HomeMy WebLinkAbout17 - Energy Efficient Streetlight NOC (C-4232)Agenda Item No. 17
June 14, 2011
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FRONT: Public Works Department
Stephen G. Badum, Public Works Director
949 - 644 -3311, sbadum @newportbeachca.gov
PREPARED BY: Iris Lee, P.E.
APPROVED:�Ll�
ENERGY EFFICIENT STREETLIGHT IMPROVEMENT PROJECT -
TITLE: COMPLETION AND ACCEPTANCE OF CONTRACT NO. 4232
ABSTRACT:
On May 25, 2010, City Council awarded Contract No. 4232 to Macadee Electrical
Construction, Inc. for an amount of $725,928.00 and a 25 percent contingency allowance.
Work is now complete and staff requests City Council accept and close out of the contract.
RECOMMENDATION:
1. Accept the completed work and authorize the City Clerk to file a Notice of Completion.
2. Authorize the City Clerk to release the Labor and Materials Bond 35 days after the Notice
of Completion has been recorded in accordance with applicable portions of the Civil Code.
3. Release the Faithful Performance Bond one year after Council acceptance.
4. Approve Budget Amendment No BA11 -,
C2202000 to account 7013- C2202002.
FUNDING REQUIREMENTS:
transferring $7,185.00 from account 7013-
The Budget Amendment records and transfers $7,185.00 in project savings for increased
expenditure appropriations. The funds will be posted to the Streetlight Conversion Harbor Hills
account in the Public Works Department, 7013- C2202002. Funds for the construction contract
were expended from the following accounts:
Account Description
EECBG Fund
General Fund
Account Number Amount
7251- C2202003 $ 852,800.00
7013- C2202002 $ 61,784.50
Total: $ 914,584.50
1
DISCUSSION:
Energy Efficient Streetlight Improvement Project - Completion and Acceptance of
Contract No. 4232
June 14, 2011
Page 2
Overall Contract Cost/Time Summary
The completed contract work removed deteriorated streetlight fixtures, installed new energy
efficient light- emitting diode (LED) streetlight fixtures, and upgraded an existing streetlight
circuit per the City's Streetlight Replacement Master Plan. The project upgraded 202
streetlights and allowed for the removal of 16 streetlights in five general locations:
1. Balboa Pier;
2. Newport Pier;
3. McFadden Plaza and adjacent parking lot area;
4. Harbor View Hills Community; and
5. San Joaquin Hills Road between Jamboree Road & MacArthur Boulevard.
These new improvements will yield energy savings and thus on -going system cost. Based a
preliminary pre- and post - project audit of the Harbor View Hills Community alone, we are
seeing over 50 percent energy cost reductions in the billing from Southern California. Given
the low- maintenance nature of LED streetlights (i.e., a minimum 10 -year fixture and bulb life
expectancy), further cost savings from maintenance is expected. Staff is currently working
with Southern California Edison to compile an actual savings comparison at the
abovementioned locations.
The contract has now been completed to the satisfaction of the Public Works Department. A
summary of the contract cost is as follows:
Original bid amount:
$725,928.00
Actual cost of bid items constructed:
728,879.00
Contract
185,705.50
Construction
Final Cost at
Contingency
Actual
Time+
Time
Contract Award
Completion
Target
Contract
Extteen
Under or
Amount
Change
sion
Over
$725,928.00
$914,584.50
25% or less
25.8%
1 151
+27
The completed contract work removed deteriorated streetlight fixtures, installed new energy
efficient light- emitting diode (LED) streetlight fixtures, and upgraded an existing streetlight
circuit per the City's Streetlight Replacement Master Plan. The project upgraded 202
streetlights and allowed for the removal of 16 streetlights in five general locations:
1. Balboa Pier;
2. Newport Pier;
3. McFadden Plaza and adjacent parking lot area;
4. Harbor View Hills Community; and
5. San Joaquin Hills Road between Jamboree Road & MacArthur Boulevard.
These new improvements will yield energy savings and thus on -going system cost. Based a
preliminary pre- and post - project audit of the Harbor View Hills Community alone, we are
seeing over 50 percent energy cost reductions in the billing from Southern California. Given
the low- maintenance nature of LED streetlights (i.e., a minimum 10 -year fixture and bulb life
expectancy), further cost savings from maintenance is expected. Staff is currently working
with Southern California Edison to compile an actual savings comparison at the
abovementioned locations.
The contract has now been completed to the satisfaction of the Public Works Department. A
summary of the contract cost is as follows:
Original bid amount:
$725,928.00
Actual cost of bid items constructed:
728,879.00
Total change orders:
185,705.50
Final construction contract cost:
$914,584.50
At the time of contract award, City Council approved a 25% project contingency to upgrade the
Harbor View Hills Community streetlights from high - pressure sodium (HPS) to energy- efficient
LED streetlights. The cost of this Council approved change was $180,670.50 and accounted
for almost the entire total project change order amount. The remaining change order amount
of $5,035.00 accounted for unforeseen project costs bringing the final construction contract
cost to 25.8% above the original bid amount. There were eight change orders broken down as
shown below:
2
Energy Efficient Streetlight Improvement Project - Completion and Acceptance of
Contract No. 4232
June 14, 2011
Page 3
CO #
Description
Cost
1
Install birdspikes
$3,941.00
2
Harbor View Hills: Change streetlights, from HPS to LED
$173,910.00
3
Harbor View Hills: Install 3" to 4" pole adaptors for LED
streetlights
$1,433.50
4
McFadden Plaza: Change Lumec LED streetlight to ELA LED
streetlight
- $2,071.00
5
Harbor View Hills: Relocate service cabinet
$1,967.00
6
Harbor View Hills: Modify service cabinet for contactors
$945.00
7
Harbor View Hills: Install an additional LED streetlight
$2,415.00
8
Remove and replace three streetlight foundations
$3,165.00
TOTAL
$185,705.50
Given the quantity of the Harbor View Hills Community streetlight fixture change, the
manufacturer needed additional time to fabricate and deliver these specialty LED streetlight
fixtures. A summary of the project schedule is as follows:
Estimated completion date per July 2010 Schedule: June 2010
Project Award for construction: May 25, 2010
Contract Completion Date Plus Approved Extensions: April 1, 2011
Actual Construction Completion Date: May 10, 2011
ENVIRONMENTAL REVIEW:
City Council found this project exempt from the California Environmental Quality Act ( "CEQA ")
pursuant to Section 15302 (2)(c) (replacement of existing facilities) of the CEQA Guidelines,
California Code of Regulations, Title 14, Chapter 3, because it has no potential to have a
significant effect on the environment.
NOTICING:
This agenda item has been noticed according to the Brown Act. In addition, the City Clerk will be
filing a Notice of Completion for the project as a result of this action.
The Notice Inviting Bids was advertised in the City's official publication and in construction
industry publications.
Suhmittari by-
Attachment: Location Map
3
,3
t �
4
SAN JOAQUIN FULLS RD
BALBOA PIER
4
a �
d
/Y
�/ FIARU(TR \�EIV COMMUNITY
S
p E�
r ID
/] r
4 -
MCFADDEN PLAZA AND NEWPORT PIER
PROBECT IOCGT10td RiAP
�+ ENERGY EFFICIENT STREETLIGHT IMPROVEMENT PROJECT, C -4232
COMPLETION AND ACCEPTANCE OF CONTRACT
CITY OF NEWPORT BEACH -PUBLIC WORKS DEPARTMENT
�tIFO��
4
City of Newport Beach
BUDGET AMENDMENT
2010 -11
EFFECT ON BUDGETARY FUND BALANCE:
Increase Revenue Estimates
Increase Expenditure Appropriations AND
qX Transfer Budget Appropriations
SOURCE:
from existing budget appropriations
from additional estimated revenues
from unappropriated fund balance
EXPLANATION:
This budget amendment is requested to provide for the following:
NO. BA- 11 BA -046
AMOUNT: $7,185.00
Increase in Budgetary Fund Balance
Decrease in Budgetary Fund Balance
X No effect on Budgetary Fund Balance
To transfer expenditure appropriations from the Westcliff Street Light Conversion account to the Harbor View Hills
Street Light Conversion to cover increased expenditure appropriations.
ACCOUNTING ENTRY:
BUDGETARY FUND BALANCE
Fund Account
REVENUE ESTIMATES (3601)
Fund /Division Account
EXPENDITURE APPROPRIATIONS (3603)
Description
Description
Signed:
Signed:
Signed:
—)we,
Approval: City
City Council Approval: City Clerk
Services Director
Amount
Debit Credit
$7,185.00
Automatic
$7,185.00
Date
`l41 a-at I
Date
Date
5
Description
Division
Number
7013
Street
Account
Number
C2202000
Street Light Conversion Westcliff
Division
Number
7013
Street
Account
Number
C2202002
Street Light Conversion Harbor Hills
Division
Number
Account
Number
Division
Number
Account
Number
Signed:
Signed:
Signed:
—)we,
Approval: City
City Council Approval: City Clerk
Services Director
Amount
Debit Credit
$7,185.00
Automatic
$7,185.00
Date
`l41 a-at I
Date
Date
5