Loading...
HomeMy WebLinkAbout08 - Balboa Village Alley ReplacementCITY OF NEWPORT BEACH CITY COUNCIL STAFF REPORT Agenda Item No. 8 June 23, 2009 TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL FROM: Public Works Department Alfred Castanon, Associate Civil Engineer 644 -3314 or acastanon @city.newport- beach.ca.us SUBJECT: BALBOA VILLAGE ALLEY REPLACEMENT— COMPLETION AND ACCEPTANCE OF CONTRACT NO. 3944 Recommendations: 1. Accept the completed work and authorize the City Clerk to file a Notice of Completion. 2. Authorize the City Clerk to release the Labor and Materials bond 35 days after the Notice of Completion has been recorded in accordance with applicable portions of the Civil Code. 3. Release the Faithful Performance Bond 1 year after Council acceptance. Discussion: On January 13, 2009 the City Council authorized the award of the Balboa Village Alley Replacement project to Golden State Constructors, Inc. The contract provided for the removal of the existing asphalt and concrete alleys, raising existing utilities to grade, and constructing new 8 -inch thick concrete alleys. In addition, a portion of the concrete pavement on "A" Street between Balboa Boulevard and the Oceanfront sidewalk was reconstructed. The contract has now been completed to the satisfaction of the Public Works Department. A summary of the contract cost is as follows: Original bid amount: $128,606.00 Actual amount of bid items constructed: $132,540.52 Total amount of change order: $10,187.68 Final contract cost: $142,728.20 The increase in the actual amount of bid items constructed over the original bid amount resulted from additional concrete construction requested by City staff. This additional concrete construction allowed for a better tie into the alley's existing pavement and was made possible due to good bid pricing. In addition, there were four change orders totaling $10,187.68. The change orders were for the following: Balboa Village Alley Replacement- Completion and Acceptance of Contract No. 3944 June 23, 2009 Page 2 Change Order Description Amount 1 Replacement of 6 bollards in Alley 256 -V. $1,500.00 2 Delay costs due to design change in the field. $2,869.51 3 Delay costs due to design change in the field. $2,702.28 4 Additional sawcut and painting red curb, additional traffic control. $3,115.89 Total Project Change Orders $10,187.68 The final overall construction cost including four Change Orders was 11 percent over the original bid amount. A summary of the project schedule is as follows: Estimated completion date per June 08' schedule: May 22, 2009 Project award for construction: January 13, 2009 Estimated completion date at award: May 8, 2009 Actual substantial construction completion date: May 7, 2009 All work was substantially completed by May 7th, fifteen days ahead of the scheduled completion date of May 22, 2009. Environmental Review: The project was exempt from the California Environmental Quality Act (CEQA) pursuant to Section 15301 of the CEQA Implementation Guidelines when the project was authorized by the City Council. This exemption covers the repair, maintenance and minor alteration of existing public facilities with negligible expansion. Funding Availability: In addition to the primary construction contract, this project involved other project expenses. Total project expenses are summarized as follows: Construction $142,728.20 Surveying $22,610.00 Geotechnical Testing $1,409.00 Incidentals $350.66 Total Project Cost $167,097.86 Balboa Village Alley Replacement- Completion and Acceptance of Contract No. 3944 June 23, 2009 Page 3 Funds for the construction contract were expended from the following accounts: Account Description Account Number Amount General Fund 7013- C5100277 $25,290.00 Assessment District No. 75 Funds 74075 -9804 $78,522.20 Water Enterprise Fund 7501- C5100277 $38,916.00 Total: $142,728.20 Prepared by: Submitted Alfrd,d Castanon S p G. Badum Associate Civil Engineer u c Works Director