HomeMy WebLinkAbout08 - Rhine Wharf Repairs & Public DockCITY OF NEWPORT BEACH
CITY COUNCIL STAFF REPORT
Agenda Item No. 8
February 8, 2011
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: Public Works Department
Frank Tran, Associate Civil Engineer
949 - 644 -3340 or FTran @nevuportbeachca.gov
SUBJECT: RHINE WHARF REPAIRS AND PUBLIC DOCK - COMPLETION AND
ACCEPTANCE OF CONTRACT NO. 3821
ISSUE
Staff requests approval to accept the Rhine Wharf Repairs and Public Dock, Contract No.
3821, as complete.
RECOMMENDATIONS
1. Accept the completed work and authorize the City Clerk to file a Notice of
Completion.
2. Authorize the City Clerk to release the Labor and Materials bond 35 days after the
Notice of Completion has been recorded in accordance with applicable portions of
the Civil Code.
3. Release the Faithful Performance Bond one year after Council acceptance.
DISCUSSION
Summary of Completed Construction Contract
Total Contract
Final Cost at
Benchmark
Actual
Contract
Time
Amount
Completion
Target
Contract
Time
Under ( -)
(days)
or Over ( +)
$430,539.84
$436,140.70
Contract
+1.3%
165 *
-55
Plus 15%
* 45 days for the Rhine Wharf Repairs, and 120 days after the approval of the design for the Rhine Channel Public
Dock. The dock design was approved by the City Building Department on August 25, 2010.
On October 27, 2009, City Council awarded the Rhine Wharf Repairs and Public Dock
contract to Associated Pacific Constructors, Inc. This contract is comprised of two projects.
(1) Rhine Wharf Repairs: This project included removing and replacing boardwalk support
beams and planks, inspecting sheet piles and tie rods, repairing concrete sheet piles
and coping, applying preservative treatment to wood decking, and upgrading guardrails.
The inspection of the tie rods involved removing a strip of concrete approximately 2' -6"
Rhine Wharf Repairs and Public Dock
Completion and Acceptance of Contract No. 3821
February 8, 2011
Page 2
wide with the subgrade along the boardwalk to expose the tie rods where they connect
to the coping. When the tie rods were exposed, staff determined all tie rods were in good
condition; therefore, Additive Bid Item 1 for replacing tie rods was deleted. Instead, staff
authorized the replacement of the concrete apron where commercial loading takes
place. Per contract, the contractor had 45 consecutive working days to complete the
work for the wharf repairs.
(2) Rhine Channel Public Dock: This was a design -build project. The contractor prepared
and submitted to the City a design for the precast concrete platform with guard railings,
floating dock with pre- stressed concrete piles, and a handicap - accessible aluminum
gangway. In accordance with the Contract, the contractor was allowed 120 consecutive
working days to build the public dock after the City's approval of the design.
The contract has now been completed to the satisfaction of the Public Works Department.
A summary of the contract cost is as follows:
Original bid amount:
Actual cost of bid items constructed:
$430,539.84
$374,539.84
Change Orders $61,600.86
Final contract cost: $436,140.70
The two change orders in the amount of $61,600.86 were approved for the concrete apron
replacement, additional decking repairs, concrete pile and coping spall repairs. The deletion
of Additive Bid Item 1 (tie rod replacement) and the change order work items totaled
$5,600.86, represented a 1.3% cost change to the project.
The Rhine Wharf repair work was started on February 1, 2010 and was completed by March
22, 2010, ahead of schedule. The public dock design was approved by the City Building
Department on August 25, 2010. The Contractor successfully manufactured and installed
the dock within 65 days, which was completed on November 23, 2010. A summary of the
over construction schedule for both projects is as follows:
Estimated Completion Date per 2010 Baseline Schedule: September 17, 2010
Project Awarded for Construction: October 27, 2009
Completion Date per the Contract & Approved Extensions: February 8, 2011
Actual Substantial Construction Completion Date: November 23, 2010
Although the actual Construction Contract time was ahead of schedule, the overall project
did experience several months of delay between the completion of the wharf project and the
start of the public dock project due to the lengthy amount of time required to complete,
process and permit the design plans for the public dock.
ENVIRONMENTAL REVIEW
The Rhine Wharf Repairs project is exempt from the California Environmental Quality Act
(CEQA) pursuant to Section 15301, Class 1 of the CEQA Guidelines. This exemption covers
Rhine Wharf Repairs and Public Dock
Completion and Acceptance of Contract No. 3821
February 8, 2011
Page 3
minor alterations of existing public facilities with negligible expansion of the facilities in areas
that are not environmentally sensitive.
The Public Dock project is exempt from CEQA pursuant to Section 15303, Class 3 of the
CEQA Guidelines. This exemption covers construction and installation of limited numbers
of new small structures.
PUBLIC NOTICE
The Notice Inviting Bids was advertised in the City's official publication and in construction
industry publications. Prior to starting work, City prepared notices were distributed by the
Contractor to both residents and businesses.
FUNDING AVAILABILITY
Total project expenses, including incidentals, are summarized as follow:
Design and Construction Support
Construction
$23,500.00
$436,140.70
$220.72
.42
Funds for the construction contract were expended from the following account:
Account Description Account Number Amount
Tide and Submerged Lands 7231- C5100921 " $ 196,140.70
Contributions 7251- C5100865 $ 240,000.00
Total Construction Cost $ 436,140.70
The identified contribution funds above are associated with the UGS Development at 919
Bayside Drive. Per a Memorandum of Understanding with the Coastal Commission that
was approved by the City Council on June 12, 2007 (Item No. 18), the developer is required
to pay the City $240,000 upon execution of the MOD's for the construction of the public
dock. As of now, records indicate that UGS Development has yet to pay the $240,000 to
the City as required. UGS has indicated that they are experiencing financing difficulty and
are not planning to pay these funds until they get their project financed.
Prepared by:
0=1 i
Frank Tran
Associate Civil Engineer
Attachment: Location Map
RHINE WHARF REPAIRS & PUBLIC DOCK PROJECT
C -3821
PROJECT LOCATION
oy
4 9i
a 4
m CITY HALL � g
D 3
n C � CE BR/OC
�T
SMUT
Ll
LET
Q�
Q- O
zsW
SMUT 91P
h IBM SMUT
911PTNm WAY
SWEET IN
zaTM A
® Y N.T.S.
8 zsW s2aEET
LOCATION MAP
N.T.S.