Agenda Item No. 13
June 14, 2011
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: Public Works Department
Stephen G. Badum, Public Works Director
949 - 644 - 3311, sbadum @newportbeachca.gov
PREPARED BY: Brad Sommers, Senior Civil Engineer
APPROVED: nl
V y
TITLE: TRAFFIC SIGNAL MODERNIZATION PROJECT - PHASE 5 -
AWARD OF CONTRACT NO. 4698
ABSTRACT:
Phase 5 of the Traffic Signal Modernization Project is the fourth separate construction
project of the multi - phased modernization of the traffic signal system. Staff advertised
and has now received bids for construction of Phase 5 and is requesting City Council
approval to award the contract to Select Electric, Inc.
RECOMMENDATIONS:
1. Approve the project drawings and specifications.
2. Award Contract No. 4698 to Select Electric, Inc. for the total bid price of
$508,372.50, and authorize the Mayor and the City Clerk to execute the
contract.
3. Establish an amount of $51,000.50 (10 %) to cover the cost of unforeseen work.
FUNDING REQUIREMENTS:
The current adopted CIP budget includes sufficient funding for the award of this
contract. The following Transportation /Circulation and Gas Tax funds will be expensed:
1
TRAFFIC SIGNAL MODERNIZATION PROJECT - PHASE 5 - AWARD OF CONTRACT NO. 4698
Page 2
Account Descri tion
Account Number
Amount
TS Modernization - Phase 5
7261- C3002009
$516,000.00
TS Rehabilitation
7181- C3001007
$ 43,373.00
Total
$559,373.00
Proposed uses are as follows:
Vendor
Select Electric, Inc.
Select Electric, Inc.
DISCUSSION:
Purpose
Construction $
Construction Contingency $
Total: $
Amount
508,372.50
51,000.50
559,373.00
At 10 a.m. on May 25, 2011 the City Clerk opened and read the following bids for
this proiect:
BIDDER
Low Select Electric, Inc.
2 Steiny and Company, Inc.
3 C.T. &F., Inc.
4 PTM General Engineering
5 VT Electric, Inc.
if�SL►�717L�Cd�P�
$508,372.50
$561,690.00
$572,072.25
$614,015.00
$672,552.90
*Corrected Bid Amount
The low total bid amount is one percent below the Engineer's Estimate of $513,196.00.
The difference in the Engineer's Estimate and the low total bid is due to a decrease in
the cost of construction over the last few years. The low bidder, Select Electric, Inc.
possesses a California State Contractors License Classification C -10 as required by the
project specifications. A check of the contractor's references indicates they have
satisfactorily completed similar projects for other municipalities.
Construction of Phase 5 (Newport Center) of the Traffic Signal Modernization Project
includes installation of Ethernet communication equipment, 3 CCTV cameras, and new
traffic signal control equipment at 10 existing signalized intersections within the Newport
Center area. The attached exhibit shows the Phase 5 project corridors as well as the
project corridors for the completed phases (1, 2, 3, 4 and 7), and planned phases.
2
TRAFFIC SIGNAL MODERNIZATION PROJECT - PHASE 5 - AWARD OF CONTRACT NO. 4698
Page 3
In addition to modernization of existing traffic signals within the Newport Center area,
new traffic signals will be installed at the Newport Center Drive /Center Drive and
Newport Center Drive /Anacapa Drive intersections.
Staff has also identified the Jamboree Road /San Joaquin Hills Road and Newport
Center Drive /San Miguel intersections to be rehabilitated. Rehabilitation includes
equipment that is outside the scope of the Modernization Project, but is essential to the
operation of the traffic signals.
The Phase 5 field equipment will connect to the City's Ethernet system through existing
equipment installed at the Central Library. Additionally, the system has been designed
to integrate into the existing Traffic Management Center completed through the first
phase of the Modernization Project.
Pursuant to the Contract Specifications, the contractor will have 120 consecutive
working days to complete the work.
ENVIRONMENTAL REVIEW:
Staff recommends the City Council find this project exempt from the California
Environmental Quality Act ( "CEQA ") pursuant to Section 15301 (for repair, maintenance
and minor alteration of existing public facilities with negligible expansion) of the CEQA
Guidelines, California Code of Regulations, Title 14, Chapter 3, because it has no
potential to have a significant effect on the environment.
NOTICING:
The agenda item has been noticed according to the Brown Act (72 hours in advance of
the meeting at which the City Council considers the item).
Submitted by:
Attachment: A. Traffic Signal Modernization Phasing Exhibit
3
UTILITIES
YARD
POLICE
I
''IIIIH •�
CITY OF IRVINE
Y
i y
c /
A
r
CITY OF IRVINE
UNIVERSITY DR
BISON AVE
SAN
o�
r
RD
1 I 1 A
LEGEND
PHASES I - 4 & 7 COMPLETED (79 SIGNALS)
PHASE 5 PLANNED CONSTRUCTION 6/2011 (12 SIGNALS)
PHASE 6 FUTURE (17 SIGNALS)
PHASE 8 FUTURE (I I SIGNALS)
PHASES 1 - 4 & 7 CCTV CAMERAS COMPLETED (22 CAMERAS)
PHASE 5 CCTV CAMERAS (3 CAMERAS)
PHASE 6 FUTURE CCTV CAMERAS (4 CAMERAS)
PHASE 8 FUTURE CCTV CAMERAS (2 CAMERAS)
. COMMUNICATION HUB
PARK RD
O