HomeMy WebLinkAbout05 - Rhine Wharf Repairs & Public DockCITY OF NEWPORT BEACH CITY COUNCIL STAFF REPORT Agenda Item No. 5 October 27, 2009 TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL FROM: Public Works Department Frank Tran, Associate Civil Engineer 949 -644 -3340 or Ftran @NewportBeachCa.gov SUBJECT: RHINE WHARF REPAIRS & PUBLIC DOCK - AWARD OF CONTRACT NO. 3821 Recommendations: Approve the project drawings and specifications. Award Contract No. 3821 to Associated Pacific Constructors, Inc. for the Total Bid Price of $430,539.84 including the Base Bid Price of $374,539.84, and an Additive Bid Item 1 of $56,000, and authorize the Mayor and the City Clerk to execute the contract. 3. Establish an amount of $64,580.00 (15 %) to cover the cost of unforeseen work. Discussion: At 10:00 A.M. on October 6, 2009, the City Clerk opened and read the following bids for this project: BIDDER Low Associated Pacific Constructors, Inc. 2 John S. Meek Co. 3 R.E. Staite Engineering 4 Copper Top Enterprises 5 AIS Construction Co. • : s � : uP1�P►i� $374,539.84 $459,974.00 $530,568.00 $551,196.95 $776,500.00 Corrected Bid Amount is $457,534.00 The low total base bid amount is 25 percent below the Engineer's Estimate of $500,000. The substantial difference may be attributed to a higher level of competiveness associated with the economic downturn. The low bidder, Associated Pacific Constructors, Inc., possesses a California State Contractors License Classification "A" as required by the Rhine Wharf Repairs and Public Dock — Award of Contract No. 3821 October 27, 2009 Page: 2 project specifications. A check of the Contractor's references indicates it has satisfactorily completed similar projects for other municipalities. Because of the unusual nature of this work and the advanced age of the marine structure, Staff recommends establishing a 15% contingency to cover the cost of unforseen work. This contract is comprised of two projects. (1) Rhine Wharf Repairs: This project includes removing and replacing boardwalk support beams and planks, inspecting sheet piles and tie rods, repairing concrete sheet piles and coping, applying preservative treatment to wood decking, and upgrading guardrails. The inspection of the tie rods involves removing a strip of concrete approximately 2' -6" wide with the subgrade along the boardwalk to expose the tie rods where they connect to the coping. Once the tie rods are exposed, City Staff will determine if any tie rods need to be replaced. For any tie rod replaced, the contractor will be paid per Additive Bid Item 1. The contractor will have 45 consecutive working days to complete the work for the wharf repairs. Additional time will be allowed for any tie rod replacements. (2) Rhine Channel Public Dock: This is a design -build project. The contractor will first prepare and submit to the City a design for the precast concrete platform with guard railings, floating dock with pre- stressed concrete piles, and handicap - accessible aluminum gangway. After City review, approval, permitting, and the Notice to Proceed issued, the contractor will have 120 consecutive working days to construct the public dock. Contractor may work both projects concurrently Environmental Review: The Rhine Wharf Repairs project is exempt from the California Environmental Quality Act (CEQA) pursuant to Section 15301, Class 1 of the CEQA Guidelines. This exemption covers minor alterations of existing public facilities with negligible expansion of the facilities in areas that are not environmentally sensitive. The Public Dock project is exempt from CEQA pursuant to Section 15303, Class 3 of the CEQA Guidelines. This exemption covers construction and installation of limited numbers of new small structures. Public Notice: The Notice Inviting Bids was advertised in the City's official publication and in construction industry publications. Prior to starting work, two City prepared notices will be distributed by the contractor to both residents and businesses. The first notice will Rhine Wharf Repairs and Public Dock —Award of Contract No. 3821 October 27, 2009 Page: 3 be distributed ten days before work in the area and the second notice 48 hours prior to starting work in the area. Geotechnical and Material Testino Services: In addition to the contract costs, approximately $10,900 in geotechnical consulting and material testing services will be needed for this project and will be performed under on- call professional services agreements. $1,980.16 is included for printing and other incidentals. Funding Availability: There are sufficient funds available in the following accounts for the project: Account Description Tide and Submerged Lands Contributions Proposed uses are as follows: Vendor Associated Pacific Constructors, Inc. Associated Pacific Constructors, Inc. Harrington Geotechnical Engineering Various Prepared by: Frank Tran Associate Civil Engineer ��rrl Chris Miller Harbor Resources Manager Attachments: Project Location Map Account Number 7231- C5100921 7251- C5100865 Total: Purpose Construction Contract Construction Contingency Materials Testing Printing and Incidentals Total: Submitted by: Amount $268,000.00 $240.000.00 $508,000.00 Amount $430,539.84 $64,580.00 $10,900.00 $1,980.16 $508,000.00 Badum s Director RHINE WHARF REPAIRS & PUBLIC DOCK PROJECT C -3821 oo PROJECT LOCATION d oy �yC m CITY HALL p .. uc a VAC ISLE splo SMET F �^� LJ111L ��' n5 0 MM S1HEff ti a9M SREEi s�vru�o wa aam smEa x 8 ® Y N.T.S. S aam smcfr LOCATION MAP N.T.S.