HomeMy WebLinkAbout12 - Quarterly Business ReportCITY OF NEWPORT BEACH
CITY COUNCIL STAFF REPORT
Agenda Item No. 12
February 8, 2011
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: City Manager's Office
Dave Kiff, City Manager
949/644 -3000, dkiff()newportbeachca.gov
TITLE: Quarterly Business Report Update
ISSUE:
Provide a quarterly update of City Business that includes; a financial review, an update of
Council's 2010 Priorities, and a more detailed project tracking report for current key projects.
RECOMMENDATION:
Review and comment, as desired.
DISCUSSION:
The City Council held a Special City Council meeting on Saturday, January 9, 2010, to
discuss and establish its priorities for 2010. Council set an ambitious agenda with 46 specific
tasks identified. As in the past the City Manager was asked to ensure resources were
appropriately designated to work on these projects and then report back periodically on the
current status of this work.
The attached update contains three sections that present a quarterly status report of City
business. First, a financial review of the City's fiscal situation is provided. Secondly, a table
is provided that gives a status update of the 2010 priorities that Council identified. The final
section contains a more detailed summary of 22 specific projects. These projects are placed
within a project tracking template that is proposed as a format to update Council on important
projects in the future. The project tracking summary format summarizes the important
highlights of the project by providing a; description, goal objective, staff lead, target
completion date, milestones, project budget, and a quarterly status update.
Your comments are welcomed.
�0
DAVE KIFF
City Manager
Attachment
NEWPORT BEACH QUARTERLY
BUSINESS REPORT
October - December 2010
0
x
a
v
cC
N
W
O
�1.
a�
QUARTERLY FINANCIAL
REVIEW
City of Newport Beach, Administrative Services Department
www.newportbeachca.gov 949.644.3127
It
O
Q
N
N
C
m
L
N
L
7
L
U
(6
m
O
Q
N
z
February 8, 2011
Volume 1, Issue 1
For the period ended December 30, 2010
INSIDE THIS ISSUE
2009 -10 Audit Results 1
Status on Long -term Funding Programs
Latest CaIPERS Actuarial Report 2
OPEB (Retiree Insurance) 2
Public Liability & Workers Compensation
Facilities Replacement Plan 2
Economic Update 3
2010 -11 Budget Update
Revenue Outlook 5
Expenditures by Department 6
Quarterly Financial Review
2009 -10 Audited Results
Page 1
The City of Newport Beach's Comprehensive Annual Financial Report (CAFR), as of June 30, 2010, is
now available at www.newportbeachca.gov /cafr. These financial statements are the responsibility of
City management and have been audited by an independent CPA firm in accordance with standards
applicable per Government Accepted Auditing Standards. Our CPA's have opined that the financial
statements are fairly presented, in all material respects, and are in conformity with Generally
Accepted Accounting Principles. The City's CAFR has been recognized for Excellence in Financial
Reporting, by the GFOA, every year for almost two decades.
FY Ending
2009 2010
served
$ 5,907,205
$ 5,472,481
ireserved (Designated)
Facilities Financing Plan
25,000,000
27,500,000
Contingencies
18,614,125
18,895,125
Operations Reserve
13,098,656
17,293,299
Capital Reappropriations
4,661,307
3,495,487
Pension Rate Stabilization
5,000,000
5,000,000
Other Miscellaneous
7,329,671
4,501,474
$ 79,610,964
S 82,157,866
General Fund Highlights
For the year ended June 30, 2010, the City was able
to avoid any use of General Fund Reserves despite
sharp declines in key General Fund revenue sources
due to the recession. The City's General Fund
actually increased in total by $2.5 million, finishing
the year with $82.2 million of fund balance.
This was the result of the City's strong fiscal
policies, and proactive response to a tough
economic climate. The City implemented ERIP
(December 2009), negotiated with employee groups
to share in pension costs and to work without pay
raises, as well as continued contracting out services
when it was proven cost effective without negative
impacts to service levels.
Of the General Fund balances, $5.5 million is
externally restricted or is otherwise unspendable.
Within the Council's discretion, the City designated
$27.5 million for the Facilities Financing Plan, $18.9
million for contingencies and unexpected
emergencies (by policy to equal 12% of General
Fund operations), and $5 million for pension rate
stabilization. Council has also designated $3.5
million for capital improvements that were not
completed during the fiscal year. Other
miscellaneous designations amounted to $4.5
million. Finally, $17.3 million remained for
unspecified future appropriations. This undesignated
portion of fund balance increased a total of $4.1
million during the fiscal year making FY 2010 the
highest level of General Fund Reserves ever for the
City.
Quarterly Financial Review
Status Updates on Long -term Funding Programs
CaIPERS Update
The latest actuarial results that are available
from CalPERS reflect a valuation date as of June
30, 2009 (received October 2010) and will be
used to set rates for fiscal year 2011 -12. This
valuation date is significant because it is the
first valuation that reflects the extraordinary
losses in the equities market that occurred in
October of 2008. The resulting increase to
contribution rates and precipitous decline in
funded status are very close to our previous
estimates. The one -year change to total
required contribution rates, annual required
contribution and funded status is illustrated in
the table to the right.
OPEB Obligation (Retiree Insurance)
Although the new retiree insurance plan does
not carry any long -term obligations associated
with it, the previous plan's unfunded liability is
being actuarially funded and amortized over a
twenty -year period. Unfortunately, the same
market losses that impacted the CalPERS
pension plan also impact our OPEB plan.
Fortunately, the assets in the OPEB prefunding
trust are only a small fraction of pension plan so
rate volatility is not expected to be nearly as
extreme. We obtain a bi- annual OPEB valuation
per Governmental Accounting Standards and are
currently in the process of updating the
valuation for fiscal year ended 6/30/2010. The
results of this valuation should be available in
the spring. For fiscal year ended 6/30/2010, our
OPEB contribution was $2.4 million and is
expected to be $2.6 million in FY 2011.
Public Liability and Workers Compensation
These liabilities can have a very long life span
between incurrence to final settlement. The
City therefore, employs actuaries to review
Page 2
Miscellaneous
Safety
91.9%
81.0%
61.1%
54.8%
Miscellaneous Plan
Expected Payroll
$ 45,292,416
$ 47,211,177
Employer Contribution
4,903,357
6,906,051
Employee Contribution
3,623,393
3,776,894
Safety Plan
Expected Payroll
$ 30,880,584
$ 33,299,729
Employer Contribution
9,326,554
11,646,229
Employee Contribution
2,779,253
2,996,976
Market Value Asset Basis
losses, case reserves and predict future losses
including incurred but not reported (IBNR) claims.
Fortunately this is one of the more mature
internal service funds, established by the City in
the early nineties, and is 100% funded for our
actuarially calculated losses of $16.1 million in
addition to having $5.7 million in reserves. These
valuations are also on a bi- annual calendar and
are currently in progress; it is expected these
programs will continue to be funded in excess of
the targets set by Council, as was the case in
fiscal year ended 6/30/2010.
Facilities Replacement Plan
Our financing plan is a long range planning tool
to ensure proper funding (cash or bond financing)
for the timely replacement of all major General
Government facilities. With the issuance of the
2011 COP'S for the civic center, our plan
maintains the strict 5% (or less) cap on annual
general fund contributions. FFP reserves are
currently at $31.3 million and the FY 2011
contribution was budgeted at $3.8 million.
More analytical data on this topic is available www. newportbeachca .gov /financiatinfo under "Reserve Funding Status"
Quarterly Financial Review Page 3
Economic Update
Despite the tepid labor market, "the economic climate and conditions for
growth are a good deal more favorable than it has been, "said Lawrence
Summers, Former Secretary of the Treasury in a recent interview.
In the closing months of 2010, leading economic and various manufacturing activity indicators painted a
brighter picture of the U.S. economy. For many, the modest improvements were enough to abate worries of a
double dip recession.
US Gross Domestic Product (GDP) growth was up 2.6
percent for the third quarter. Moody's estimates that
GDP growth will be 3.0 percent for the fourth quarter
2010 and then accelerate to a 4.0 percent growth
average for 2011.
Consumer Spending appears to have rebounded from
recession lows but is nowhere near pre- recession
levels. Household spending has continued to increase
in 2010 at a moderate pace but consumers remain
somewhat cautious due to job losses, home price
declines and tightening credit standards.
Retail Sales enjoyed a modest increase of .8 percent
in November and strong holiday shopping season
reported by retailers. Year- over -year sales are up
nationally 7.7 percent. Auto Sales and Restaurants
continue to be Newport Beach's top sales tax
segments.
The Housing Market is still weak but showed signs of
improvement at the end of the year with sales of
existing homes increasing 5.6% in November over the
previous month. While this is welcome news, sales are
still down 27.9 percent from a year ago however
prices are up .4 percent year over year. Some
economists are looking to the housing market as a
key indicator of how the economy as whole may fare
in 2011 but at present, a meaningful housing
recovery is not expected until 2012.
Inflation remains in check for the time being with the
Core CPI (excluding food & energy) report indicating a
year- over -year increase of only .8% but many
economists forecast moderate inflation well into
2011.
Monetary Policy: At its January 26, 2011 meeting, the
Federal Reserve Board's Open Market Committee
(FOMC) kept the federal funds rate unchanged with a
target range between zero to .25 percent and the
pledge to keep interest rates "exceptionally low" for
an "extended period" to support the economic
recovery. "The Committee will continue to monitor
the economic outlook and financial developments and
will employ its policy tools as necessary." The next
FOMC meeting is scheduled for March 15, 2011.
Labor Market: The economy added 103,000 jobs in
December although it was lower than many analysts
were expecting. Overall the latest employment report
was disappointing and continues to be the number
one concern in the nation. jobs creation has not
historically come back in the numbers that are typical
after an economic recession.
"It could take four to five years for the job
market to normalize fully, " Bernanke said in
prepared testimony to the Senate Budget
Committee
Quarterly Financial Review
Most serious recession since World War II
12.00%
a
t
�
10.00%
8.00%
c
G 6.00%
N
d
u
� 4.00%
0
0 2.00%
K 0.00%
a
V' -2.00%
ry
d
-4.00%
d
m
� -6.00%
L
Cumulative % Change in GDP from the Starting Quarter of Recent Recessions
Am
—Jul 1981- Nov 1982
Jul 1990 - Mar 1991
Mar 2001 - Nov 2001
Dec 2007 -Jun 2009
r 9 12 15 18 24 27 30 33 3fi
Months After Recessioio n Start
The above illustration compares the depth and recovery cycle of most the recent recession to previous recessions. The most
recent recession realized a steeper decline and a more gradual recovery.
Although unemployment rates are more than double the norm, employment in Newport Beach far compares favorably to County and
Statewide figures.
Quarterly Financial Review
2010 -1 1 Budget Update
FY 2010-11 Revised R- •.
24%
Original
12/31/10 YTD
Mid Year
Revenue Budget
Revenues
Revised Est.
Change
Property Taxes
$ 70,642,840
$ 33,597,170
$ 71,000,000
$ 357,160
Sales Tax
17,374,734
3,895,079
18,250,000
875,266
Property Tax - In Lieu of Sales Tax
6,392,273
-
6,308,305
(83,968)
Transient Occupancy Tax
11,555,034
6,002,173
12,500,000
$ 944,966
Business Licenses
4,008,800
1,783,239
3,820,000
(188,800)
Franchises
4,145,000
886,416
3,985,000
(1(,0,000)
Building Revenue
3,852,749
1,573,002
4,319,381
466,632
Other
27,154,240
14,229,533
27,154,240
-
Tran5fers -In
3,679,834
-
3,679,834
-
TotalRevenues &Transfers
$ 148,805,504
$ 61,966,612
$ 151,016,760
$ 2,211,256
Revenue Summary
Generally, our economic outlook is stable with
revenue projections coming at budget or slightly
above. Newport Beach revenues are steadily, yet
modestly, returning to pre- recession levels. In almost
all categories we are expecting to surpass budget
targets, but at a very modest pace.
In their aggregate, 2010 -11 revenues are expected to
outpace our original projections by one to two percent
producing a revenue surplus of approximately $2
million at present.
FY 2011 Revenues by Source
..-
Property Taxes - The California residential housing
market appears to have bottomed out for now and is now
showing weak signs of recovery. Unfortunately, the City's
number one revenue source is projected to produce
minimal growth for the next several years.
For 2010 -11, Property tax revenues are on track to
produce a modest increase over the original budget by
approximately $350,000, representing only .5% growth.
Sales and Use Taxes - Consumer sentiment is still very
cautious but sales tax revenues appear to be improving
slightly. Although luxury auto sales continue to be the
City's number one generator of sales taxes, the restaurant
and department store sectors are showing the greatest
improvement on a year- over -year basis; current
projections estimate an increase over budget of
$875,000.
• Property Taxes
•Sales Tax w /Paid Tax in Transient Occupancy Tax (TOT) - TOT receipts are
Lieu
Traoneot 0,caparr, Ta improving at a moderate pace and are expected to finish
-Building Revenue above the 2010 -11 budget by more than 8 %, $940,000,
• AIL Other Revenue at the current pace. The Pelican Hills resort is again
showing the greatest year over year improvement.
TOP " 3"
The City's Top Three revenue sources are Property
Taxes, Sales Taxes, and Transient Occupancy Taxes.
The order of magnitude of General Fund revenues is
illustrated by the chart above.
Other Revenues - While far less significant than the top
three revenue sources, but representing other community
based activity indicators, building permit activity and
revenues showing modest improvements over the prior
year are likely to beat budgetary estimates. However
Business tax and recreation based activities are likely to
fall short of prior year estimates.
24%
a%
I
Bo
..-
Property Taxes - The California residential housing
market appears to have bottomed out for now and is now
showing weak signs of recovery. Unfortunately, the City's
number one revenue source is projected to produce
minimal growth for the next several years.
For 2010 -11, Property tax revenues are on track to
produce a modest increase over the original budget by
approximately $350,000, representing only .5% growth.
Sales and Use Taxes - Consumer sentiment is still very
cautious but sales tax revenues appear to be improving
slightly. Although luxury auto sales continue to be the
City's number one generator of sales taxes, the restaurant
and department store sectors are showing the greatest
improvement on a year- over -year basis; current
projections estimate an increase over budget of
$875,000.
• Property Taxes
•Sales Tax w /Paid Tax in Transient Occupancy Tax (TOT) - TOT receipts are
Lieu
Traoneot 0,caparr, Ta improving at a moderate pace and are expected to finish
-Building Revenue above the 2010 -11 budget by more than 8 %, $940,000,
• AIL Other Revenue at the current pace. The Pelican Hills resort is again
showing the greatest year over year improvement.
TOP " 3"
The City's Top Three revenue sources are Property
Taxes, Sales Taxes, and Transient Occupancy Taxes.
The order of magnitude of General Fund revenues is
illustrated by the chart above.
Other Revenues - While far less significant than the top
three revenue sources, but representing other community
based activity indicators, building permit activity and
revenues showing modest improvements over the prior
year are likely to beat budgetary estimates. However
Business tax and recreation based activities are likely to
fall short of prior year estimates.
Quarterly Financial Review
A.- .
Expenditure Update
The recession became most significant to Newport
Beach during FY 2010; severe revenue shortfalls
became evident. Early projections estimated the
revenue shortfall to be as much as $8 million. Long-
term forecasts of a declining revenue environment
foreshadowed a slow recovery and a persistent
structural deficit, if not addressed immediately. Making
matters worse, it soon became apparent that the
extraordinary losses in the equities market would cause
a sudden and radical change to the funded status of
pension plans which would in turn result in
unsustainable pension cost increases for the
foreseeable future. To address these concerns head -on
the City Manager, with Council's approval, made an
organization -wide structural shift in how the City
operates. The structural changes included an early
retirement incentive plan, outsourcing certain
governmental functions, department cut - backs,
employment concessions and deferral of capital
improvement projects.
At the close of FY 2010, revenue shortfalls were less
severe than originally projected, actually coming in $6
million short of the budget vs. the $8 million
projection. The City Manager's organizational re-
structuring and revenue enhancement proposals
resulted in an operating surplus which improved
General Fund Reserves by more than $2 million during
the worst economic recession since the Great
Depression! These were structural changes which
helped address the budget issues for the long -term.
The FY 2011 Budget was initially adopted with an
estimated $2 million of expenditures over revenues.
However, management pledged to balance the budget
and not access reserves prior to the close of the fiscal
year. As of December 2010, as discussed earlier,
revenue excesses alone will likely cover this deficit.
Further expenditure reductions under development will
be brought forward in the near term but they will likely
bring about only modest savings during the remainder
of the fiscal year. At present, an operating surplus of at
least $1 -2 million is projected for FY 2011 and the City
Manager has committed to budgeting any General Fund
surplus in FY 2011 to capital needs previously deferred.
GeneralFundf_ anditures4y Department
FY 2010 -11
FY 2009 -10
FY 11 Original
Amended
YTD as of
Percent
YrD as of
Percent
Department
Budget
Budget
12/31/2010
Expended
12/31/2009
Expended
City Council
1,044,410
$ 1,053,886
$ 535,594
51%
$ 557,233
44%
City Clerk
492,538
493,978
189,163
38%
189,886
50%
City Manager
2,437,018
2,463,169
1,025,489
42%
1,069,089
44%
Human Resources
2,292,046
2,326,746
1,024,207
44%
1,052,602
44%
City Attorney
2,348,842
2,358,728
1,490,411
63%
1,231,353
51%
Administrative Svcs
7,775,976
7,729,781
3,304,578
43%
3,977,803
47%
Police
42,823,171
42,958,157
20,313,992
47%
21,723,448
48%
Fire
34,055,183
34,183,820
17,100,589
50%
17,411,684
51%
Planning
3,005,540
3,327,073
1,418,547
43 %.
1,475,024
40%
Building
4,237,603
4,237,602
2,038,980
48%
2,254,487
46%
General Services
22,034,946
22,121,466
9,760,047
44%
10,937,364
46%
Library
6,472,808
7,052,147
3,221,516
46%
3,312,572
47%
Recreation
7,590,671
7,655,730
3,668,227
48%
3,487,116
48%
Public Works
5,550,535
5,877,960
2,624,883
45%
2,698,725
46%
Electrical
1,307,491
1,336,290
438,150
33%
498,756
34%
Cl P.
1,061,000
5,878,342
585,939
10%
2,357,406
23%
OPEB
2,128,000
2,128,000
-
0%
-
0%
FFP
3,800,000
3,800,000
-
0%
-
0%
Debt Service
780,000
780,000
-
0%
-
0%
Total
151,237,778
$ 157,762,874
$ 68,740,312
44%
$ 74,234,548
46%
Expenditure Update
The recession became most significant to Newport
Beach during FY 2010; severe revenue shortfalls
became evident. Early projections estimated the
revenue shortfall to be as much as $8 million. Long-
term forecasts of a declining revenue environment
foreshadowed a slow recovery and a persistent
structural deficit, if not addressed immediately. Making
matters worse, it soon became apparent that the
extraordinary losses in the equities market would cause
a sudden and radical change to the funded status of
pension plans which would in turn result in
unsustainable pension cost increases for the
foreseeable future. To address these concerns head -on
the City Manager, with Council's approval, made an
organization -wide structural shift in how the City
operates. The structural changes included an early
retirement incentive plan, outsourcing certain
governmental functions, department cut - backs,
employment concessions and deferral of capital
improvement projects.
At the close of FY 2010, revenue shortfalls were less
severe than originally projected, actually coming in $6
million short of the budget vs. the $8 million
projection. The City Manager's organizational re-
structuring and revenue enhancement proposals
resulted in an operating surplus which improved
General Fund Reserves by more than $2 million during
the worst economic recession since the Great
Depression! These were structural changes which
helped address the budget issues for the long -term.
The FY 2011 Budget was initially adopted with an
estimated $2 million of expenditures over revenues.
However, management pledged to balance the budget
and not access reserves prior to the close of the fiscal
year. As of December 2010, as discussed earlier,
revenue excesses alone will likely cover this deficit.
Further expenditure reductions under development will
be brought forward in the near term but they will likely
bring about only modest savings during the remainder
of the fiscal year. At present, an operating surplus of at
least $1 -2 million is projected for FY 2011 and the City
Manager has committed to budgeting any General Fund
surplus in FY 2011 to capital needs previously deferred.
Quarterly Financial Review
Page 7
A New Era
The severity of the recent recession will obviously leave its mark on the world for many years to come. The
private and public sectors are still struggling to define equilibrium in a changed world. In September of
2009, phase 1 changes were engaged to provide expedient solutions in reaction to the fiscal crisis that
was bearing down on the City. Phase 2 changes are under development and are intended to provide more
structural and substantive change, adapting to a new norm where City operations will be more strategically
focused, leanly operated and held accountable to our business objectives.
2010 COUNCIL PRIORITY UPDATE
0
a
v
cC
N
W
O
�1.
a�
z.
O
O
a�
r~
0�
N
z»
rC
O
a
U
U
t�
N
0�
O
N
ii
2010 Council Priority Quarterly Update
Protect and Enhance Quality of Life Goal
Status
Next steps
• Airport: minimize adverse impacts of JWA
Corridor cities added in
2011 will see a majority of
on the community by protecting the
2010:
the Settlement Extension
Settlement Agreement's caps on average
- Irvine
discussions /negotiations,
daily departures and passengers as well as
- Laguna Beach
led by Council, City
the curfew and current noise ordinances.
Villa Park
Manager, City Attorney
implementation updates to the Council.
Met several times with
employee benefit plan
Supervisor Moorlach
concessions
• Group homes: implement group home
See Project Tracking Report
See Project Tracking Report
regulations to minimize adverse impacts on
— Project 8
— Project 8
residential neighborhoods while preserving
updates regularly
appropriate treatment options.
- Succeeded. 1" Orange
- Protect ratings by taking
• Fiscal health and sustainability: make
- Adopted Fiscal
Implement Muni Cast
decisions today that will protect and
Sustainability Policy
Analysis Tool
enhance the City's fiscal health into the
- Provided Finance
-Multi Year Budget Forecast
future.
Committee regular updates
- Control Costs
on current and short and
-Full Cost Recovery &
long -term budget issues
Revenue Enhancement
• Public safety: provide services that
Ongoing. Performance
Hire new fire chief; protect
enhance safety and protection in the
measurement goals
community safety despite
community.
generally met for 2010
continuing budget
reductions
Fiscal Sustainability Goal
Status
Next steps
• Adopt and follow a Fiscal Sustainability
- Adopted & Implemented
- Regular Monitoring
Plan.
• Adopt a balanced budget that adjusts to
-Final Budget adopted with
- Identify and implement cost
lower revenues; provide quarterly
$2.5M in unidentified
control measures including
financial forecasts and budget
adjustments. Should
department reductions and
implementation updates to the Council.
balance by year end by
employee benefit plan
monitoring revenue
concessions
increase and implanting
- Implement full cost
expenditure reductions
recovery and fee schedule
updates regularly
• Achieve and maintain the highest
- Succeeded. 1" Orange
- Protect ratings by taking
possible bond rating.
County city and one of
budget actions to respond to
only five cities in California
revenue conditions and cost
to receive AAA underlying
control rising cost threats
agency rating from all
- Expand and improve upon
three rating agencies
financial policies where
necessary
O
N
a�
O
O
0�
N
s,
cC
O
a
U
U
CZ
N
0�
s.
O
N
ii
2010 Council Goals Quarterly Update
Fiscal Sustainability Goal Con't
Status
Next steps
• Update the Facilities Financing Plan (FFP)
-FFP was updated several
- Update FFP quarterly or
to reflect priorities for capital projects
times during the course of
when new information
funding.
the year as new
concerning construction
construction estimates
costs or funding changes
• Provide quarterly reports to City Council
became available
significantly
• Update the City's harbor fees in a manner
See Project Tracking
See Project Tracking Report
that is fair; secure a funding mechanism
Report— Project 5
— Project 5
for funding harbor projects, such as
- Will be integrated with
dredging and providing additional harbor
new results based
amenities.
budgeting system once
• Initiate a results -based budgeting system.
-Met with Department
- Convert all other
• Conduct the second Citizen Satisfaction
Directors and Consultants
department RAP to
Survey.
- Developed concept plan
Performance Plan template
-Admin Services and Public
Works will serve as first
test budgets for 2011 -12
Effective Management Goal
Status
Next steps
• Restructure City government to become
Several changes in 2009 -10
More to come in 2010 -11
more efficient and effective in the delivery
(MOD, Code Enf, Harbor
and 2011 -12
of valued services.
Resources, contracting out,
more)
• Provide quarterly reports to City Council
- Performance
Awaiting implementation of
on performance measurements
Measurement Program
results based budgeting
(comparing ourselves to ourselves) and
under transition.
system
information on feasibility of
- Will be integrated with
benchmarking (comparing ourselves to
new results based
other agencies).
budgeting system once
implemented
• Conduct the second Citizen Satisfaction
- Survey conducted in
Completed. Next Survey
Survey.
August 2010.
likely to be in 2012 or 2013.
- Final survey report
presented to Council on
October 26, 2010
• Update the City Charter.
Measure V passed by
Amending Polices to match
voters November 2010
new Charter language
• Improve customer service by mirroring
Generally met goal of 24-
Provide more services
the "gold standard" of service in the
hour response time for
online, 24/7. Reduce trips
public or private sector.
calls, a -mails
to City Hall
C4
Ln
N
l�
CZ
V
CDv
rC
a�
s,
O
2010 Council Goals Quarterly Update
Effective Management Goal Con't
Status
Next steps
• Improve City / resident communications.
- Citizen survey indicated
PIOs from various
and the prompt opening of Nordstrom.
increased citizen
departments will meet early
satisfaction with overall
in new year to align
communication efforts and
communication goals and
several communication
objectives for 2011
tools
- Staff continues to
incorporate new
• Abate nuisances and improve Mariners
technologies & update
See Project Tracking Report
Mile between Dover and MacDonalds.
processes for community
— Project 1
• Start implementation of The Irvine
outreach and
See Project Tracking Report
Company's North Newport Center project.
communication efforts
— Project 11
• Restructure development services
See Project Tracking Report
See Project Tracking Report
function for improved coordination
— Project 16
— Project 16
among disciplines; continued
improvement in customer service.
• Adopt an updated Zoning Code and
Zoning Code adopted in
- Implement and train staff
Transportation Fair Share Fee and obtain
October
on updated Zoning Code,
certification of Housing element.
- Fair Share fee See Project
Adopt any necessary
Tracking Report— Project 19
revisions to the Zoning Code
- Fair Share fee See Project
Tracking Report— Project 19
• Address the economic impact of new
None passed in 2010
regulations considered by the City Council.
Economic Sustainability Goal
Status
Next steps
• Support the renovation of Fashion Island
Staff has worked closely
Continuation of key staff
and the prompt opening of Nordstrom.
with the Irvine Company to
assignment to support
support renovation of
renovation of Fashion Island
Fashion Island including
renovation of the movie
theaters
- Nordstrom opened in
April of 2010
• Abate nuisances and improve Mariners
See Project Tracking Report
See Project Tracking Report
Mile between Dover and MacDonalds.
— Project 1
— Project 1
• Start implementation of The Irvine
See Project Tracking Report
See Project Tracking Report
Company's North Newport Center project.
— Project 11
— Project 11
• Dredge the Lower Bay and establish a
See Project Tracking Report
See Project Tracking Report
long -term funding source for repeat
— Project 13
— Project 13
dredging efforts.
N
tx
a�
s~
0�
N
s,
cC
d
U
U
N
W
r—+
s,
O
N
2010 Council Goals Quarterly Update
Economic Sustainability Goal Con't
Status
Next steps
• Continue to support business
Economic Development
Focus on providing business
development efforts consistent with the
staff has supported the
attraction and business
Strategic Plan for Economic & Fiscal
Chamber of Commerce,
retention services and
Stability and with the Council's Fiscal
BIDS, Restaurant Week,
project implementation
Sustainability Plan.
Film Festival and has
coordination where
coordinated development
necessary
processing for several
water from 432 acre -feet
prospective businesses,
(af) to 500 of
OPIS Network program
- Increase our basin
support
pumping percentage from
• Identify a process and the resources
See Project Tracking Report
See Project Tracking Report
needed to support innovative planning of
— Project 12
— Project 12
and improvement in Lido Marina Village,
Landscaping and
imported water from
including Via Oporto and other nearby
landscape & Irrigation
Metropolitan Water District
properties.
Design Standards
- Implement a progressive
• Complete update of vision for Balboa
See Project Tracking Report
See Project Tracking Report
Village.
— Project 3
— Project 3
Environmental Sustainability Goal
Status
Next steps
• Respond to the results of the JWA air
Study completed August
Decide if Phase II study
quality study.
110
(water quality) warranted
• Reduce our use of potable water and our
- Reduced residential
- Support construction of
dependence on imported water sources.
potable water
the Poseidon desalinization
consumption by 15% from
plant
Syr average to 130 gallons
- Increase use of recycled
per day per capita (GPCD)
water from 432 acre -feet
- Updated NBMC 14.16
(af) to 500 of
Water Conservation and
- Increase our basin
Supply Level Regulations
pumping percentage from
- Adopted NBMC 14.17
62% to 65% to eliminate
Water- Efficient
the need for 500 of of
Landscaping and
imported water from
landscape & Irrigation
Metropolitan Water District
Design Standards
- Implement a progressive
tiered water rate
- Implement City rebate
programs to incentivize
efficient water use
N
a�
S~
oa
N
s,
cC
CY
v
rC
W
r-+
s,
O
i
2010 Council Goals Quarterly Update
Environmental Sustainability Goal Con't
Status
Next steps
• Improve recreational water quality.
- Coastal Cleanup Day
- Work with our upstream
the new Civic Center.
1293 volunteers
cities and regional agencies
• Break ground on the Civic Center Project,
- Upper Buck Gully
to reduce nutrient, selenium
including the park.
Wetlands Restoration
and debris loading into the
• Complete the EIR and seek funding
- Newport Beach Receives
Upper Bay and Harbor
sources for the Banning Ranch property.
Five Star Rating - NRDC's
- Water quality projects in
• Start construction of Sunset Ridge Park.
report provides a 5 -star
Lower Buck Gully and Big
rating guide for 200 of the
Canyon Creek
• Start construction of Marina Park (phase I
nation's most popular
- Maintain our enhanced
or all phases).
beaches
cleaning and maintenance
of storm drains
- Deploy trash booms in
Newport Bay
• Assist the Corps and County in dredging
Upper Bay project
Longterm funding for Upper
the Upper Bay and establish a long -term
complete in November
Bay possibly provided by
funding source to repeat the UNB
2010
current harbor fee increases
dredging.
(moorings, BYB, pier permit
fees etc...)
• Dredge the Rhine Channel.
See Project Tracking Report
See Project Tracking Report
— Project 17
— Project 17
• Create a plan for responding to future sea
- Building code slab
Consultant report on Sea
level changes that may affect properties.
construction height
Level rise impact to Balboa
adjusted to meet latest
Island to be completed in
FEMA guidelines
Spring 2011
- Future Bulkhead heights
- Future review of Sea Level
to be increased as
rise impacts to rest of
replaced
Coastal area to be
Study underway to
undertaken
understand Sea Level
impacts to Balboa Island
Community Enhancements Goal
Status
Next steps
• Incorporate a public art component into
See Project Tracking Report
See Project Tracking Report
the new Civic Center.
— Project 10
— Project 10
• Break ground on the Civic Center Project,
See Project Tracking Report
See Project Tracking Report
including the park.
— Project 6
— Project 6
• Complete the EIR and seek funding
See Project Tracking Report
See Project Tracking Report
sources for the Banning Ranch property.
— Project 4
— Project 4
• Start construction of Sunset Ridge Park.
See Project Tracking Report
See Project Tracking Report
— Project 18
— Project 18
• Start construction of Marina Park (phase I
See Project Tracking Report
See Project Tracking Report
or all phases).
— Project 14
— Project 14
a�
O
N
a�
O
O
0�
N
s,
cC
d
U
U
N
W
r-+
s,
O
2010 Council Goals Quarterly Update
Community Enhancements Goal Con't
Status
Next steps
• Complete construction of and open the
Opened per plan on
Project is Complete.
new OASIS Senior Center.
September 20, 2010.
Project is Complete
• Reduce fire hazard in Buck Gully and
See Project Tracking Report
See Project Tracking Report
Morning Canyon.
— Project 15
— Project 15
• Implement traffic management plan
See Project Tracking Report
See Project Tracking Report
(including traffic synchronization) to
— Project 9
— Project 9
improve traffic flows.
• Implement a comprehensive parking
See Project Tracking Report
See Project Tracking Report
program for the Balboa Peninsula.
— Project 7
— Project 7
• Widen Jamboree Road in the Airport Area
See Project Tracking Report
See Project Tracking Report
(especially Jamboree and Bristol).
— Project 20
— Project 20
• Initiate the acquisition of Coast Highway
See Project Tracking Report
See Project Tracking Report
between Jamboree and the Santa Ana
— Project 2
— Project 2
River and Newport Boulevard from Finley
to West Channel Bridge; create a process
for initiating a longer range planning
process for Mariner's Mile Traffic,
Pedestrian, and Parking Comprehensive
Plan.
• Facilitate Newport Beach arts
$100,000 Council grant in
- Continued efforts to
opportunities through:
support of the Film Festival
support the Arts in Newport
• Opening of the remodeled Port Theater;
given in 2010
Beach
• The Newport Beach Film Festival;
-Arts Commission is giving
- The City continues to have
• Encouraging fundraising to renovate the
the Festival a $5,000 arts
a staff representative to
Balboa Theater and implement the
grant
work with the Film Festival
- Master events calendar
Board
Newport Nautical Museum's master plan;
that is enclosed in the
• Assisting VisitNB.com or the Chamber in
City's Navigator newsletter
publishing and promoting a Master
Calendar of Events.
• Plan the future of the current City Hall site
Study Session 1/11/2011
- Approve the final
at 3300 Newport Boulevard.
completed with direction
conceptual plan on
given to staff as a
1/25/2011,
component of the Lido
- Implement final Council
Village Conceptual planning
direction on re -use, prepare
effort
environmental review and
adopt necessary
amendments to regulatory
documents
• Work to change the dynamics in West
West Newport Safety
Committee will meet
Newport on July 4 to have a more family-
Committee reps,
regularly through the late
friendly celebration and lower law
community members and
winter & spring
enforcement costs.
staff to meeting in January
PROJECT TRACKING REPORTS
0
a
v
cC
N
W
O
�1.
a�
PROJECT TRACKING REPORT TABLE OF CONTENTS
Abatement Nuisances and Improve Mariner's Mile PROJECT 1
Acquisition of Coast Highway PROJECT 2
Balboa Village Visioning PROJECT 3
Banning Ranch
PROJECT 4
City Harbor Fees
PROJECT 5
Civic Center Project
PROJECT 6
Comprehensive Parking Program for the Balboa Peninsula PROJECT 7
Group Homes PROJECT 8
Implement Traffic Management Plan PROJECT 9
Incorporate Public Art Component in new Civic Center PROJECT 10
Irvine Company's North Newport Center Project PROJECT 11
Lido Village Conceptual Planning PROJECT 12
Lower Bay Dredging Project PROJECT 13
Marina Park PROJECT 14
Reduce Fire Hazard in Buck Gully and Morning Canyon PROJECT 15
Restructure Development Services PROJECT 16
Rhine Channel Contaminated Sediment Cleanup PROJECT 17
Sunset Ridge Park PROJECT 18
Transportation Fair Share Fee PROJECT 19
Widen Jamboree Road in the Airport Area PROJECT 20
0
o.
a�
cC
Ln
Ln
N
W
0
c�
o'
U
c6
a�
0�
O
�L
3
a�
ii
PROJECT 1
PROJECT: Abate Nuisances and Improve Mariner's Mile
Department(s): City Attorney's Office and Community Development
Project Lead: Kyle Rowan, Deputy City Attorney
Project Start Date: July 2009
Target Completion Date: July 2010
Description:
The project is to aggressively pursue enforcement actions against the property owner of 17 lots
within the Mariner's Mile area of the City, more specifically located at 200 -600 West Coast
Highway, in order to abate nuisance conditions that exist on the properties. The lots were
vacant for several years as a result of a redevelopment plan that never materialized, resulting in
dangerous conditions and public nuisances, including graffiti, abandoned signs, overgrown
landscaping, weeds, debris, broken windows, and harboring vagrants. The City's goal is to have
all of the public nuisances that exist on the property corrected, abated, or remedied, and to
improve the aesthetics of the properties.
Funding Source: General Fund and Settlement Agreement
Total Funding Required for Project: unknown
Funding Allocated to Date: $10,000 received from current property owners as part of
settlement agreements.
Amount Spent to Date: Approximately $10,000 in external legal fees and budgeted staff
resources from multiple departments.
Status to Date:
Background- In 2004, a development application was filed with the City to redevelop
properties located at 200 -600 West Coast Highway. The properties are located on the north
side of the highway, between Dover Drive and the MacDonald's restaurant. In anticipation of
project approval and demolition of the existing structures, the landowner vacated the eight
detached retail /commercial structures. Entitlements to develop a 56,000- square -foot retail
center was approved on January 19, 2006; however, due to difficulties obtaining approvals to
install a new traffic signal from Caltrans and litigation with former prospective tenants, the
Project Tracking Report (October- December 2010) Page 1
t.
O
�1.
N
CC
Ln
Ln
N
O
W
s.
N
c�
O
o'
U
c6
a�
0�
O
�L
3
Ong
PROJECT 1
Abatement Nuisances and Improve Mariner's Mile
landowner was unable to commence construction on the approved project.
Public Nuisances and Actions - Starting as early as February 2005, Building and Code
Enforcement staff began working with the landowner to correct dangerous conditions and
public nuisances, including graffiti, abandoned signs, overgrown landscaping, weeds, debris,
broken windows, and harboring vagrants.
Due to the landowner's lack of cooperation and continual violations, the City commenced a
more aggressive attempt to abate the nuisances starting in July of 2009, by recording a Notice of
Violation of Public Nuisance and Order to Abate on the property. At that time, the landowner
was in the process of advertising the property for sale and the recorded Notice proved to be an
encouragement for the landowner to cooperate with the City. After several months of meeting
with the landowner to abate the nuisances, it became evident that the landowner had no
intentions of abating the public nuisances and was only interested in selling the property. To
ensure that the properties were not sold to new buyers without addressing the required
nuisance abatement, on February 9, 2010, the City filed a Complaint with the Orange County
Superior Court against the landowner and also recorded a Notice of Pendency of Action, which
provides notice of the pending compliant with the Court. On February 26, 2010, settlement
agreements were entered into with the landowner and the two new buyers of the properties,
Russell Fluter and VBAS, Properties, Inc. Each new buyer was given a schedule for abatement.
Current Status - The VBAS property consists of the first 6 lots west of Dover Drive (200 -300
West Coast Highway). A development application was submitted in August of 2009, to
redevelop the property with a 23,015 square -foot, two -story commercial building and a three-
story parking structure. Project implementation requires several approvals from the City and
the preparation of a Mitigated Negative Declaration in compliance with the California
Environmental Quality Act. Planning Commission and City Council hearings are anticipated to
be scheduled in late Spring or early Summer 2011. Although the property is not in technical
compliance with the conditions of the settlement, the applicant is diligently processing their
application and has maintained the property in a safe and secure condition, including the
removal of graffiti, painting the buildings, and adequately securing the site. Thus, it is not in the
City's best interest at this time to take further code enforcement actions because if the project is
approved, the applicant will commence demolition and complete the abatement.
Project Tracking Report (October- December 2010) Page 2
PROJECT 1
Abatement Nuisances and Improve Mariner's Mile
The Fluter property consists of the remaining 11 lots (400- 600 West Coast Highway). Fluter
has complied with all conditions of the settlement and has abated all nuisances associated with
this property. Staff has supported Fluter's efforts to aesthetically enhance and re -use the six
existing buildings that occupy the site. The buildings have been upgraded and leased out to new
commercial and retail tenants.
M
L.
O
N
U)
Cz
N
O
W
N
s..
O
d
U
N
L.
O
3
Ong
VBAS Properties
Fluter Properties
Project Tracking Report (October- December 2010) Page 3
O
N
a
Cn
V)
CU
CO
s..
a�
d
v
N
0.
O
a�
i
PROJECT 2
PROJECT: Acquisition of Coast Highway
Department(s): Public Works
Project Lead: Dave Webb
Project Start Date: January 2004
Target Completion Date: Winter 2012
Description:
The objective of this project is to initiate a long range planning process to create a Mariner's
Mile Traffic, Pedestrian and Parking Comprehensive Plan. The first step is to acquire ownership
of Coast Highway between Jamboree Road and Santa Ana River and Newport Boulevard
between Finley Street and West Channel Bridge from the State of California Department of
Transportation ( Caltrans). The process involves passing the appropriate legislation, having the
State review the facility for ability to relinquish and its state of repair, providing a report to the
City on the facility, development of an offer for City to take the facility, and the City to chose
whether it would accept the offer. There is no defined schedule for this process and it is
expected to be rather lengthy to accomplish.
Funding Source: Sources for future improvements to be determined
Total Funding Required for Project: To be determined
Funding Allocated to Date: None
Amount Spent to Date: None other than staff time
Status to Date:
Section 73 of the Streets and Highways Code allows the California Transportation Commission
to relinquish state highways through a prescribed process. Caltrans has prepared a Project
Study Report that documents an assessment of the condition of the two segments of state
highway to be considered for relinquishment and has circulated the report within its
organization. On September 16, 2010, staff met with Caltrans to discuss its tentative findings of
the current condition assessment of the two highway facilities. Caltrans informed staff that they
found the facilities to be in a good state of repair and would offer $0 for its relinquishment.
Project Tracking Report (October- December 2010) Page 1
O
V)
V)
O
f�
N
c0
O
a
U
U
M
4-
L.
O
Q7
i
Project 2
Acquisition of Coast Highway
Staff expressed concern with this position and requested Caltrans review / correct various
existing items such as traffic signals, drainage structures, failed pavement areas, failing slopes,
etc., prior to finalizing the report and determining the value of relinquishment. Caltrans agreed
to conduct further review and update its report
Project Tracldng Report (October- December 2010) Page 2
0
o~
0
as
a�
0
0
oa
z.
cC
a
U
t�
N
W
r.-+
s..
O
N
ii
PROJECT 3
PROJECT: Balboa Village Visioning
Department(s): Community Development
Project Lead: James Campbell, Acting Deputy Director
Project Start Date: February 2010
Target Completion Date: December 2010
Description:
The completion of an updated vision for the Balboa Village area to support revitalization and
sustained economic growth while supporting the efforts of the Newport Harbor Nautical
Museum and Balboa Theater. The Newport Harbor Nautical Museum has conceptual plans for
the future expansion of their maritime museum presently located within the Balboa Fun Zone
and the Balboa Theater Foundation also has plans for the future reconstruction of the
performing arts theater located at 707 E. Balboa Boulevard.
Funding Source: None identified
Total Funding Required for Project: $100,000 (estimated)
Funding Allocated to Date: None identified
Amount Spent to Date: None
Status to Date:
It was anticipated that the City and major stakeholders within the area would join together to
form a partnership to fund and manage the preparation of an updated vision for Balboa Village.
An updated vision could lead to changes in land use, parking or economic development policy to
create an environment for the economic success of the district while maintaining compatibility
with nearby residential uses.
Project Tracking Report (October- December 2010) Page 1
O
S�
N
CG
a�
O
O
0�
O
c�
O
d
U
CT<
N
S.
O
PROJECT 3
Balboa Village Visioning
h1 .
NHNM ��
Theater
i a<N
f�.
aW
Balboa Village
Past vision and planning documents were collected and reviewed, and as a result, the need for
an economic analysis was identified. Pursuant to Council direction, the Balboa Market site was
purchased and a surface parking lot was developed to support businesses and visitors. Staff
completed the preliminary groundwork in support of a parking management district to enhance
parking resources. Further progress on this visioning project was stalled due to staffing and
budget constraints. If this project is to be continued, City Council direction is requested to re-
affirm its priority and funding. The estimated budget of $100,000 would include retaining a
project manager, planning /architectural consultant, a financial consultant and City staff time.
Budget expenditures could be off -set by private contributions.
Project Tracking Report (October- December 2010) Page 2
s.
O
N
CC
Ln
Ln
N
O
w
s
ro
o'
U
c6
N
L.
O
�L
3
Ong
PROJECT 4
PROJECT: Banning Ranch
Department(s): Community Development, Public Works and City Manager's Office
Project Lead: Patrick Alford, Planning Manager
Project Start Date: August 2008
Target Completion Date: January 2013
Description:
The General Plan contemplates two uses for the Banning Ranch: acquisition for open space or a
planned community consisting of retail, hospitality, recreational, open space and residential
uses. Newport Banning Ranch is a 402.3 -acre planned community proposed by Newport
Banning Ranch, LLC, a partnership formed by Aera Energy, Cherokee Investment Partners, and
Brooks Street The project would contain a maximum of 1,375 dwelling units, 75,000 square
feet of retail commercial, a 75 -room "boutique' hotel, parks and open space. The site is
generally bound to the north by Talbert Nature Preserve /Regional Park (Costa Mesa) and to the
south by West Coast Highway and the Newport Shores Community; to the east by Newport
Crest Community, West Newport Mesa, and Westside Costa Mesa; and to the west by a U.S.
Army Corps of Engineers wetlands restoration area and the Santa Ana River. Approximately 40
acres of the site are located within the incorporated boundary of the City of Newport Beach; the
remainder of the site is within unincorporated Orange County, but within the City of Newport
Beach's adopted Sphere of Influence.
Funding Source: General Fund (off -set by application fees)
Total Funding Required for Project: $3.5 million (estimated)
Funding Allocated to Date: $2,317,000
Amount Spent to Date: $2,315,398
Project Tracking Report (October- December 2010) Page 1
S?.
W
Sr
.M
W
N
ca
d
U
c6
N
O
�L
3
Ong
PROJECT 4
Banning Ranch
Status to Date:
The exploration of funding sources for the acquisition of the Banning Ranch is continual, but to
date, no funding sources have been identified.
Newport Banning Ranch (NBR) submitted applications to the City in August of 2008 for the
development of the property consistent with the General Plan. NBR is finalizing their drafts of
the proposed Planned Community (PC) text and the Master Development Plan (MDP), which
were expected to be submitted to the City for final review by the end of January 2011.
_ v
-F
The Tentative Tract Map (TTM) submitted by NBR has undergone extensive review by City staff
and will be finalized following the completion of the PC text and MOP. The target completion
date for the PC text, MDP, and TTM is March 2011. A draft of the Development Agreement (DA)
is expected to be submitted to the City for staff /City Council Committee review by February
2011. The target completion date for the draft DA is March 2011.
Project management has transitioned from a special projects coordinator within the City
Manager's Office to the Planning Division. The existing team of consultants who have been
working on the project have been retained to provide continuity within the overall review
Project Tracking Report (October- December 2010) Page 2
s.
O
Q,
N
CC
Ln
Ln
N
O
O
W
s.
N
ca
O
d
U
c6
N
L.
O
�L
3
Ong
PROJECT 4
Banning Ranch
process.
Staff and consultants have been in the process of preparing a Draft Environmental Impact
Report (DEIR) including all necessary technical studies. The final draft will be completed once
the PC text, MDP, DA and TTM are finalized. Publication of the DEIR with a 60 -day public
comment period is anticipated in Anril 2011. Following DEIR public comment period, responses
to public comments and a draft Final EIR will be prepared and submitted along with the project
for public hearings before the Planning Commission that are anticipated to begin in the Summer
of 2011. The Planning Commission's recommendation will be forwarded to the City Council for
hearing and final action in the Fall of 2011. Should the City Council approve the project, an
application will be submitted to the California Coastal Commission (CCC) by Newport Banning
Ranch. Processing by the CCC staff is anticipated to take a minimum of 15 months.
Project Tracking Report (October- December 2010) Page 3
0
rx
N
0
oa
N
ct<
O
d
v
cC
N
W
O
O
PROJECT 5
PROJECT: City's Harbor Fees
Department(s): Public Works/ City Manager's office
Project Lead: Chris Miller, Dave Kiff
Project Start Date: Summer 2010
Target Completion Date: December 2011
Description:
This project consists of updating Harbor Resources' cost of service fees and updating the City's
harbor fees to reflect the fair market value for the use of the Tidelands by the associated user
groups. Fees include permits for moorings, Balboa Yacht Basin slip rates, and commercial pier
leases. These fees contribute to harbor projects such as dredging and the provision of additional
harbor amenities.
Funding Source: Tidelands
Total Funding Required for Project: None to date. However, consultant funding is
required to negotiate leases for all of the commercial marina owners. The RFP is currently
under review by OCA.
Funding Allocated to Date: None
Amount Spent to Date: Not available at this time. The City hired MGT Services to
update City wide cost of services including harbor related fees.
Status to Date:
The Harbor Commission will be recommending a conceptual review for a Mooring Support
Service Center idea to the City Council in February 2011 to address mooring owner needs. In
the fall of 2010, City Council approved Harbor Resources cost of services fees, with
Administrative Services implementation estimated in the next couple months. Revised mooring
fees and Balboa Yacht Basin fees (boat slips, garages, and apartments) were approved by
Council in November /December 2010. Staff has worked on the last component of evaluating
the commercial marinas and converting their annual permits to commercial leases.
Project Tracking Report (October- December 2010)
0
a
rx
CU
r~
N
o'
v
CU
N
0.
0
0
M1
PROJECT 6
PROJECT: Civic Center Project
Department(s): Public Works
Project Lead: Steve Badum
Project Start Date: April 2010
Target Completion Date: December 2012
Description:
The Civic Center Project includes a City Hall Office Building, one of the city's largest parks (16
acre), a 450 -space parking structure, and an expansion of the Newport Beach Central Library. It
is located on two parcels inland of the Newport Beach Central Library and bordered by Avocado
Avenue and MacArthur Boulevard. The project also includes a community room, new Council
Chambers, a "One Stop" Customer Service Center, dog park, passive wetlands park, a civic green,
and a small cafe to service library and city hall customers.
Funding Source: Bond Proceeds /General Fund
Total Funding Required for Project: $128,000,000 (estimated)
Funding Allocated to Date: $128,000,000*
Amount Spent to Date: $18,542,143 (through 12/31/10)
*includes financing
Status to Date:
The Civic Center Project is on schedule and budget. The first phase (Soil Export, Grading, and
the construction of the Parking Structure Shoring Wall) is nearing completion with soil export
substantially complete and the shoring wall to be completed in February. The second phase
(Parking Structure) will begin foundation construction in March. Bid packages for the third and
final phase (City Hall Office Building, Library Addition, and Parks construction) will be
presented to City Council on February 22, 2011 for approval. The project is scheduled to be
substantially complete during the Fall of 2012 with the grand opening planned for December
2012.
Project Tracking Report (October- December 2010)
I
PROJECT 6
Nevrport Beach CivicC enter and Park Boh H nCyviinski Jackson I PWP
Newponsemi. caINmN MAY 10, MIG
z.
O
�1.
N
CG
Ln
V)
w
N
c�
O
o'
U
c6
a�
0�
O
�L
3
a�
M!
PROJECT 7
PROJECT: Comprehensive Parking Program for the Balboa Peninsula
Department(s): Community Development & Public Works
Project Lead: Leigh M. De Santis, Economic Development Administrator
Project Start Date: January 2010
Target Completion Date: December 2010
Description:
The project includes implementation of a comprehensive parking program for the Balboa
Peninsula with the broad goal to optimize the use of existing parking resources and to explore
opportunities to increase public parking supply. Walker Parking Consultants studied two
geographic areas on Balboa Peninsula; Balboa Village and the Lido /Cannery /McFadden Square
area. One recommendation was to modify the pricing of on- street and public parking spaces to
increase access and optimize their use and availability to the public. An opportunity also
became available to increase parking supply in Balboa Village through the purchase the Balboa
Market site and the expansion of the existing public parking lot located at the intersection of
Palm Street and Balboa Boulevard.
Funding Source(s): General Fund, Neighborhood Enhancement B Reserve Account, the
Off- Street Parking Reserve Account, and the [n -Lieu Parking Reserve Account.
Total Funding Required for Project: $75,000 estimated for consulting assistance
and 1.0 FTE split between CDD and Public Works.
Funding Allocated to Date: $3,664,765 (does not include staff time)
Amount Spent to Date: Appraisal: $12,000, Environmental clearance: $2,250,
Acquisition: $3.5 million, demolition and construction of the parking lot: $150,515.
Status to Date:
Due to the differing geographic characteristics of the Balboa Peninsula and the
recommendations provided by Walker Parking Consultants, parking management efforts were
limited to Balboa Village as a way to test and validate the precepts. Progress was made toward
the creation of a parking management plan or district and the City purchased the Balboa Market
site and expanded the Palm Street public parking lot.
Project Tracking Report (October- December 2010) Page 1
S.
7�.
N
ry
Ln
V)
U
N
r-.
v
c�
o'
U
c6
a�
0�
O
�L
3
Ong
PROJECT 7
Comprehensive Parking Program
Public Parking Lot Expansion - The City took possession of the Balboa Market property in
March 2010. Public Works staff prepared designs for the parking lot and managed Coastal
Commission approvals, demolition of the market building, and the construction of the 32 -space
parking lot. The expanded parking lot was completed and opened to the public in December of
2010.
�W
Palm Street Public Parkm9 yQl o'"cs , •' �Ii'Bwae y-e.
Yoh,
® i y- ins
jy
'! Former Balboa Market Site
Parking Management Plan or District - Based upon the recommendations of the Walker
Consultants report and City Council direction, Community Development staff prepared a
parking management plan. Included within the plan was the creation of a parking management
district where public parking revenues would be collected and used to manage existing public
parking and where feasible, expand public parking. The pricing of public parking would be
modified and seasonally adjusted to improve access to spaces. The parking management district
was presented to the City Council at the study session on September 28, 2010. The Council
placed the project on hold pending a more comprehensive look at Balboa Village (see status of
the Balboa Village Visioning).
Project Tracking Report (October- December 2010) Page 2
s.
O
Q,
N
CG
Ln
V)
N
O
O
r-.
s..
O
c�
O
d
U
c6
N
L.
O
�L
3
Ong
PROJECT 7
Comprehensive Parking Program
Next Steps - If deemed a priority by the City Council, next steps includes the continuation of
comprehensive parking management strategies for Balboa Village as well the remainder of the
Balboa Peninsula, provided sufficient funding sources can be identified. Parking management
for the Balboa Village would be a component of the broader visioning effort to be undertaken.
Project Tracking Report (October- December 2010) Page 3
t.
O
fL
N
CC
Ln
Ln
N
O
O
W
s
N
c�
O
o'
U
c6
N
L.
O
cL
3
Ong
PROJECT 8
PROJECT: Group Homes
Department(s): Office of the City Attorney, City Manager's Office; Planning
Project Lead: City Attorney and City Manager
Project Start Date: 2007
Target Completion Date: ongoing
Description: Group homes: Implement and defend group home regulations to maintain
the residential character of the City's residential neighborhoods while providing equal access to
housing and accommodating the needs of the disabled.
Funding Source: General Fund and Fund Balance
Total Funding Required for Project: All costs have not been specifically identified
since a great deal of the costs are internal, staff resources from the City Manager's Office, Office
of the City Attorney, Planning, and Code Enforcement.
Funding Allocated to Date: $2.8 million in outside counsel and litigation costs to date
with an additional $225,000 anticipated in this fiscal year and $400,000 next fiscal year.
Amount Spent to Date: $2.8 million on outside counsel plus internal staffing costs and
cost of Hearing Officer in administrative
Status to Date:
(1) Initial preparation of ordinance and implementation of the administrative process for
existing operators completed by February of 2010; (2) Ongoing defense of the ordinance in the
Federal Court successful to date through victories on motions to dismiss portions of the
complaints and motions for partial summary judgment with a trial date now scheduled August
2, 2011, then an anticipated appeal that could last up to two years; (3) Enforcement of the
ordinance and two zoning agreements used as vehicles to settle the cases of two operators
ongoing.
Project Tracking Report (October- December 2010)
z.
O
N
tx
N
r~
ov
U
CU
N
0.
O
ai
i
PROJECT 9
PROJECT: Implement Traffic Management Plan
Department(s): Public works
Project Lead: Antony Brine
Project Start Date: December 2002
Target Completion Date: 2012
Description:
The City is undertaking work to improve traffic signal system reliability, traffic flow, and reduce
congestion. Current traffic management projects include a combination of traffic signal
rehabilitation improvements and Phases 4, 5, and 7 of the traffic signal modernization program.
The annual traffic signal rehabilitation program provides required maintenance and
improvements of existing equipment. The traffic signal modernization program is a multi-
phased effort to install new software, CCTV live feedback equipment, and fiber optic cable that
allows staff to adjust signal timing from the traffic management center at City Hall. Current
efforts include improvements to intersections around Balboa Peninsula, Superior Avenue, and
Irvine Avenue. Phase 5 improvements address intersections in the Newport Center area.
Funding information below only includes estimates for the traffic modernization program.
Funding Source: Transportation and Circulation, Measure M Turnback, Measure M
Competitive
Total Funding Required for Project: $7,500,000
Funding Allocated to Date: $5,000,000 (excludes Phases 6 and 8)
Amount Spent to Date: $3,886,035
Status to Date:
Phases 1 -3 of the traffic modernization program are complete and operational. Phases 4 and 7
are substantially complete. Phase 5 of the traffic signal modernization program is currently in
design and will be combined with a traffic rehabilitation project. Award of a construction
contract is anticipated in spring 2011.
Project Tracking Report (October- December 2010)
0
rx
N
5~
O
N
c�
O
d
v
cC
N
W
O
a�
PROJECT 10
PROJECT: Incorporate a Public Art Component in new Civic Center
Department(s): Public Works and Library Services
Project Lead: Steve Badum and Cynthia Cowell
Project Start Date:
Target Completion Date: December 2012
Description:
Goal 6 pertains to Community Enhancements to increase opportunities for recreational and arts
enjoyments, provide for essential facilities and facilitate sound land use decisions. The
objective is this project is to incorporate public art as part of the new Civic Center project.
Funding Source: Civic Center Bond Proceeds and Private Contributions
Total Funding Required for Project: to be determined
Funding Allocated to Date: None
Amount Spent to Date: None
Status to Date:
A memorandum of understanding has been executed with the Orange County Museum of the
Arts for the acquisition and installation of art work as part of the Civic Center project.
Additional art will be acquired and installed when construction of the buildings and park is
completed. The Civic Center Park design incorporates willow structures by Patrick Dougherty
and animal sculptures in the various meadows.
Project Tracking Report (October- December 2010)
PROJECT 10
abAss
Children's Discovery Elements
77
Nev�port Beach CivicC enter and Park nonllnuywnsn dacx sons vvvY
NewlP n6exk. CallonU FIPy Ia. 9110
t.
O
a�
cC
Ln
Ln
a)
w
s.
N
ct<
O
d
U
c6
a�
0�
O
�L
3
a�
nf
PROJECT 11
PROJECT: Irvine Company's North Newport Center Project
Department(s): Community Development
Project Lead: Patrick Alford, Planning Manager
Project Start Date: March 2011
Target Completion Date: May 2011
Description:
Irvine Company has notified City Staff of their plans to construct a new office building within
Block 600 of Newport Center. The exact location has not been identified at this time. The North
Newport Center Planned Community (PC) text requires any development to be submitted to
Plan Review by the Planning Director in order to determine compliance with the PC text The
Plan Review application will include floor plans, elevations, parking plans, and preliminary
landscape plans.
Funding Source: General Fund (off -set by application fees)
Total Funding Required for Project: Funded through budgeted staff resources,
$2,200 application fee
Funding Allocated to Date: Existing budgeted resources
Amount Spent to Date: Unknown
Status to Date:
In January 2010, the City Council approved a transfer of developments rights, which included
the transfer of 50,000 square feet from Block 500 to Block 600. In October 2010, the City
Council approved a transfer of development rights, which included the transfer of 45,236
square feet of general office from Block 100 to Block 600. Staff has reviewed and approved on
schedule the Irvine Company's request for seismic retrofit of the Block 600 parking garage.
The Irvine Company has not submitted plans for new construction within the North Newport
Center Planned Community to date; however, staff has had preliminary meetings with project
proponents. When the plans are submitted, Staff will administratively review the plans to
Project Tracking Report (October- December 2010) Page 1
s.
O
Q,
N
CC
Ln
Ln
N
O
O
W
s.
N
c�
O
d
U
c6
N
L.
O
�L
3
Ong
PROJECT 11
Irvine Company's North Newport Center Project
determine compliance with the PC tent and Development Agreement. When compliance is
determined, the Irvine Company will submit the all the necessary architectural and structural
plans and calculations to the Building Division for the review and issuance of a building permit
for construction.
Project Tracldng Report (October- December 2010) Page 2
O
S=L
a�
cC
Ln
Ln
a)
w
s.
N
c�
O
d
U
c6
a�
0�
O
�L
3
Ong
PROJECT12
PROJECT: Lido Village Conceptual Planning
Department(s): Community Development
Project Lead: James Campbell, Acting Deputy Director
Project Start Date: June 2010
Target Completion Date: October 2010
Description:
Provide planning for the future vision and improvement of the Lido Village area that is
generally bounded by Newport Boulevard, Newport Bay and 32nd Street. The process and
necessary resources were identified in July 2010. The process consisted of a public /private
partnership with Fritz Duda Company and Vornado Partners to jointly fund and manage a
conceptual planning effort. The purpose of the effort was to create a process and plan to guide
redevelopment of Lido Marina Village, facilitate pre - planning for the Duda shopping center due
to the relocation of Pavilions and to identify re -use opportunities for the existing City Hall site.
Funding Source: General Fund & Private Funds
Total Funding Required for Project: $75, 000 total
($25,000 from the General Fund & $50,000 from major stakeholders)
Funding Allocated to Date: $25,000 from unallocated reserves was allocated on July
27, 2010
Amount Spent to Date: $25,000
Status to Date:
Tim Collins was retained by the public /private partnership in August 2010. Proposals from
several planning firms were evaluated and a grouping of consultants consisting of William
Hezmalhalch Architects, The Concord Group and Government Solutions was selected. Planning
began in September with a ULI Technical Advisory Panel, consultation with City Staff and
targeted public outreach. Four 90% draft plans were presented to the City Council on
11/23/2010, and direction was provided and additional public outreach was conducted. Two
final draft plans were presented to the City Council on 1/11/2011, and the Council provided
input and direction on re -use opportunities for the existing City Hall site.
Project Tracking Report (October- December 2010) Page 1
0
u.
0
rx
V)
O
5~
O
W
N
Cz
sz
O
d
U
ns
N
O
f-L
3
Ong
i
!
i
ladr Sao
!!
Wt6
ALTERNATIVE 5B
PROJECT12
Lido Village Conceptual Planning
The final plan above was presented to the City Council on January 25, 2011, and the Council
directed staff to prepare an action plan for the implementation of Alternative 5b including the
planning for a community center and housing at the existing City Hall site. A lot line adjustment
between the City Hall site and the Duda property and a potential specific plan are contemplated.
Project Tracking Report (October- December 2010) Page 2
!
� Ya••S
a••a
Jj
r ♦ J
ALTERNATIVE 5B
PROJECT12
Lido Village Conceptual Planning
The final plan above was presented to the City Council on January 25, 2011, and the Council
directed staff to prepare an action plan for the implementation of Alternative 5b including the
planning for a community center and housing at the existing City Hall site. A lot line adjustment
between the City Hall site and the Duda property and a potential specific plan are contemplated.
Project Tracking Report (October- December 2010) Page 2
0
a
CU
0
0
o'
v
CU
CU
0.
0
a�
i
PROJECT 13
PROJECT: Lower Bay Dredging Project
Department(s): Public Works
Project Lead: Chris Miller
Project Start Date: 2012
Target Completion Date: 2013
Description:
This project includes dredging the main navigational channels in the Lower Bay by the
federal government. There is approximately 1 million cubic yards of material to be
dredged with most of the sediment being suitable for ocean disposal at the off -shore
site "LA -3". The remaining material is unsuitable for ocean disposal and needs to be
disposed of at an alternate approved location. It is anticipated the project will not
obtain full funding and which will require it to be spread over multiple years.
Funding Source: Federal Funds, Tidelands
Total Funding Required for Project: —$25 Million
Funding Allocated to Date: $100,000 (CIP) and—$2.5 Million (federal funds)
Amount Spent to Date: $400,000 (0 &M Tidelands) for sediment testing
Status to Date:
Staff is coordinating with and assisting the Army Corps of Engineers. There are two
major hurdles to overcome: funding and sediment disposal. The City's local and D.C.
lobbyists are exploring creative solutions within the Corps' funding mechanism to
ensure this project moves forward in a timely manner. Some sediment material is
deemed unsuitable for disposal in the ocean and must be disposed at an alternate
location. Previously, the City applied to the Port of Long Beach (POLB) for disposal in
their Middle Harbor fill site, but the request was not granted because the City's
quantities exceeded capacity. There is a possibility that the window with the POLB may
in 20
Project Tracking Report (October- December 2010)
O
Q
N
ry
U
O
c
00
T
L
L
cu
C�
U
O
N
m
O
Q
N
Z
PROJECT 14
PROJECT: Marina Park
Department(s): Public Works
Project Lead: Dave Webb
Project Start Date: 2007
Target Completion Date: 2013
Description:
Between 2005 and 2009, the City worked with various citizen groups, the Harbor Commission,
and a 9- member Council /Citizens Advisory Committee to develop a plan to replace the current
mobile home park between 18th Street and 15th Street along West Balboa Boulevard (on the
"Bay" side of Balboa Boulevard) with something more visitor - serving. The Marina Park project
proposes new visitor - serving marina facilities, an aquatics sports building, community center
and community park. The Environmental Impact Report was completed in spring 2010. The
next step involves approval and permitting by the California Coastal Commission which began
in 2010. Considering the City's current budget challenges, the City Council has not decided
whether to implement the project in phases or to construct the entire park and marina project
at once. Among the things that will influence the Council's decision is the City's success in
receiving Federal and State grants and /or loans.
Funding Source: General Fund and undetermined sources
Total Funding Required for Project: To be determined
Funding Allocated to Date: $4,470,727 (not including settlement agreement costs)
Amount Spent to Date: $1,361,766.37
Status to Date:
Currently, the Coastal Commission and federal agencies are reviewing the project. The status of
the various permit /approvals required is:
CA Regional Water Control Board 401 Permit - Permit obtained 12/22/2010
US Army Corp 404 Permit - Application submitted. Letter of Public Noticed being issued.
CA State Land Boundary Agreement & Project Concurrence - Approval expected late Spring
Project Tracking Report (October- December 2010)
Page 1
PROJECT 14
Marina Park
2011.
CA Coastal Commission Permit - Application submitted. Responded to first Incomplete
Application letter. Received second Incomplete Application letter stating project needs CA State
Lands Commission approval to proceed.
Staff is also continuing to negotiate with the Southern California Edison Company to purchase a
surplus piece of property adjacent to the south side of the project.
Project Tracking Report (October- December 2010) Page 2
s.
O
N
tx
Cu
N
o'
v
CU
N
0.
O
i
PROJECT 15
PROJECT: Reduce Fire Hazard in Buck Gully and Morning Canyon
Department(s): Fire
Project Lead: NBFD Fire Marshal Ron Gamble
Project Start Date: Dependent on the final Cal Fire FHSZ Maps due in early 2011
Target Completion Date: Once the maps are completed and available from the state,
they will be submitted to the City Council. Then scheduling of public hearings on the subject can
take place and the CAL FIRE map can be adopted by the city council. This will become part of
the annual hazard reduction program.
Description:
(CAL FIRE) began a project in 2007 to update the Fire Hazard Severity Zone Map for all areas of
California. The data used in the development of these scientific computer modeled maps
combines recognized risk factors like fuel loading, fire weather, topography, emergency access,
building construction and satellite imagery to pinpoint hazards from wildfire. The very high fire
hazard severity zones include areas where winds have been identified by Cal Fire as a major
cause of wildfire spread, such as our annual Santa Ana wind storm conditions. Due to budget
cuts, this project has taken longer than expected to complete but should be available in early
2011.
With the SB1595 written by Senator Kehoe, the California Legislature found and declared that
Wildfires are extremely costly, not only to property owners and residents but also to local
agencies. Preventive measures are therefore needed to ensure the preservation of the public
peace, health, or safety. The wildfire front is not the only source of risk since embers, or
firebrand, travel far beyond the area impacted by the front and pose a risk of ignition to a
structure or fuel or fuel on a site for a longer time. The prevention of wildland fires is not a
municipal affair, as that term is used in Section 5 of Article XI of the California Constitution, but
is instead, a matter of statewide concern. It is the intent of the Legislature that, this chapter
applies to all local agencies, including, but not limited to, charter cities, charter counties, and
charter cities and counties. This subdivision shall not limit the authority of a local agency to
impose more restrictive fire and public safety requirements, as otherwise authorized by law.
Project Tracking Report (October- December 2010) Page 1
0
a.
ryo
N
s~
0
w
ca
O
d
v
N
W
s.
O
L�.
3
Ong
PROJECT 15
Reduce Fire Hazard in Buck Gully and Morning Canyon
Because this bill would change the definition of a crime, it would impose a state - mandated local
program. Although SB 1595 is a state mandated program, no reimbursement is required by this
act pursuant to Section 6 of Article XIII B of the California Constitution because the only costs
that may be incurred by a local agency will be incurred because this act creates a new crime
within the meaning of Section 17556 of the Government Code, or changes the definition of a
crime within the meaning of Section 6 of Article XIII B of the California Constitution.
SB 1595 became law in 2008 and the CAL FIRE maps will allow the provisions of this law to be
enforced.
It requires a person who owns, leases, controls, operates, or maintains an occupied dwelling or
structure within a very high fire hazard severity zone to maintain defensible space no greater
than 100 feet from each side of the structure. It will involve removing or reducing vegetative
and non vegetative fuels (wood piles and combustible materials).
Funding Source: unknown
Total Funding Required for Project: unknown
Funding Allocated to Date: Currently we have $190,000 budgeted for Fuel
Modification maintenance Account 2330 - 80804. Our city wide, weed abatement and hazard
reduction programs from 2330 - 8080 has $46,114.
Amount Spent to Date: $163,085 from 80804 and $44,564 from 8080
Status to Date:
The second revised map is currently up in Sacramento for final approval and is anticipated to be
available in the first half of 2011. All local comments to the draft FHSZ map were provided to
Cal Fire/ SFM staff on December 21st 2010. At that time, Cal Fire staff told us that they were
planning on beginning their work in early January, so 1 assume they've already begun. We were
also told that they plan to establish a method to make the process more visible to each city
while it occurs. That will likely mean we will be provided access to a website that will be
regularly updated. As soon as they make that happen I will pass the information along.
Project Tracking Report (October- December 2010) Page 2
PROJECT 15
Reduce Fire Hazard in Buck Gully and Morning Canyon
Please attach a location map if the project is site specific: One portion of the VHFHZ map is
attached showing
s.
O
N
tx
N
O
O
N
ca
O
d
v
cC
N
W
O
�1.
a�
Project Tracking Report (October- December 2010) Page 3
0
s�.
N
CC
Ln
Ln
N
O
0
w
s.
O
s.
ct<
O
o'
U
U
N
t�
O
3
Ong
`,
PROJECT 16
PROJECT: Restructure Development Services
Department(s): City Manager's Office & Community Development
Project Lead: Dana Smith, Assistant City Manager and
Joel Fick, Interim Community Development Director
Project Start Date: February 2010
Target Completion Date: July 2011
Description:
In February 2010, City Council identified "Effective Management" as a specific goal. A project
within this goal included restructuring the development services function for improved
coordination among disciplines, and continued improvement in customer service. The City
Manager's Office took action steps toward addressing this goal and project by combining the
Planning and Building Departments.
Funding Source: General Fund
Total Funding Required for Project: Funded through budgeted staff resources.
Funding Allocated to Date: Existing budgeted staff resources.
Amount Spent to Date: Salary savings experienced from funding Interim Community
Development Director position from two vacant Department Head positions.
Status to Date:
Vacancies in the two Department Head positions for Planning and Building afforded the
opportunity to proactively address restructuring of the departments and related customer
service issues. In mid October an Interim Community Development Director was hired. A
number of very focused customer service initiatives have been implemented, including
numerous procedural and operational improvements. Enhancements have also been initiated
to improve counter customer service and reduce permit issuance timeframes, expedite issue
and problem resolution, and improve navigation of the web site and direction of telephone
contacts. Additional improvements, including on -line permitting and electronic plan checking,
are also being explored.
Project Tracking Report (October- December 2010) Page 1
s.
O
Q,
N
CC
Ln
Ln
N
O
O
W
s.
N
c�
O
d
U
c6
N
L.
O
�L
3
Ong
PROJECT 16
Restructure Development Service
City Council on January 25, 2011, approved the staffing and organizational changes for the
Community Development Department. A recruitment is currently underway for the permanent
Community Development Director position. Full implementation of the reorganization is
anticipated during the next several months.
Project Tracidng Report (October- December 2010) Page 2
0
rx
s~
0
N
c�
O
d
v
cC
N
W
O
O
PROJECT 17
PROJECT: Rhine Channel Contaminated Sediment Cleanup
Department(s): Public Works
Project Lead: Chris Miller
Project Start Date: August 2011
Target Completion Date: December 2011
Description:
This project will remove contaminated sediments from the Rhine Channel in Lower Newport
Bay as well as from nearby areas found unsuitable for unconfined ocean disposal under
Regional General Permit S4 issued by the U.S. Army Corps of Engineers. The project will
remove contaminated sediments to restore and enhance state - designated impaired beneficial
uses of the Rhine Channel, dispose of material in an environmentally responsible and cost -
effective manner, and improve navigation.
Funding Source: Tidelands
Total Funding Required for Project: $4,000,000.00
Funding Allocated to Date: $4,000,000.00
Amount Spent to Date: None
Status to Date:
The project is shovel ready with construction documents complete. The bid package will be
released by February 18, 2011, for 30 days with an anticipated Council approval in April. A
conditional Coastal Permit was issued in January 2011 and a Water Board permit was secured.
A permit from the Army Corps of Engineers is expected in February 2011. Also, the Port of
Long Beach's Memorandum of Agreement for disposal will be sent to the City for approval soon.
The anticipated start date is August 2011 but is dependent on the Port of Long Beach schedule.
The project should take 4 months and should be complete by December 2011. A location map is
attached.
Project Tracking Report (October- December 2010)
PROJECT 17
SOURCE: Basemap prepared from City of Newport Beach GIS files.
NOTE: Temporary moorage areas are located throughout Lower
Newport Bay.
,� �Q ANCHOR
�[,,, OEA
LEGEND:
M
Proposed Project Area
Pierhead Lines (Approximate)
0
01000
Scale in Fee
Figure 2
Proposed Project Area
Rhine Channel Contaminated Sediment Cleanup
0
rx
0
O
t�
N
c�
O
d
v
cC
N
W
O
�1.
a�
PROJECT 18
PROJECT: Sunset Ridge Park
Department(s): Public Works & Recreation & Senior Services
Project Lead: Mike Sinacori
Project Start Date: 6/1/2007
Target Completion Date: Winter 2012
Description:
The proposed 13.7 acre Sunset Ridge park is situated on the northern corner of the West Coast
Highway and Superior Avenue in West Newport Beach. Sunset Ridge Park is to be an active
park per the city's General Plan with amenities including Pony League baseball field, soccer
fields, parking area, restroom, butterfly garden, shaded viewpoint, walkways, walls, signs, and
fencing.
Funding Source: General Fund and Park -in -lieu
Total Funding Required for Project: $11,125,000.00
Funding Allocated to Date: $11,125,000.00
Amount Spent to Date: $1,456,493.32
Status to Date:
Staff is currently working to obtain all necessary regulatory permits including a Coastal
Development Permit from the California Coast Commission. Construction of the park, entry
road and traffic signal at West Coast Highway could begin in Fall of 2011 and is estimated for
completion in Winter 2012.
Project Tracking Report (October- December 2010)
PROJECT 18
t
I
II �
Entry laza
y
Retaining Wall
Memorial Garden
Vehicular Access
I \ r Restrooms
Walking Path
1\ \\ \
Overlook with
Shade Structure
`t • ���— \
& Seating
Y
Pedestrian
cc Field
Access
Ls
\� > Soccer Field
p
_
Pedestrian
----- --..�— - .^,�— Stair
Access
PAOF�I HIGgyyAV
�
Pedestrian Play Area
--
_ _ Access
Park Sign
Conceptual Site Plan
Exhibit 3 -9
Sunset Ridge Park EIR
• •
��jj
ZP del!
C O N S U L T I N G
(Rev 1=2V9 KFD) PmjxffiMewpaNJ018IGPappIEIR /Ex3 -0_CSP.pM
0
rx
0
0
w
N
c�
O
d
v
cC
N
W
O
a�
PROJECT 19
PROJECT: Transportation Fair Share Fee
Department(s): Community Development
Project Lead: Formerly Sharon Wood
Project Start Date: Feb 2007
Target Completion Date: Spring 2011
Description:
In 1984, City Council established the Fair share Traffic Contribution Ordinance to alleviate
funding shortfalls of the City's Master plan of Arterial highways and General Plan Traffic
Circulation Element. The ordinance established a fair and equitable method to distribute costs
of the circulation system improvements necessary to accommodate the traffic volumes
generated by development. From time to time, the City Council has updated this ordinance as
costs have risen and whenever the General Plan has been updated. The city recently updated
the General Plan and the General Plan Implementation Committee has been pursuing an update.
Funding Source: General Fund
Total Funding Required for Project:
Funding Allocated to Date:
Amount Spent to Date:
Status to Date:
The completion of this project has stalled with various iterations being proposed by The
General Plan /LCP implementation committee, project consultant and interested parties such as
the BIA. The most recent version of the Fair Share fee was reviewed by GP /LCP committee and
final draft is being prepared by a consultant.
City Manager's Quarterly Report (October- December 2010)
O
a
N
rx
w
C.
cz
7
o'
v
Cz
N
W
O
t1.
a�
PROJECT 20
PROJECT: Widen Jamboree Road in the Airport Area
Department(s): Publicworks
Project Lead: AndyTran
Project Start Date: January 2005
Target Completion Date: June 2012
Description:
This project involves widening of the Jamboree Road bridge over the 73 Freeway by 22 feet to
the west and the Jamboree Road Improvement project to widen the intersection of MacArthur
Boulevard between Bristol North and Fairchild Road in an effort to reduce traffic congestion
and delay. The bridge widening will create one additional northbound and southbound thru
lane on Jamboree Road between MacArthur Boulevard and Bristol South. The project required
developing a design and obtaining approval and a permit from Caltrans for this state owned
bridge. Additionally, the project required negotiations and purchase of three pieces of private
property as well as an OCTA grant funding application and successful funding award. The
Jamboree Road Improvement will provide one additional northbound lane and an additional
left turn lane onto southbound MacArthur Boulevard.
Funding Source: Transportation and Circulation, IBC Settlement, Measure M Turnback,
and Measure M Competitive
Total Funding Required for Project: $10,217,942.00
Funding Allocated to Date: $10,217,942.00
Amount Spent to Date: $1,647,736.41
Status to Date:
Plans and specification are complete and the bridge widening project and is currently out for
public bid. Staff expects to award the construction contract in March 2011. This past quarter,
staff resolved some outstanding right -of -way issues and secured the Caltrans encroachment
permit. Construction should begin in May 2011 and is estimated for completion in Summer
2012. The road widening project is nearing the completion of design and staff is negotiating
with property owners for the purchase of needed property. Currently, award of construction is
estimated for fall 2011.
Project Tracking Report (October- December 2010)
PROJECT 20
PROJECT LOCATION
JAMBOREE RD. BRIDGE WIDENING
LOCATION MAP
CITY OF NEWPORT BEACH
PUBLIC WORKS DEPARTMENT
N.T.S.
C -3724
X OF XX
R- XXXX -S
Rj EjVE R AGE, i DA
l =RjNTEVI - �-l1
r'
Central Newport Beach Community Association
PO Box 884 • Bewport Beach, CA • 92661 -0884
www.CentrablewporLOrg
Date: February 8, 20113
To: Mayor Henn, Members of the City Council C, i=n o
From: Central Newport Beach Community Association (CNBCA) ? m
= ap
44
Subject: Quarterly Business Report Update, Agenda Item #12, February 8, 2011 � 44 �
rn
We previously provided comments to the Saturday Workshop on 2011 goals. We would like to to this oppgl§nity 0
to comment on the subject Quarterly Business Report, and in particular, the Marina Park Tracking Report, Project
14. Staff should be commended for implementing project status using a template. It is a useful tool to keep both the
Council and residents informed of progress in 1-2 pages. We do have several concerns:
• The Marina Park (Project 14) report does not reflect the 'Status To Date" of grant fundino and "undetermined sources"
that staff have said they were working on since the Council approved the Marina Park Concept Plan, roughly 38 months
ago.
• The Marina Park (Project 14) "Status To Date" is a bit misleading as it implies that the California Coastal Commission
(CCC) is reviewing the project. It is our understanding that since early November, 2010, the CCC has considered our
Coastal Development Permit application incomplete. The status should simply state this fact.
We would also like to suggest several items that would add value to the project templates, in general:
• The reports don't contain any graphic schedules with milestones and activities. A high-level schedule would go a long
way to help answer simple questions like: Are we making progress ?, or What is the next step after the CCC?
•- Risk is not mentioned in most of the project reports. The identification of significant cost, schedule, and/or technical risk
areas, if any, are helpful in understanding the project. These can be as simple as a couple of bullets in a box, or a couple
of sentences in a paragraph and still be meaningful.
• A graphic "Dashboard" that communicates the proiect manager's status of Cost, Schedule, and Technical
issues, at a glance, would be very helpful. It can take many forms: Happy /Sad faces. Green, Yellow, Red
signal lights. All of these formats work well to communicate how the project is progressing.
Again, we ask the Council to make the Marina Park Project a management priority in 2011 so that it gamers the appropriate
attention by both City management and staff.
Thank you for the opportunity �tto— comment.
Central Newport Beach Community Association
Louise Fundenberg, President
From
77
02/08/2011 12:22 #469 P.002/002
RECEIVED
2M FEs -s PH a 10
PYCSE/ IlOA9R /eH%/OdIBP.AC�SPB,I,�'S &OpSYI Spaces
February 7, 2011 For Public Record, February 8, 2011, Council Meeting, Item 12
Honorable Mayor and Council Members
City Of Newport Beach
3300 Newport Boulevard
Newport Beach, CA 92663
Dear Mr. Mayor and Council Members:
Thank you for the opportunity to once more contribute with our thoughts on Council 2011 Priorities.
As you know, our organization has worked closely with the community, potential stakeholders, architects, City
Council members and City staff on the Marina Park Project for neatly seven years. Hundreds of hours have been
committed by POP volunteers to advance this Project in one way or another.
We have become increasingly concerned with attention given to the Marina Park project schedule, or lack
thereof. It appears that project activities that could be worked concurrently are being worked in series. Nearly
five (5) months elapsed between the date the Council certified the Environmental Impact Report and the date
the application was submitted to the California Coastal Commission. With the extended EIR preparation
period —over a year and one - half —one would have hoped the application would have been prepared
concurrently with EIR preparation. Clearly it was not.
In addition, we believe that issues which have stalled acceptance of the City's application to the Coastal
Commission could have been dealt with anytime after November 2007 when the Marina Park Concept Plan was
approved by the Council. We understand that survey and mapping efforts were required before the issue could
be resolved, but continue to be puzzled why the issue hasn't been resolved in over three years.
By our estimate, by requiring a revised EIR(-8 months), not preparing the Coastal Commission application
concurrently with the EIR ('"5 months), and not addressing issues that were undoubtedly known to be important
to the Coastal Commission ("'4 months), almost a year and one -half has been lost, to date. None of these delays
can be attributed to State bureaucracy or "standing in line, waiting our turn" as we have been told recently.
Our Coastal Development Permit application has vet to be accepted!
The bottom line is that we believe the Marina Park Project needs to be a higher priority for City
management. The project needs to be managed more effectively. Milestones alone do not make a schedule of
interrelated tasks for staff to execute. The "Project Of The Month" (and there have been many!) seems to have
been getting most of their attention. Milestones that aren't tracked against a baseline are not worth the paper
they are printed on. As one of our members remarked, "Thank goodness we're building a park and not a plane
or a rocket!"
Thank you for portunityto provide comments.
Tam Billings
For the Protect Our Parks Steering Committee