Loading...
HomeMy WebLinkAbout9 - San Miguel Drive Street ImprovementsCITY OF NEWPORT BEACH CITY COUNCIL STAFF REPORT Agenda Item No. 9 February 8, 2011 TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL FROM: Public Works Department Fong Tse, Principal Civil Engineer 949 - 644 -3321 orftse @newportbeachca.gov SUBJECT: SAN MIGUEL DRIVE STREET IMPROVEMENTS - COMPLETION AND ACCEPTANCE OF CONTRACT NO. 4472 ISSUE Staff requests approval to accept the San Miguel Drive Street Improvements Project, Contract No. 4472 as complete. RECOMMENDATIONS 1. Accept the completed work and authorize the City Clerk to file a Notice of Completion for the project. 2. Authorize the City Clerk to release the Labor and Materials Bond 35 days after the Notice of Completion has been recorded in accordance with applicable portions of the Civil Code. 3. Release the Faithful Performance Bond one year after this Council acceptance. DISCUSSION Summary of Completed Construction Contract Awarded Final Cost at Benchmark Actual Contract Time Contract Amount Completion Target Contract Time Under ( -) or Change (days) Over ( +) $1,170,000.00 $1,202,390.00 Contract +2.77% 90 -32 Plus 10% On June 8, 2010, City Council authorized the award of the San Miguel Drive Street Improvements contract to GASS Construction Company, Inc. for a total contract cost of $1,170,000.00 plus a 10% allowance for contingencies. The focus of this project was to widen the portion of San Miguel Drive between MacArthur Boulevard and approximately 500' westerly of Avocado Avenue so as to increase the roadway capacity as well as to install a third left -turn lane for eastbound San Miguel Drive traffic to get onto northbound San Miguel Drive Street Improvements Completion and Acceptance of Contract No. 4472 February 8, 2011 Page 2 MacArthur Boulevard. Other associated project work included new traffic signals; relocation of The Irvine Company's Fashion Island entry monument sign and trees; new sidewalks, curbs, access ramps, .and raised median; new roadway pavement and striping; new landscaping; and the relocation and extension of existing underground facilities. The contract has now been completed to the satisfaction of the Public Works Department. Two change orders in the amount of $32,390.00 were approved to account for the numerous plan revisions and other changed conditions encountered in the field. A summary of the contract cost is as follows: Original bid amount $1,170,000.00 Cost of contract bid item quantity changes $ - 73,478.00 Plan changes $ 105,868.00 Final contract cost: $1,202,390.00 A summary of the project schedule is as follows: Estimated Completion Date per July 2010 Schedule November 3, 2010 Project Award for Construction June 8, 2010 Contract Completion Date per Notice To Proceed December 29, 2010 Substantial Completion Date November 18, 2010 Due to a delay in contract execution, the start of construction work did not occur in July 2010 as staff as hoped. Once work started, however, our field inspection and traffic engineering staff teamed with the Contractor and worked many nights to complete the work that otherwise would have required daytime traffic lanes and street closures. Although the team encountered field issues, changed parameters, and rain delays, they managed to deliver the finished product within budget and before the start of the 2010 holiday shopping season. ENVIRONMENTAL REVIEW This project was included within the Final Environmental Impact Report for the City Hall and Park Development Plan, SCH209041010, which was certified by the City Council on November 27, 2009. PUBLIC NOTICE The Notice Inviting Bids was advertised in the City's official publication and in construction industry publications. Prior to starting work, City - prepared construction informational notices were distributed by the Contractor to residents and businesses within the work vicinity. San Miguel Drive Street Improvements Completion and Acceptance of Contract No. 4472 February 8, 2011 Page 3 FUNDING AVAILABILITY Total project expenses, including incidentals, are summarized as follow: Construction Consultant Project Design Project Advertisement Reprographics Materials Testing Extra Work Reauested By The Irvine Co $1,202,390.00 233,945.98 95.00 139.04 4,811.50 $1,445,189.52 Of the total project cost above, The Irvine Company (TIC) cost share portion is $1,355,649.52. Of that amount, $450,330.00 is funded by CIOSA that the City has received. The remaining $905,319.52 will be reimbursed by TIC as part of the $2.5 million allocated for construction of transportation and circulation improvements within the Newport Center in accordance with the "Newport Center Transportation Improvement Program Agreement ". The City is responsible for $89,540 of the total project cost. See below summary: Account Description Newport Beach City Hall CIOSA Contributions Prepared by: F)din!d,1se P r6ipal Civil Engineer Attachment: Location Map Account Number 7251- C1002025 7432- C2002038 7251- C2002038 Amount $ 89,540.00 450,330.00 905,319.52 $1,445,189.52 Submitted by: Lu Ij J4 FARALLON tp- ) T-P A7 LOCATION MAP NOT TO SCALE SAN MIGUEL DRIVE STREET IMPROVEMENTS