Loading...
HomeMy WebLinkAbout18 - Harbor View Hills South & Newport Heights Pavement Rehabilitation (C-4609)�EwaoRr CITY OF NEWPORT BEACH °9CIF R City Council Staff Report Agenda Item No. 18 June 14, 2011 TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL FROM: Public Works Department Stephen G. Badum, Public Works Director 949 - 644- 3311,sbadum @newportbeachca.gov PREPARED BY: Alfred Castanon, Associate Civil Engineer APPROVED: L 0", TITLE: HARBOR VIEW HILLS SOUTH & NEWPORT HEIGHTS PAVEMENT REHABILITATION - AWARD OF CONTRACT NO. 4609 ABSTRACT: In accordance with the City's Pavement Management Plan, staff has received construction bids for the Harbor View Hills South & Newport Heights Pavement Rehabilitation project and is requesting City Council's approval to award the work to R.J. Noble Company. RECOMMENDATION: 1. Approve the project drawings and specifications. 2. Award Contract No. 4609 to R.J. Noble Company for the Total Bid Price of $1,247,650, and authorize the Mayor and the City Clerk to execute the contract. 3. Establish an amount of $125,000 (10 %) to cover the cost of unforeseen work not included in the original contract. 4. Approve Budget Amendment No. 11- _ transferring $202,000 from Account No. 7281- C2002024 to Account No. 7281- C2002039. FUNDING REQUIREMENTS: The current adopted budget includes sufficient funding in the following accounts for the award of this contract. The following funds will be expensed: 1 Harbor View Hills South & Newport Heights Pavement Rehabilitation — Award of Contract No. 4609 June 14, 2011 Page 2 Account Description Measure M Turnback Water Enterprise Wastewater Enterprise Proposed uses are as follows: Vendor R.J. Noble Company R.J. Noble Company Harrington Geotechnical Various DISCUSSION: Account Number 7281- C2002039 7511- C2002039 7531- C2002039 Total: Purpose Construction Contract Construction Contingency Geotechnical Printing & Incidentals Total: Amount $ 1,344,547.00 $ 22,500.00 $ 26,500.00 $ 1,393,547.00 Amount $ 1,247,650.00 $ 125,000.00 $ 19,397.00 $ 1,500.00 $ 1,393,547.00 At 10:00 A.M. on May 31, 2011 the City Clerk opened and read the following two bids for this project: BIDDER TOTAL BID AMOUNT Low R.J. Noble Company $1,247,650.00 2nd EBS General Engineering, Inc. $1,263,940.00 3rd All American Asphalt $1,316,174.00 4th Sequel Contractors, Inc. $1,363,080.00 5th Hillcrest Contracting $1,438,055.00 6th Palp, Inc. DBA Excel Paving Company $1,473,031.25 The low total bid amount is 5 percent below the Engineer's Estimate of $1,318,700. The low bidder, R.J. Noble Company possesses a California State Contractors License Classification "A" as required by the project specifications. A check of the contractor's references indicates satisfactory completion of similar projects for the City of Newport Beach and other public agencies. The work necessary to complete this contract consists of distributing construction notices to affected businesses and residents, construction surveying, removing existing pavement, reconstructing sidewalks, curb and gutter, cross gutters, driveway approaches, curb access ramps, pruning trees and installing tree root barriers, adjusting utility and survey facilities, and other incidental items of work necessary to complete the work in place. Pursuant to the Contract Specifications, the Contractor will have 80 consecutive working days to complete the work. 2 Harbor View Hills South & Newport Heights Pavement Rehabilitation — Award of Contract No. 4609 June 14, 2011 Page 3 ENVIRONMENTAL REVIEW: Staff recommends the City Council find this project exempt from the California Environmental Quality Act ( "CEQA ") pursuant to Section 15301 (c) (minor alterations of existing public facilities with negligible expansion of the facilities) of the CEQA Guidelines, California Code of Regulations, Title 14, Chapter 3, because it has no potential to have a significant effect on the environment. NOTICING: The Notice Inviting Bids for this project was advertised in the City's official publication and in construction industry publications. Ten days prior to starting work, a City prepared notice will be distributed by the contractor to residents within the project limits advising them of the pending work. Additionally, a second notice will be distributed by the contractor to residents two days before work will start adjacent to their property. Submitted by: Stepnen ci: baoum Public,Works Director Attachments: Project Location Maps 3 ry '/ M.n� •� v OP r �yf oP �P5 a� CRFF/f ` (P iNSq�/ oR �) 9e 9fq °gyp (a�jOB9P` Q''hJ a v' DR 0 <A (p x OA RD o OR- , ¢ o �tiC �Pi o c �<v Qp an (� ti ' K h� JASMINE J� (PVT) 4.. 1 �O O WHITEWA �� �a h U� Jy'h V� Z �h Q n O,q Fr9,y� ro ) ro l?) SAN JOAQUIN HILLS ROAD - -� CATAMARAN DR - ��m J N OCEAN BIRC BLUE m 153 03 % ;, 7 :; (PVT) VT) rri J ✓� f C T n KEY VIEW o� ToRFFti m � •�'L Giv pS��F �,� 0� G � HARBOR VIEW HILLS SOUTH PREMIERE POINT (PVT) T 9, L� J N sG s x GAS MAA, HARBOR VIEW HILLS SOUTH & I CITY OF NEWPORT BEACH NEWPORT HEIGHTS PAVEMENT REHABILITATION PROJECT PUBLIC WORKS DEPARTMENT O : * u.' LOCATIONS DATE 9/14/10 SCALE N.T.S SHT 1 OF 1 DRAWN AC 1 -4609 N P �q `FA y0 - P Q� '9.pCq 0 ST DR HARBOR VIEW HILLS SOUTH & NEWPORT HEIGHTS PAVEMENT REHABILITATION LOCATION MAP p Sp P S�F�CgC� O C/ NEWPORT HEIGHTS - Z JAMES R�pO J 3 0 � C w 4 O N Q Y PROJECT LOCATIONS 1, a A CITY OF NEWPORT BEACH PUBLIC WORKS DEPARTMENT AC I C -4609 5 City of Newport Beach BUDGET AMENDMENT 2010 -11 EFFECT ON BUDGETARY FUND BALANCE: Increase Revenue Estimates Increase Expenditure Appropriations AND fJ Transfer Budget Appropriations SOURCE: from existing budget appropriations from additional estimated revenues from unappropriated fund balance EXPLANATION: NO. BA- 11 BA -045 AMOUNT: $202,000.00 P XIncrease in Budgetary Fund Balance Decrease in Budgetary Fund Balance No effect on Budgetary Fund Balance This budget amendment is requested to provide for the following: To transfer expenditure appropriations from the Tustin Avenue /Avon Street Rehabilitation account to the Harbor View Hills Pavement Rehabilitation to cover costs related to the awarding of contract number 4609 to R.J. Noble Company. ACCOUNTING ENTRY: BUDGETARY FUND BALANCE Fund Account REVENUE ESTIMATES (3601) Fund/Division Account EXPENDITURE APPROPRIATIONS (3603) Description Description Signed: `n `-,f WL �G Financial Signed: Signed: Administrative Services Director Approval: City Council Approval: City Clerk Amount Debit Credit $202,000.00 Automatic $202,000.00 (x.7.1 Date 4 h/ )1 Date Date 0 Description Division Number 7281 Measure M - Turnback Account Number C2002024 Tustin Avenue /Avon Street Rehabilitation Division Number 7281 Measure M - Turnback Account Number C2002039 Harbor View Hills Pavement Rehabilitation Division Number Account Number Division Number Account Number Signed: `n `-,f WL �G Financial Signed: Signed: Administrative Services Director Approval: City Council Approval: City Clerk Amount Debit Credit $202,000.00 Automatic $202,000.00 (x.7.1 Date 4 h/ )1 Date Date 0