.
Therefore, for several reasons, a rate increase is likely to be needed — and likely to be needed before the
City can adequately study going to a tiered rate system. The tiered -rate study necessarily will include
impacts to the water billing system — including its software, meters, meter reading, and more. Therefore,
it is likely that staff will come to the City Council with a rate increase based on the current rate structure
followed by a recommendation on applying that rate increase across a rate structure different from what
we have today. If there is a simpler way to both accommodate the needs of the Water Master Plan and
appropriately address suggested conservation -based rate structures at the same time, we will do so.
Staff: Dave Kiff, George Murdoch, Shane Burckle, Dave Webb, Bob Stein
DEVELOP AND IMPLEMENT A STRATEGY, INCLUDING A FUNDING
COMPONENT, FOR THE DREDGING OF THE LOWER BAY
Advocate in Washington DC and with the
February 2009 to May
DC advocate Jim Crum has
US Army Corps of Engineers (LA District)
2009
been involved in this
for the Corps' consideration of a Lower
discussion. As of the date of
Newport Bay (LNB) dredging project within
this report, no news yet on
the Economic Stimulus Package (American
Stimulus funding for the Upper
Recovery and Reinvestment Plan of 2009).
Bay. Because of "shovel -
ready" requirement, City is
seeking Federal FY 10
appropriations for LNB.
Council Member Daigle went
to DC on this matter March 4-
5, 2009.
Continue City's current work on toxicity
Ongoing
City Council heard a
testing of the LNB and its analysis of the
presentation about the CAD at
possible use of a Confined Aquatic Disposal
its April 14, 2009 Study
(CAD) site for certain materials.
Session.
Develop project alternatives (including
May 2009
Staff to develop with the
funding) for the LNB, including a range of
consultation and advice of:
options as follows:
• Harbor Commission
• No federal funding.
• Coastal -Bay Committee
• 100% federal funding of the Federal
• Bay Issues Committee
Navigational Channel.
• Corps staff
• The "one and done" plan (encourage
. Consultants (Larry Paul,
the Corps to fund a complete dredging
Tom Rossmiller, Jim
project then remove the obligation from
I
Crum)
the Corps' operations and maintenance
i
list).
• Other alternatives in between the
above.
Consider any possible alternatives and
May 2009
funding recommendations within the City's
FY 2009 -2010 budget.
When Stimulus Package is adopted,
February 2009 and
See above.
advocate before the Corps for LNB project
onward
implementation (within the Corps' O&M
allocation).
Directly assist Corps with any studies,
Ongoing
City's current testing and CAD
environmental reports, or permitting
analysis has the City taking
required with the LNB project.
the lead on these issues,
pending any Congressional
authorization for the US Army
L_
Corps to work on them.
Comments: A Lower Newport Bay Dredging Project is a long- hoped -for goal of the community, given the
expanse of shoaling in the Harbor. A full project may cost in the range of $15 -20 million. The City has
attempted to jump -start a future project by advancing much of the testing and analysis that the Corps will
have to do before an LNB project is shovel - ready. The City is optimistic that the Corps will receive a large
amount of appropriation in any Economic Stimulus Package within the new Congress. Some of this is
likely to go to the Upper Bay Ecosystem Restoration Project, which would enable the City to focus its
federal FY 2010 appropriations requests on securing Corps funding for dredging the Lower Newport Bay.
Dredging the LNB is not a "new" project for the Corps. It is an ongoing, current Operations and
Maintenance ( "O &M ") Corps obligation (yet one that the Corps has consistently zeroed out in funding).
As such, the prospects look better than usual for getting the project done in 2009 or 2010, if this project
competes successfully against other Corps O &M needs.
Staff: Dave Kiff, Chris Miller, Larry Paul (consultant), Jim Crum (DC advocate)
10
4/,?
COUNCIL PRIORITY
I ------------- u ----------
CONTINUE TO IMPLEMENT AN
EFFECTIVE TRAFFIC MANAGEMENT
PLAN BY A VARIETY OF PROJECTS
WHICH IMPROVE TRAFFIC FLOWS
THROUGHOUT THE CITY
Objective
Target
Action
Phase 1 signal project completed and
March 15, 2009
Project was completed and
operational
operational on March 15, 2009
Phases 2 and 3 signal project designs
March 30, 2009
Design Complete.
completed, work begins
Construction contract awarded
April 14, 2009
Phases 2 and 3 — Completed and
December 31, 2009
operational
Council discussion on Phases 4 -8 as
March 24, 2009
FY 09 -10 currently includes
whether to accelerate design and
funding for design and
construction
construction of Phases 4 & 7
Staff recommends projects which facilitate
May 12, 2009
FY 09 -10 currently includes
traffic flows in FY 09 -10 CIP budget
the Jamboree/73 Bridge
widening and Improvements to
the Jamboree /MacArthur
Intersection
Council approves new CIP budget with
June 23,2009
project schedules
Staff reports to Council as to status of CIP
November 24, 2009
traffic related projects
Comments: As discussed at the Council's priority setting meeting, to accelerate the design and construction of
Phases 4 -8 would cost approximately $4M, so Council may want to consider accelerating some or all of the Phases,
depending on how funding could be accommodated.
This priority includes staff proposing CIP projects which might result in additional turn lanes, street widening, turn-
outs and other measures which could translate into improved traffic circulation for particular problematic locations.
COUNCIL PRIORITY
COMPLETE THE SCHEMATIC DESIGN
PHASE AND THE EIR FOR THE NEW
CITY HALL AND PARK SITE
Objective
Target
Action
Hire City Hall & Park architect (BCJ)
January 2009
Achieved
Hire City Hall & Park Project Management
Firm (CW Driver)
January 2009
January 2009
April 15, 2009
November 24, 2009
Achieved
Hire City Hail & Park EIR Consultant (LSA)
Complete Concept Plan Phase
Complete Schematic Design Phase and
adopt Final EIR
Achieved
Achieved
Comments: The City Hall and Park Design project is well underway in 2009, with design team
meetings held weekly. City staff and the design team presented a concept plan for the City
Hall and Park to City Council on April 14, 2009. The rest of 2009 will be the Schematic Design
phase, including at least one public meeting during summer 2009. 2010 will include the
"Design Development" and construction documentation phases, which precede bidding and
construction itself. Completion of the project is generally estimated at summer 2012, with an
up to 18 -month construction period.
As to the EIR, LSA Associates, Inc., the City's environmental consultant, has completed the
Initial Study (IS) for the proposed City Hall and Park Development Plan project. The Notice of
Preparation was distributed on April 1, 2009. The purpose of the NOP is to notify all
responsible agencies and interested parties of the City's intent to prepare an Environmental
Impact Report (EIR) for the project and to solicit comments and suggestions regarding the
preparation of the EIR. The required 30 -day public comment period will conclude on April 30,
2009. The next step of the process is the preparation of the Draft EIR, which will include a
detailed and thorough analysis of all environmental aspects of the project consistent with the
requirements of the California Environmental Quality Act (CEQA). It is anticipated that the
Draft EIR will be distributed for public review and comments by September 1, 2009 to meet the
November 24, 2009 planned certification date.
COUNCIL PRIORITY
----- uu--- .-. -1
PROVIDE MORE PUBLIC PARKS AND
RECREATION FACILITIES, WITH
EMPHASIS ON ACTIVE FACILITIES
WHERE APPROPRIATE;
CONSTRUCT A NEW OASIS FACILITY
FOR OUR SENIORS
Objective
Target
Action
Sunset Ridge Park — obtain PB &R and
June 24, 2008 PB &R approved May 20, 2008;
Council conceptual approvals
Council approved June 10, 2008
November 25, 2008 Awarded contract to EIR
Begin CEQA and final design processes
consultant and architect; in
process
Determination of MND or EIR process March 15, 2009
City will process an EIR
On Target
Environmental clearance for park based on June 2010
EIR
Coastal Commission permit approval
February 2011
expected (after EIR finalized)
Award bid after preparation of construction
June 2011
documents and bidding
Park open for public use
December 2012
Marina Park — conceptual plans prepared and
June 31, 2008
Council approved on Nov. 13,
approved by PB &R, City Council
2007; PB &R approved December
14,2007
EIR public review period
Feb. 23 -April 2, 2009
Achieved
City Council EIR hearing
May -June, 2009
On Target
Environmental clearance expected
September, 2009
Completion of construction plans and specs,
August 2010
all water quality permits, Army Corps, etc.
Advertise, bid and award multiple construction
November 2010
contracts for specialized contractors
Construction completed and open for public
December 2014
use
Objective Target Action
Coastal Peak Park - construction permits February 10, 2008 Approved February 5, 2008
approved
Construction period with The Irvine Company
May -March 2009
Construction complete
overseeing and paying for construction
120 day construction company maintenance
March -June 2009
On Target
period
City assumes ownership of park and
June 2009
continues maintenance period
Open to public use
September 2009
OASIS Rebuild - construction out to bid
Jan. 12 - Feb. 12, 2009
Bid opening Feb. 12, 2009
Award construction bid
March 10, 2009
Awarded March 10, 2009
Construction of project
March 2009 -Oct. 2010
October 2010
Currently under Construction
Construction completed and open for public
use
Banning Ranch Community Park —
Sept. 2008
Application submitted
development application submitted
Discuss Community Park plans including
Ongoing
Ongoing
size, location and improvements with
developer
Completion of construction plans and specs,
August 2010
all water quality permits, Army Corps, etc.
Advertise, bid and award multiple construction
November 2010
contracts for specialized contractors
Construction completed and open for public
December 2014
use
Objective
Target -
Action
_
Synthetic Turf Study — RFP for consultant
December 2008
Proposals received Dec. 19,
services
2008
Award of consultant contract for $23,000
February 2009
Study Awarded to CMX Sports
Engineers on April 2, 2009
Phase I- study of existing park sites for usage
February-April 2009
Revise to April — June 09
recommendations
May 2009
Revise to July 09
PB &R Commission — presentation of study
findings
Revise to August 09
Presentation to Council of study findings and
June 2009
determination of whether to proceed with
plans and specs
December 2008
Bids received January 6, 2009
CYC- Renovation — project out to
construction bid
Award construction bid
January 2009
February -June 2009
Bid awarded January 27, 2009
Currently under construction
Construction of project
Construction completed and open for public
June 22, 2009
use
Comments: Most of these projects are continuations of the related 2008 Council priority and
most involve multi -year planning, processing and construction.
COUNCIL PRIORITY
CONTINUE WITH THE PROCESS TO
DETERMINE EVENTUAL
LAND USE FOR THE BANNING RANCH
PROPERTY, PURSUING BOTH OPEN
SPACE AND DEVELOPMENT OPTIONS
OUTLINED IN THE GENERAL PLAN
Open Space
Objective
Target
January 27, 2009
Action
City Council receipt of appraisal report
Provided January 27, 2009
Resource Opportunity Group report to Ad
May 8, 2009
Hoc Committee on funding availability
Meeting with interested parties to discuss
April 23, 2009
ROG met with representatives
funding availability
of Banning Ranch
Conservancy
City Council receipt of funding availability
May 26, 2009
report, and direction to Ad Hoc Committee
on next steps
Comments: Interested parties have been slow to arrange meetings with ROG, as provided by City
Council in January. Both City and Conservancy submitted requests for Measure M environmental
funding to OCTA, and City supported Conservancy's request as consistent with our own.
Development
Objective Target Action
City receipt of complete application January 21, 2009 Application material sufficient
material to begin environmental review,
and will be supplemented as
review process proceeds
NOP public review period
March 9 - April 9, 2009
NOP released March 16;
review period ended April 17,
2009
Draft EIR public review period
November 2 - December
16, 2009
Planning Commission recommendations
April 22, 2010
on development application
Final City Council action on development
June 8, 2010
application
Comments: The two processes — determining whether Banning Ranch can be purchased and
preserved for open space and the development of Banning Ranch as a residential project — are
being processed concurrently in order to determine at the end of both processes which alternative
is most feasible. Development schedule depends on receipt of final project information from
applicant and amount of required review by outside agencies.
COUNCIL PRIORITY
------- -------------- 0 --------- -- -
CONTINUE TO IMPLEMENT WATER
QUALITY IMPROVEMENT PROJECTS,
WHILE AT THE SAME TIME ASSESSING
THE NEED TO ADOPT A TIERED WATER
RATE STRUCTURE TO ASSIST IN WATER
CONSERVATION EFFORTS
Objective
Target
Action
Bring forth a draft Water Quality
March 2009
Not completed yet. Key to
Management Plan (WQMP) to City
plan's completion is Federal
Council which identifies fiscal impacts
government's pending
determination on Stimulus
funding for Upper Newport
Bay.
Establish Council ad hoc Committee on
March 2009
Not completed yet. Planned
Water Use. Purpose is to assist/review
for May 2009. However, City
staff action relating to potable water
staff has been able to attend
purchases and use in the city (with OCWD
all relevant OCWD and
and MWDOC).
MWDOC Water Producers
meetings.
Consider certain aspects of the WQMP in
May 2009
the context of the 2009 -2010 Fiscal Year
Budget.
Update the City's Water Master Plan (for
May 2009
Update of Water Master Plan
potable water delivered to homes, city
Completed
facilities, and businesses). Determine if
existing rate structure will accomplish the
Plan, including likely increases in water
purchasing costs. If not, recommend rate
changes.
Continue City's water conservation efforts
Ongoing
via Water Conservation Coordinator.
Direct WCC and Utilities Director to follow
and update City on other jurisdiction's
actions relating to tiered rate structures.
Implement any rate changes based on the
July 2009
Water Master Plan's needs. Evaluate the
city's obligations relating to rate changes
under Proposition 208.
Study how the updated Water Master
May 2009 to October
Plan's needs could be addressed with a
2009
tiered -rate structure (to encourage
conservation).
Determine whether to implement a Tiered
October 2009
Rate structure, and suggest the timing
thereof.
Comments: At first glance, these are two separate goals. But because excessive water use outside of homes and businesses
causes urban runoff, and urban runoff has a major impact on water quality in our Bay and Ocean, the two issues are tied together.
One challenge in this Priority is to analyze the pros and cons of a Tiered Water Rate (a rate structure that rewards conservation but
penalizes overuse) while the City enters a year of water supply uncertainty. Many believe that prolonged drought will force our
water suppliers (the Orange County Water District and the Metropolitan Water District of Orange County) to ration water. At the
same time, rates charged to the City for water purchases have gone up and will continue to go up. City staff believes that a current
review of the Water Master Plan, a plan that tells the City what water distribution facilities need upgrading and recommends an
order for these upgrades, will tell us that we cannot sustain the WMP's needs with the current water rates.
Therefore, for several reasons, a rate increase is likely to be needed — and likely to be needed before the City can adequately
study going to a tiered rate system. The tiered -rate study necessarily will include impacts to the water billing system — including its
software, meters, meter reading, and more. Therefore, it is likely that staff will come to the City Council with a rate increase based
on the current rate structure followed by a recommendation on applying that rate increase across a rate structure different from
what we have today. If there is a simpler way to both accommodate the needs of the Water Master Plan and appropriately address
suggested conservation -based rate structures at the same time, we will do so.
COUNCIL PRIORITY
DEVELOP AND IMPLEMENT A
STRATEGY, INCLUDING A FUNDING
COMPONENT, FOR THE DREDGING
OF THE LOWER BAY
Objective
Target
Action
Advocate in Washington DC and with the US
February 2009 to May 2009
DC advocate Jim Crum has been
Army Corps of Engineers (LA District) for the
involved in this discussion. As of
Corps' consideration of a Lower Newport Bay
the date of this report, no news
(LNB) dredging project within the Economic
yet on Stimulus funding for the
Stimulus Package (American Recovery and
Upper Bay. Because of "shovel -
Reinvestment Plan of 2009).
ready" requirement, City is
seeking Federal FY 10
appropriations for LNB. Council
Member Daigle went to DC on this
matter March 4 -5, 2009.
Continue City's current work on toxicity testing of
Ongoing
City Council heard a presentation
the LNB and its analysis of the possible use of a
about the CAD at its April 14,
Confined Aquatic Disposal (CAD) site for certain
2009 Study Session.
materials.
Develop project alternatives (including funding)
May 2009
Staff to develop with the
for the LNB, including a range of options as
consultation and advice of:
follows:
• Harbor Commission
• No federal funding.
• Coastal -Bay Committee
100% federal funding of the Federal
0 Bay Issues Committee
Navigational Channel.
• Corps staff
• The "one and done" plan (encourage the
• Consultants (Larry Paul,
Corps to fund a complete dredging project then
Tom Rossmiller, Jim Crum)
remove the obligation from the Corps'
operations and maintenance list).
Other alternatives in between the above.
Consider any possible alternatives and funding
May 2009
recommendations within the City's FY 2009-
2010 budget.
When Stimulus Package is adopted, advocate
February 2009 and onward
See above.
before the Corps for LNB project implementation
(within the Corps' O &M allocation).
Directly assist Corps with any studies,
Ongoing
City's current testing and CAD
environmental reports, or permitting required
analysis has the City taking the
with the LNB project.
lead on these issues, pending any
Congressional authorization for
the US Army Corps to work on
them.
Comments: A Lower Newport Bay Dredging Project is a long- hoped -for goal of the community, given the
expanse of shoaling in the Harbor. A full project may cost in the range of $15 -20 million. The City has
attempted to jump -start a future project by advancing much of the testing and analysis that the Corps will
have to do before an LNB project is shovel- ready. The City is optimistic that the Corps will receive a
large amount of appropriation in any Economic Stimulus Package within the new Congress. Some of this
is likely to go to the Upper Bay Ecosystem Restoration Project, which would enable the City to focus its
federal FY 2010 appropriations requests on securing Corps funding for dredging the Lower Newport Bay.
Dredging the LNB is not a "new" project for the Corps. It is an ongoing, current Operations and
Maintenance ( "O &M ") Corps obligation (yet one that the Corps has consistently zeroed out in funding).
As such, the prospects look better than usual for getting the project done in 2009 or 2010, if this project
competes successfully against other Corps O &M needs.