HomeMy WebLinkAbout05 - Rhine Wharf Repairs & Public DockCITY OF NEWPORT BEACH
CITY COUNCIL STAFF REPORT
Agenda Item No. 5
October 27, 2009
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: Public Works Department
Frank Tran, Associate Civil Engineer
949 -644 -3340 or Ftran @NewportBeachCa.gov
SUBJECT: RHINE WHARF REPAIRS & PUBLIC DOCK - AWARD OF CONTRACT
NO. 3821
Recommendations:
Approve the project drawings and specifications.
Award Contract No. 3821 to Associated Pacific Constructors, Inc. for the Total Bid
Price of $430,539.84 including the Base Bid Price of $374,539.84, and an Additive
Bid Item 1 of $56,000, and authorize the Mayor and the City Clerk to execute the
contract.
3. Establish an amount of $64,580.00 (15 %) to cover the cost of unforeseen work.
Discussion:
At 10:00 A.M. on October 6, 2009, the City Clerk opened and read the following bids for
this project:
BIDDER
Low Associated Pacific Constructors, Inc.
2 John S. Meek Co.
3 R.E. Staite Engineering
4 Copper Top Enterprises
5 AIS Construction Co.
• : s � : uP1�P►i�
$374,539.84
$459,974.00
$530,568.00
$551,196.95
$776,500.00
Corrected Bid Amount is $457,534.00
The low total base bid amount is 25 percent below the Engineer's Estimate of $500,000.
The substantial difference may be attributed to a higher level of competiveness associated
with the economic downturn. The low bidder, Associated Pacific Constructors, Inc.,
possesses a California State Contractors License Classification "A" as required by the
Rhine Wharf Repairs and Public Dock — Award of Contract No. 3821
October 27, 2009
Page: 2
project specifications. A check of the Contractor's references indicates it has
satisfactorily completed similar projects for other municipalities.
Because of the unusual nature of this work and the advanced age of the marine
structure, Staff recommends establishing a 15% contingency to cover the cost of
unforseen work.
This contract is comprised of two projects.
(1) Rhine Wharf Repairs: This project includes removing and replacing boardwalk
support beams and planks, inspecting sheet piles and tie rods, repairing concrete
sheet piles and coping, applying preservative treatment to wood decking, and
upgrading guardrails. The inspection of the tie rods involves removing a strip of
concrete approximately 2' -6" wide with the subgrade along the boardwalk to expose
the tie rods where they connect to the coping. Once the tie rods are exposed, City
Staff will determine if any tie rods need to be replaced. For any tie rod replaced, the
contractor will be paid per Additive Bid Item 1. The contractor will have 45
consecutive working days to complete the work for the wharf repairs. Additional time
will be allowed for any tie rod replacements.
(2) Rhine Channel Public Dock: This is a design -build project. The contractor will first
prepare and submit to the City a design for the precast concrete platform with guard
railings, floating dock with pre- stressed concrete piles, and handicap - accessible
aluminum gangway. After City review, approval, permitting, and the Notice to
Proceed issued, the contractor will have 120 consecutive working days to construct
the public dock.
Contractor may work both projects concurrently
Environmental Review:
The Rhine Wharf Repairs project is exempt from the California Environmental Quality
Act (CEQA) pursuant to Section 15301, Class 1 of the CEQA Guidelines. This
exemption covers minor alterations of existing public facilities with negligible expansion
of the facilities in areas that are not environmentally sensitive.
The Public Dock project is exempt from CEQA pursuant to Section 15303, Class 3 of
the CEQA Guidelines. This exemption covers construction and installation of limited
numbers of new small structures.
Public Notice:
The Notice Inviting Bids was advertised in the City's official publication and in
construction industry publications. Prior to starting work, two City prepared notices will
be distributed by the contractor to both residents and businesses. The first notice will
Rhine Wharf Repairs and Public Dock —Award of Contract No. 3821
October 27, 2009
Page: 3
be distributed ten days before work in the area and the second notice 48 hours prior to
starting work in the area.
Geotechnical and Material Testino Services:
In addition to the contract costs, approximately $10,900 in geotechnical consulting and
material testing services will be needed for this project and will be performed under on-
call professional services agreements. $1,980.16 is included for printing and other
incidentals.
Funding Availability:
There are sufficient funds available in the following accounts for the project:
Account Description
Tide and Submerged Lands
Contributions
Proposed uses are as follows:
Vendor
Associated Pacific Constructors, Inc.
Associated Pacific Constructors, Inc.
Harrington Geotechnical Engineering
Various
Prepared by:
Frank Tran
Associate Civil Engineer
��rrl
Chris Miller
Harbor Resources Manager
Attachments: Project Location Map
Account Number
7231- C5100921
7251- C5100865
Total:
Purpose
Construction Contract
Construction Contingency
Materials Testing
Printing and Incidentals
Total:
Submitted by:
Amount
$268,000.00
$240.000.00
$508,000.00
Amount
$430,539.84
$64,580.00
$10,900.00
$1,980.16
$508,000.00
Badum
s Director
RHINE WHARF REPAIRS & PUBLIC DOCK PROJECT
C -3821
oo PROJECT LOCATION
d oy
�yC
m CITY HALL p
.. uc
a VAC ISLE splo
SMET
F
�^� LJ111L ��' n5 0
MM S1HEff
ti a9M SREEi
s�vru�o wa
aam
smEa x
8
® Y N.T.S.
S aam smcfr
LOCATION MAP
N.T.S.