HomeMy WebLinkAbout24 - Review of Six City Council PrioritiesCITY OF NEWPORT BEACH
CITY COUNCIL STAFF REPORT
Agenda Item No. 24
September 22, 2009
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: City Manager's Office
Dave Kiff, City Manager
949/644 -3000 or dkiff@newportbeachca.gov
SUBJECT: Council Review of Staff Status Report on Six of the City Council's
2009 Priorities
ISSUE:
How is the City staff doing in terms of implementing the City Council's thirteen 2009
priorities?
RECOMMENDATION:
Review and comment, as desired.
DISCUSSION:
Background:
The City Council held a Special City Council meeting on Saturday, January 10, 2009, to
discuss and establish its priorities for 2009. This was the third consecutive year the City
Council has met early in the calendar year to set its priorities. A total of thirteen (13)
priorities were settled on, but in no particular order. As in the past, the City Manager
was asked to provide draft priority statements, action steps and schedules for the City
Council to review, make revisions to and finalize.
The status of priority implementation is reviewed each month. Status reports on seven
priorities began in March and are provided during alternating months. This status report
provides current information on the remaining six priorities. This is the sixth status report
of the year. The six priorities being reported on in no particular order are as follows:
• Continue to implement an effective traffic management plan by a variety of projects
which improve traffic flows throughout the City.
City Council Priorities
September 22, 2009
Page 2
• Complete the Schematic Design Phase and the EIR for the new city hall and park
site.
• Provide more public parks and recreation facilities, with emphasis on active facilities
where appropriate. Construct a new OASIS facility for our seniors.
• Continue with the process to determine the eventual land use for the Banning Ranch
property, pursuing both open space and development options outlined in the
General Plan.
• Continue to implement water quality improvement projects, while at the same time,
assessing the need to adopt a tiered water rate structure to assist in water
conservation efforts.
• Develop and implement a strategy, including a funding component, for the dredging
of the Lower Bay
Additional status reports will be provided at the second City Council meeting of each
month for the remainder of the calendar year.
Environmental Review: The City Council's approval of this Agenda Item does not
require environmental review.
Public Notice: This agenda item has been noticed according to the Brown Act (72 hours
in advance of the meeting at which the Council considers the item).
Submitted by:
L
DAVE KIFF
City Manager
Attachments: 2009 Council Priorities Indicator Tracker
City of Newport Beach
2009 Council Priorities Indicator
Tracker
Status Report
Date published: September 22, 2009
Presented by: Dave Kiff
CONTINUE TO IMPLEMENT AN EFFECTIVE TRAFFIC MANAGEMENT
PLAN BY A VARIETY OF PROJECTS WHICH IMPROVE TRAFFIC
FLOWS THROUGHOUT THE CITY
2
Phase 1 signal project completed and March 15, 2009
:Project was completed and
operational
;operational on March 15, 2009
Phases 2 and 3 signal project designs March 30, 2009
Design Complete.
completed, work begins !
Construction contract awarded
April 14, 2009
_.—._.. -.... __ _
Phases 2 and 3 - Completed and December 31, 2009
j On target
operational
Council discussion on Phases 4 -8 as March 24, 2009
FY 09 -10 currently includes
whether to accelerate design and
;funding for design and
construction
construction of Phases 4 & 7.
Council confirmed this
direction at the June 911h Study
'. Session.
rSta:ff recommends projects which facilitate May 12, 2009
FY 09 -10 currently includes
traffic flows in FY 09 -10 CIP budget
the Jamboree/73 Bridge
i widening and Improvements to
i the Jamboree /MacArthur
Intersection
--
Council approves new CIP budget with June 23,2009
~Adopted as planned.
project schedules
..- .. . ----------- .. --- ..... .
Staff reports to Council as to status of CIP November 24 2009
traffic related projects
----------- ._
Comments: As discussed at the Council's priority setting meeting,
to accelerate the design and
construction of Phases 4 -8 would cost approximately $4M. Expanding to do additional phases was
discussed on June 9` ", however, Council and staff believe it is more prudent to continue on the schedule
that has been previously developed and is being implemented.
This priority includes staff proposing CIP projects which might result
in additional turn lanes, street
widening, turn -outs and other measures which could translate into
improved traffic circulation for
particular problematic locations.
Staff: Steve Badum; Dave Webb
2
COMPLETE THE SCHEMATIC DESIGN PHASE AND THE EIR FOR THE
NEWPORT BEACH CIVIC CENTER
Hire Civic Center architect (BCJ)
I January 2009
Achieved
Hire Civic Center Project Management
January 2D09
Achieved
Firm (CW Driver)
�
Hire Civic Center EIR Consultant (LSA)
January 2009 ~�
Achieved
Complete Concept Plan Phase
t___..._.
April 15, 2009
Achieved
-... _ ---- -- -_-- -- _ .. -- -- --
Public Comment Period for Draft EIR
- - - - -- - - - - - ---
( September 1, 2009
Achieved (public comment
period runs through mid-
__.. -- _ _. - -.__ _, .- .. . ... __ __
October 2009)
. . .... . ......
City Council Approval of Schematic Design
, November 24 2009
On schedule
and adopt Final EIR
_---.___--.____...-..____.-.__.-_.-._----.__.___.----.,__
a-._._. ._- ____._.- _------ --- ..-- -______.
_— , --- - .- _�.._._
Comments: The Civic Center project is well underway in 2009, with design team meetings held by
conference call each week, and in person meetings for two to three days every three weeks. City staff
and the design team presented a concept plan for the Civic Center on April 14, 2009. The rest of 2009
involves the Schematic Design and early Design Development phases, including at least one public
meeting of the Design Committee set for 6:30 p.m. on Wednesday, September 30, 2009 in the City
Council Chambers. Much of 2010 will include the "Design Development" and construction documentation
phases, which precede bidding and construction itself. But there is a strong likelihood of an "early start"
of mass excavation of the site, even as soon as early in 2010, if we can find a willing taker of the clean fill
that will come from the site.
Completion of the Civic Center project is generally estimated at summer 2012, with an up to 18 -month
construction period.
The Civic Center Draft EIR is out for public review at this time, with the review period anticipated to
conclude in mid - October 2009.
Staff: Steve Badum, Jaime Murillo, Sharon Wood, Dave Kiff
PROVIDE MORE PUBLIC PARKS AND RECREATION FACILITIES,
WITH EMPHASIS ON ACTIVE FACILITIES WHERE APPROPRIATE;
CONSTRUCT A NEW OASIS FACILITY FOR OUR SENIORS
Sunset Ridge Park - obtain PB &R and June 24, 2008 PB &R approved May 20,
Council conceptual approvals l 2008; Council approved June
10, 2008
-- __
__
Begin CEQA and final design processes November 25 2008 ' Awarded contract to EIR
consultant and architect in
process
. __. .__ ._
Determination of MND or EIR process i March 15, 2009 i City has decided to process an
EIR
__ „__. __. _ __ ----- ............ _ _ --------------- _ __
City Council EIR Hearing for Approval January 2010 On target
— _ ,
Coastal Commission permit approval July 2010
expected (after EIR finalized) i
- - -__ - -___ ...... . -__t. ... .........
Award bid after preparation of construction September 2010
documents and bidding
! ..._. ------------ _ _ _ __ --------------- - _._.- ...... .. -. — _. --------------- _ __..__.... .- -----
Park open for public use March 2012
Marina Park - conceptual plans prepared F June 30, 2008 Council approved on Nov. 13,
and approved by PB &R, City Council 2007; PB &R approved
{ December 14, 2007
i EIR public review period Feb. 23 -April 2, 2009 Achieved
Re- circulated EIR public review period November 9 - December Added Phases 1 & 2 and
23, 2009 needed to address CCC
wetland delineation of beach
City Council EIR Hearing for Approval I
February July 2009 2010
_ ...
_ _.. _.__. __.
Completion of construction plans and Au9a6t-2Q!G Ongoing
specs, all water quality, Army Corps, November 2010
j Coastal Commission permits etc. j
...... __.____ _ -- - -_
Advertise bid and award multiple Desepaber -2019
construction contracts for specialized January 2011
contractors
___ - - - - -__ _.- - - - ___ . _ ..... _ _._ . _ _ ----
.. -i
Construction completed and open for July 2013 i
public use
Coastal Peak Park- construction permits February 10, 2008 Approved February 5, 2008
approved
Construction period with The Irvine` May -March 2009 _ Construction complete
i Company overseeing and paying for j
construction i
. _ _ _ __. __. -- -_ - ... --- . I__..__.
,, I
SHHEM
.
120 day construction company
1 March - August 2009
On target
maintenance period
City assumes ownership of park and
August 2009
.. . ........
On target
continues maintenance period
r Open to public use i
September 2009
Achieved
OASIS Rebuild - construction out to bid
Jan. 12 - Feb, 12, 2009
Bid opening Feb. 12, 2009
Award construction bid
March 10, 2009
Awarded March 10, 2009
— -------------------
Construction of project
- -----------
March 2009 Oct. 2010
------- — -------- ----------_ --
;Currently under Construction
Construction completed and open for
October 2010
On target
public use
i Banning Ranch Community Park —
Sept. 2008
Application submitted
I development application submitted
Discuss Community Park plans including
_- --- - --------
Ongoing
- -------- ----------- ------------ ------------
Ongoing
size, location and improvements with
developer
Synthetic Turf Study — RFP for
December 2008
Proposals received Dec. 19,
consultant services
2008
_ __- ---------- — --------
Award of consultant contract for $23,000
February 2009
Study Awarded to CMX Sports
Engineers on April 2, 2009
Phase I- study of existing park sites for
1 April — June 2009
Completed
usage recommendations
PB&R Commission — presentation of study
August 2009
On track for August meeting
findings
--- — ------
---------
Presentation to Council of study findings
August 2009
Achieved
and and determination of whether to proceed
with plans and specs
CYC-Renovation — project out to
December 2008
Bids received January 6, 2009
construction bid
Award construction bid
January 2009
Bid awarded January 27, 2009
Construction of project
February-June 2009
�Achieved
urrently under construction
Construction completed and open for
June 22, 2009
public use
Comments: Most of these projects are continuations of the related 2008 Council priority and most involve
multi-year planning, processing and construction.
Staff: Laura Detweiler. Dave Webb
CONTINUE WITH THE PROCESS TO DETERMINE EVENTUAL
LAND USE FOR THE BANNING RANCH PROPERTY,
PURSUING BOTH OPEN SPACE AND DEVELOPMENT OPTIONS
OUTLINED IN THE GENERAL PLAN
Open Space
E a _,. -""" r Sat
Ii y 4
Ye�,ti
i City Council receipt of appraisal report
January 27 2009
Provided January 27 2009
Resource Opportunity Group report to Ad
? July 2009
i ROG spoke with Coastal
Hoc Committee on funding availability
j
Conservancy, OCTA,
Wildtands Conservancy,
s
l Resources Legacy Fund, and
i
j
Fund Foundation; researched
applicability of stimulus funds
Meeting with interested parties to discuss
t April 23, 2009 ~
O met with representatives
;funding availability
( of Banning Ranch
Conservancy
City Council receipt of funding availability
August 11, 2009
j During the August 11, 2009
report, and direction to Ad Hoc Committee
I Study Session, Council
on next steps
suggested that staff "be open
to any new funding
i opportunities" as they present
themselves
Staff continue to search for new funding
Ongoing
Ongoing
opportunities for a purchase.
-- "- —
i
Comments: City, Conservancy and Newport Banning Ranch submitted requests for Measure M
environmental funding to OCTA; City supported all requests in testimony and letter to Environmental
Oversight Committee.
r
Development
-ts„t yam ,---
5 �a" Oil
City receipt of complete application January 21, 2009 Application material sufficient
material to begin environmental review,
and will be supplemented as
review process proceeds
---- - - - ---- - - - - -- -- -- - - - - - -- — f - -- - -- - --- - - - -- -- — ,—. --
NOP public review period March 9 - April 9, 2009 NOP released March 16;
review period ended April 17,
E 2009
. -
Draft EIR public review period November 2 - December Technical studies underway:
j f 16, 2009 ; biological resources, water
j supply assessment, traffic,
hydrology and water quality,
I geotechnical, cultural
I ! resources, fire and life safety,
j health risk analysis
Planning Commission recommendations April 22, 2010 I
on development application j
_ -- -_ —.���
Final City Council action on development 'June 8, 2010 '
application
Comments: The two processes - determining whether Banning Ranch can be purchased and preserved
for open space and the development of Banning Ranch as a residential project- are being processed
concurrently in order to determine at the end of both processes which alternative is most feasible.
Development schedule depends on receipt of final project information from applicant and amount of
required review by outside agencies.
Staff: Sharon Wood
CONTINUE TO IMPLEMENT WATER QUALITY IMPROVEMENT
PROJECTS, WHILE AT THE SAME TIME ASSESSING THE NEED TO
ADOPT A TIERED WATER RATE STRUCTURE TO ASSIST IN WATER
CONSERVATION EFFORTS
Bring forth a draft Water Quality I March 2009 With the UNB funded and the
Management Plan (WQMP) to City LNB having an appropriation
Council which identifies fiscal impacts j for the first time, Staff will re-
evaluate the WQMP and bring
it back to Coastal-Bay before
Council.
Consider the establishment of a Council ad March 2009 Not completed. However, City
hoc Committee on Water Use, Purpose is i staff has been able to attend
I to assist/review staff action relating to all relevant OCWD and
potable water purchases and use in the 1 MWDOC Water Producers
city (with OCWD and MWDOC). meetings.
— - ---------------- --------
Consider certain aspects of the WQMP in I May 2009 Aspects related to LNB GEQA
the context of the 2009-2010 Fiscal Year and testing work are funded
1: Budget. within the City's FY 2009-10
I I budget.
------------
Update the City's Water Master Plan (for I May 2009 Update of Water Master Plan
potable water delivered to homes, city completed and presented to
facilities, and businesses). Determine if Council 918109,
existing rate structure will accomplish the
Plan, including likely increases in water I Proposed rate structure
purchasing costs. If not, recommend rate includes costs associates with
changes. i Water Master Plan.
.. ------------- --- -- ---- -- ------ --- -- - -------- ........... - --------- ........ . ..
Continue City's water conservation efforts Ongoing
via Water Conservation Coordinator.
Direct WCC and Utilities Director to follow
and update City on other jurisdiction's II
i actions relating to tiered rate structures.
i - — ----------- ........ . . . . ......... . ....... .......
.................. I.I.-.11-11- ........ ____ ....... . .. __....__.1
1 Implement any rate changes based on the duly 2909 i Proposed rate structure
Water Master Plan's needs. Evaluate the January 1, 2010 i approved by Council 9/8109.
I city's obligations relating to rate changes j 1 Rate effective 111/10, pending
1 under Proposition 208. Prop 218 protest results.
.......... . . .. - ------ ------- ___ -- ---- --- -- - --- --------- -
May 2009 te OGtGbef-
Study how the updated Water Master 1 Water Master Plan costs are
i Plan's needs could be addressed with a 2009
not tied to variable portion of
tiered-rate structure (to encourage September 2009 the rates. Capital costs will be
conservation) covered in proposed fixed
fees.
I Determine whether to implement a Tiered I ClatAbAr =0
Rate structure, and suggest the timing March 2010
thereof.
----------- - __ — - ----- ---
Comments: At first glance, these are two separate goals. But because excessive water use outside of
homes and businesses causes urban runoff, and urban runoff has a major impact on water quality in our
Bay and Ocean, the two issues are tied together.
Due to court ordered water supply restrictions, on April 14, 2009, the Metropolitan Water District Board
voted to implement water allocations to all agencies that purchase water from them. Agencies are to
reduce their water purchases by 15% for fiscal year 09/10. In addition, Orange County now enters its third
year of drought (lack of rain). Because of this lack of local rainfall, our ground water supplies have been
reduced for the second year in a row. All of the above are good reasons to implement a Tiered Rate
system to encourage water conservation, however there are procedures that need to be followed per
Proposition 218.
Proposition 218 requires a full financial study to be conducted prior to any rate increase or rate
restructure. Because of the recent rate hikes from our suppliers and the fact the rates have not been
increased since 2005; staff felt it necessary to bring to Council an increase immediately to balance the
budget. Council approved the Water Utility Financial Plan and proposed rates at the September 8, 2009
meeting. As part of the Prop 218 procedure, a 45 -day notice period precedes a public hearing where if
less than the majority of the customers and property owners protest, the rates can be adopted. Balancing
the budget to match revenues and expenditures is the first step in rate setting.
Staff intends to next analyze the development of a Tiered Water Rate. Some of the challenges in
adopting Tiered Rates are: monthly meter reading and billing as opposed to bi- monthly; billing system
capabilities; development of allocations based on what calculation ?; variance procedures; customer
service; and, public education. Feasibility and costs associated will need to be discussed with Council
along the way.
The Water Master Plan is now complete and costs associated have been addressed in the current rate
proposal. The funds required to maintain our infrastructure have been proposed to be included as a
capital charge and part of the "fixed" fee. Including the capital costs in the variable portion of the rate, or
to include it in a Tiered Rate, will not be recommended due to the volatility of water use.
It should be noted that the current rate structure is considered a conservation rate as defined by the
California Urban Water Conservation Council however; Tiered Rates seem to be very effective tools in
encouraging conservation and staff will continue to pursue that goal.
Staff: Dave Kiff, George Murdoch, Shane Burckle, Dave Webb, Bob Stein
DEVELOP AND IMPLEMENT A STRATEGY, INCLUDING A FUNDING
COMPONENT, FOR THE DREDGING OF THE LOWER BAY
Comments: A Lower Newport Say Dredging Project is a long-hoped-for goal of the community, given the
expanse of shoaling in the Harbor. A full project may cost in the range of $25-29 million. The City has
attempted to jump-start a future project by advancing much of the testing and analysis that the Corps will
have to do before an LNB project is shovel-ready.
10
o 11
I Advocate in Washington DC and with the
February 2009 to May
I Achieved. President Obama's
I US Army Corps of Engineers (LA District)
for the Corps'
2009
budget included $1.78 million
consideration of a Lower
1!
for LNB Dredging, an
Newport Bay (LNB) dredging project within
important milestone for this
the Federal FY 10 budget.
project. This appears to be
the correct number for FY
2010 in terms of the Corps'
planning expenses. FY 2011
should include up to $14
-- ----------------- --
million to start construction.
-- ---- --
Continue City's current work on toxicity
-------- . ............
Ongoing
. . .. - - - - --------- - ------------
Testing continues with New
testing of the LNB and its analysis of the
Fields as the contractor. City
possible use of a Confined Aquatic Disposal
j
staff meets with New Fields
(CAD) site for certain materials.
and members of the DMIMT to
home in on areas of
contamination that will tell us
how much sediment can go to
the LA-3 offshore disposal
site. Testing results are later
than expected.
-- -- - --
Develop project alternatives (including
November 2009
Ongoing.
funding) for the LNB dredging project's
disposal alternatives, including:
Long Beach Port and LA Port fill
• Cement-based stabilization
9 Inland disposal.
• CAD site in Newport Harbor
• Offshore (LA-3) disposal,
• CAD site in Long Beach
I
---------- -------------- ___ -------- - - ------
Consider any possible alternatives and
May 2009
.................
Achieved. City's FY 09-10
funding recommendations within the City's
budget includes funding for
FY 2009-2010 budget.
some amphipod testing,
CEQA, and CAD work.
Directly assist Corps with any studies,
- --- --------
Ongoing
City's current sting and CAD
environmental reports, or permitting
analysis has the City taking
required with the LNB project.
the lead on these issues i
pending any Congressional I
authorization for the US Army
Corps to work on them.
Comments: A Lower Newport Say Dredging Project is a long-hoped-for goal of the community, given the
expanse of shoaling in the Harbor. A full project may cost in the range of $25-29 million. The City has
attempted to jump-start a future project by advancing much of the testing and analysis that the Corps will
have to do before an LNB project is shovel-ready.
10
Dredging the LNB is not a "new" project for the Corps. It is an ongoing, current Operations and
Maintenance ( "O &M ") Corps obligation (yet one that the Administration has consistently zeroed out in
funding, until this year). As such, the prospects look better than usual forgetting the project done in 2010
and 2011, if this project competes successfully against other Corps O &M needs.
Staff: Dave Kiff, Chris Miller, Larry Paul (consultant), Jim Crum (DC advocate)