HomeMy WebLinkAbout12 - C-3270 Bonita Canyon Sports ParkCITY OF NEWPORT BEACH
CITY COUNCIL STAFF REPORT
Agenda Item No. 12
July 22, 2003
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: Public Works Department
Michael J. Sinacori, P.E.
949 - 644 -3311
msinacori @city. newport- beach. ca. us
SUBJECT: BONITA CANYON SPORTS PARK— COMPLETION AND ACCEPTANCE
OF CONTRACT NO. 3270
RECOMMENDATIONS:
1. Accept the work.
2. Authorize the City Clerk to file a Notice of Completion.
3. Authorize the City Clerk to release the Labor and Materials Bond 35 days after the
Notice of Completion has been recorded in accordance with applicable portions of
the Civil Code.
4. Release the Faithful Performance Bond 1 year after Council acceptance.
PROJECT BACKGROUND AND HISTORY:
On May 9, 2000, the City Council awarded the $6,276,000 Bonita Canyon Sports Park
Improvements contract to Castello, Inc., of Escondido, California. The park has three
distinct use areas - East Park, Mid Park, and West Park. The contract included the
following basic park components:
(a) Three 200 -foot youth baseball fields
(b) One multi - purpose baseball /soccer field
(c) Mid Park - three mid -youth soccer fields
(d) West Park youth soccer fields
(f) East Park restroom and equipment storage facilities
(g) East Park on the site parking for 240 vehicles
(h) West Park on site parking for 115 vehicles
(i) East Tot Lot
Q) Open spaces with earth berms, pedestrian walking trails, and security
lighting
(k) Picnic areas
In addition to the above described park components, several alternative bid items were
considered in the contract documents and added to the project by other Council
actions. These items were:
1. West Park Open Space (area south of soccer fields) along MacArthur
Boulevard to the Manning Park (approximately 2000 feet)
2. West Park Tot Lot
3. West Park tennis courts
SUBJECT: BONITA CANYON SPORTS PARK— COMPLETION AND ACCEPTANCE OF CONTRACT NO. 3270
July 22, 2003
Page 2
4. West Park basketball courts
5. Mid Park restroom facility
6. Five decorative park signs (completed by General Services Department
Staff)
(Bold items were approved Alternative Bid Items at time of Award)
In November 2001, work on the project stopped due to financial difficulties of the
general contractor, Castello, Inc. (Castello). The park was approximately .88%
complete and the construction was scheduled for completion in February 2002 with five
months of plant establishment and maintenance to follow. The park opening was being
planned for July 2002.
A number of meetings were held in November 2001 as Castello attempted to obtain
financial assistance from the bonding company for the project, The St. Paul Company
(Surety). In December the Surety rejected their request. Because of this, the City
terminated the Contractor's right to work on the project by letter on December 21, 2001,
and also formally requested that the Surety complete the project.
On January 22, 2002 the City Council approved the Takeover Agreement with the
Surety. The Agreement had stipulated the work begin within 30 days of that approval
and be completed within 90 days (which was the remaining contract time for Castello)
and the 5 months of plant establishment would begin.
The Surety hired Erreca's, Inc to be their completion contactor along with many of the
original sub - contractors. As they began work it became painfully apparent that Castello
was far from finished and the 90 days was not enough time to complete the project. It
was also apparent the cost to finish the project would far exceed the original bid
amount.
In addition to the problems at the beginning of the take over, the landscape sub-
contractor began to have financial difficulties and was removed from the project in
November 2002. A new landscape sub - contractor was brought on board and recently
completed the required work.
St. Paul has financed the completion at their cost and has spent approximately
$3,670,000 to date to complete the project (see attached letter). At the time when the
Surety took over the contract, approximately 88% or $5,667,365 had already been paid
to Castello. The total cost to date to complete the park is over $9.3 million dollars.
Since the City's costs are capped at $6.8 million, the Surety is responsible for the
overage which currently totals over $2.5 million. The Surety has estimated that their
costs at final completion may rise to over $3 million.
NOTICE OF COMPLETION AND CURRENT STATUS:
The contract has now been completed to the satisfaction of the Public Works, General
Services, and Recreation and Senior Services Departments with the exception of West
Park's 90 day maintenance. A summary of the contract cost is as follows:
Original Award amount (Including West Park Tot Lot and $6,276,000.00
Mid -Park Restroom):
Total amount of change orders: $559,692.66
Final contract cost: $6,835,692.66
SUBJECT: BONITA CANYON SPORTS PARK — COMPLETION AND ACCEPTANCE OF CONTRACT NO. 3270
July 22. 2003
Page 3
Attached is a summary of the 38 change orders. As indicated above, the Surety has
expended approximately $2.5 million, to date, in additional funds. For that reason,
along with the complications related to this project, they have respectfully requested the
relief of liquidated damages for the contract which are estimated to be $280,000 based
upon 576 days beyond contract completion date at $500 per calendar day. In light of
the amount of funding that the Surety has provided to complete the project, staff agrees
that the liquidated damages should be waived.
Funds for the project were expended from the following accounts:
Description
Bonita Canyon Sports Park (Bonds)
Bonita Canyon Sports Sewer Improvements
Freeway Reservation Park
Sewer Main Improvement Program
West Park Open Space Improvements (CIOSA)
MacArthur Boulevard Landscaping
Park and Field Renovation
Bonita Canyon Sports Park - Tennis &
Basketball Court Improvements
Account No.
Amount
7441- C4120434
$6,167,500.00
7532- C4120434
100,000.00
7021- C4120434
48,000.00
7531- C5600292
34,808.30
7432- C5100657
318,294.66
7015- C5100599
33,607.70
7021- C4120431
13,482.00
7021- C4120616
120,000.00
Total $6,835,692.66
After the project is closed there will be $81,701.34 of funds remaining. These funds
represent the value of $54,892 credit for the West Park 90 day maintenance period and
a portion of the $40,493.88 reimbursement for irrigation water used on the project.
These funds will be used by the General Services Department to complete the 90 day
maintenance in the West Park and other requested improvements necessary to open
the park. The formal opening of East and Mid -Parks is planned for August 24, 2003
and a portion of these funds will be used by the Recreation and Senior Services
Department for this purpose. West Park will be open at the completion of the
maintenance period later in the Fall.
Environmental Review:
On March 14, 2000 City Council approved a Mitigated Negative Declaration for this
project, which is on file with the City Clerk's Office. , -
Prepared by: I Submitted
J. SiKacori, P.E.
I Civil Engineer
Approv I Recommended by:
Mari Knight, Z ecreat n and
Senior Services Director
Attachments: Letter from St. Paul Surety Dated July 15, 2003
Change Order Summary
Badum
s Director
Approval Recommended by:
David E. Niederhaus
General Services Director
StPaul Surety
July 15, 2003
United States Fidelity and Guaranty Company
31919 First Avenue South, Suite 100
Federal Way, WA 98003
Talephone:(253) 945 -1540
Fax:(253) 945 -1559
Mailing Address
P.O. Box 4669
Federal Way,WA 96063 -4669
'RYA FACSIIYIILE (949) 644 -3318 AND FmST CLASS MAIL
Mr. Steve Badum
City of Newport Beach
3300 — Newport Blvd.
Newport Beach, CA 92658 -8915
Re: United States Fidelity and Guaranty Company (USF &G)
Principal: Castello, Inc. (Castello)
Claim No.: 040OKFI654 46H001 (1) (57)
Bond No.: KF1654
Completion Contractor: Erreca's, Inc. (Erreca's)
Obligee: City of Newport Beach (City)
Project: Bonita Canyon Sports Park, Contract No. C -3270
Subject: Summary of Takeover Agreement and Final Settlement
Dear Mr. Badum:
This letter is written to follow discussions with the City and Erreca's. Below, is an itemized
breakdown of the accounting on this project:
Final Contract Balance
$6,835,692.66
Amount Paid to Date
67505,772.39
Subtotal
329,920.27
Retention Being Held
325,544.93
Progress Payment #28
4,375.34
The total amount due on the contract to USF &G is $329,920.27. There are pending CCO's as
follows: additional landscaping and sidewalk in West Park (CCO 36), deleting the 90 day
maintenance period from West Park (CCO 37), and the credit for water bills (CCO 38). There
is a tentative understanding that no liquidated damages will be assessed on this project against
USF &G by the City. If the City counsel rejects the current settlement proposals and proceeds
with liquidated damages, USF &G reserves the right to renegotiate and pursue additional
affirmative claims under the contract.
With acceptance of (CCO 36), the City will be accepting West Park prior to the maintenance
period being completed. All remaining maintenance work will be completed at the cxpen.se of
the City. All warranties will be from the date of acceptance by the engineer per specification.
All in place Castello work that will require warranty will be covered in accordance with the
terms of the contract.
W. Steve $adum
July 15, 2003
Page 2
By way of summary, USF &G has expended $3,671,636.14 for performance of the contract and
payment of subcontractors and suppliers of Castello (USF &G Payment history attached). In
addition, USF &G has expenses of some $17,376.53 for attorney's fees, consultants and
miscellaneous expenses. Currently, USF&G has a pending pay estimate due Errecas's in the
approximate amount of $180,000.00. USF &G also anticipates additional costs and fees related
to performance and fmal payments to Erreca's, final settlements and/or final retention payments
to subcontractors and suppliers, additional legal fees and costs in pursuing Castello, individual
indemnitors and Flintridge Landscaping, Inc. for potential recovery. It is anticipated that
USF &G's net loss after completion of our bond obligations will exceed $3,000,000.00.
We wish to thank you for your attention to this matter, and look forward to your prompt
response to final settlement of this contract.
Sincerely yours,
United States Fidelity and Guaranty Company
Peter At
stall
Sr. Bond Claims Specialist
Phone: (253) 945 -1542
PAF /bd
cc: Mr. Mike Sinacori, City of Newport Beach
Ms. Jo Elsmore, Erreca's, Inc.
G:\ SUREfYTjellstad \Castello,laclKrl654 \I -City of Newport Re=h\Radum- 071503.doc
Bonita Canyon Sports Park Change Order Summary
Change Order No. 1 — Mid Park Wet Soils
Placing Geotextile Fabric 8XT per Field Meeting on 7/10/2000 $16,243.00
Fill Test Holes $1,850.00
Extra Excavation @ Canyon Drains @ East Park $30,085.00
Grading "Credit" at Mid Park ($14,079.00)
Subtotal CC01 $34,099.00
Total $32,000.00
Change Order No. 2. - Request for Time Extension from Soils Issue (30 days) $0.00
Change Order No. 3 - Modifications to Sewer Mains for Pacific Bell
Pothole at Pacific Bell
$824.00
Add for Realignment of Sewer line on Ford Road
$7,940.35
Additional Depth of Sewer
$5,834.40
Delete Sewer Cleanout/PVC
($3,300.00)
Total
$11,298.75
Change Order No. 4 - Modification of Storm Drain Pipe Material
Substitute SDR -35 for specified Schedule 40 PVC ($2,133.00)
Substitute HDPE for RCP ($3,481.00)
Labor Credit ($7,350.00)
HDPE Special fittings $2,968.00
Total ($9,996.00)
Change Order No. 5 - Modification to Sidewalk Base Material
Credit for deleting Class II base from under all sidewalks ($32,572.00)
Credit for not cutting subgrade 4" to receive base ($3,434.00)
Credit for reducing walks to 4" thickness ($13,096.00)
Installation of wire mesh to 10' walks $5,597.55
Total ($43,504.45)
Change Order No. 6 - Structural Changes at Dissipater Structure $1,700.16
Change Order No. 7 - Interfering Utilities (ACP Water Main)
Abandon in place 12 inch transite water main $5,000.00
Markup (10 %) $500.00
Total $5,500.00
Change Order No. 8 - Reduction to Street Patching Efforts ($3,856.00)
Changer Order No. 9 — Additional Cost for Sewer Main (partial paid by Pacific Bell)
Slurry backfill for sewer 8/4/2000
$3,086.60
Hard Rock Excavation 8/7 & 8/8
$4,767.40
Remove Excess Rock 8/9/2000
$2,816.00
Remove Excess Rock 8/10 & 8/11
$5,637.55
Slurry backfill for sewer 8/7/2000
$4,202.00
Sewer Pothole /Delay on Ford Road
$3,000.00
Total
$23,509.55
Page 1
Bonita Canyon Sports Park Change Order Summary
Change Order No. 10 — City Requested change to berms along MacArthur Blvd.
Change Order No. 11 —Value Engineering Changes to Irrigation System
Change Order No. 12 —Changes for Electrical Connections
Penetrate Edison Vaults
Credit for DG Pads vs. Concrete Pads
Total
Change Order No. 13 - Electricairrelephone Services to Site
Install telephone and Edison services to three restrooms
Credit for dual trenching of edison and street light conduits
Relocate 8" subdrain around 66" outlet structure
Total
Change Order No. 14 — Powder Coat Cable Fencing and Stabilize Outlet Structure
Stabilize the outlet structure
Powder coat cable fencing in medians
Total
Change Order No. 15 — Modification to Irrigation Control Valves
Epoxy coat master irrigation valves
Re- install T -lock plastic lining into IRWD manhole
Total
$6,108.00
($101,870.00)
$3,300.00
($408.00)
$2,892.00
$59,072.85
($100.00)
$1,486.10
$60,458.95
$5,716.30
$1,595.00
$7,311.30
$6,119.30
$1,050.00
$7,169.30
Change Order No. 16— Subsitution of Bleachers and storm drain junction structure
installation
Substitute Dant - Clayton Co. bleachers for Tomark Sports bleachers $10,208.00
Add JS #1 junction structure and manhole on 66" storm drain $4,162.40
Total $14,370.40
Change Order No. 17 - Add back into contract Tennis and Basketball Courts
Add Bid Alternate 3 "Tennis Courts'
Add Bid Alternate 4 "West Park Basketball Court"
Total
Change Order No. 18 — Provide and Install conduit for electrical and irrigation
Provide and install irrigation sleeving
Install electrical conduit to provide power for West Park restroom
Provide and install roof framing valley hangers and modified beams for
restrooms
Total
Change Order No. 19 — Modifications to utilities due to conflicts in plans
Modify ballfield pole footing
Install modified domed gratings on storm drain collector inlets
Total
$85,000.00
$28,000.00
$113,000.00
$2,750.00
$5,372.00
$2,595.24
$10,717.24
$1,194.16
$8,570.88
$9,765.04
Page 2
Bonita Canyon Sports Park Change Order Summary
Change Order No. 20 — Modifications to irrigation hardware due to conflicts in plans
Increase POC box size $9,912.00
Credit for 4' chain like fencing modifications ($3,450.00)
Total $6,462.00
Change Order No. 21 — Modifications to restroom roof, drinking fountain and slope
work
Install modified copper restroom roof crickets $1,900.00
Repair slope washouts in West Park $3,291.00
Provide and install ceramic tile drinking fountain lid at restrooms $1,951.00
Total $7,142.00
Change Order No. 22 — Modification to planting palate due to tree unavailability
Relocate and plant 36" Agonis
$8,000.00
Credit for supplying 15 gallon box trees
($3,045.00)
Loading and unloading of box Agonis trees
$1,822.00
Restocking fee from Valley Crest Landscaping
$2,900.00
Deliver and place 36" box trees
$1,250.00
Credit for supplying 24" box trees
($7,000.00)
Total
$3,927.00
Change Order No. 23 — Addition of West Park Landscaping and Irrigation
Add West Park Alternate 1 into the contract
$332,668.70
Add additional office and field overhead
$3,935.00
Total
$336,603.70
Change Order No. 24— Parking lot weedkill prep, slope repairs and misc. painting
Provide and place week kill at parking lots
$2,150.00
Repair slope washouts in West Park open space
$3,207.00
Paint baseball field poles glossy black
$2,000.00
Total
$7,357.00
Change Order No. 25 — Modifications to planting and irrigation materials
Extra application of fertilizer
$1,320.00
Install oversize tree staking
$2,561.90
Asphalt material price increase 50% allocation agreement
$3,575.00
Modifications to soil amendments per agreed upon pricing
($1,637.63)
Total
$5,819.27
Change Order No. 26 — Modifications to tree planting, slopes and seed materials
Provide and install additional soil for added berms
$11,250.00
Increase the seed rate of Ballfield 1A mix
$3,477.86
Provide additional screening trees in south West Park
$1,375.00
Provide additional screening trees in mid West Park
$2,310.00
Provide and install jute netting
$4,770.00
Total
$23,182.86
Change Order No. 27 — Changes to Basketball and Tennis Courts $22,016.38
Change Order No. 28 — Changes to restrooms and backstops $6,961.14
Page 3
Bonita Canyon Sports Park Change Order Summary
Change Order No. 29 — Provide bathroom mirrors, upgrade trees, and mortar in
pavers $15,323.77
Change Order No. 30 — Provide in- process modifications to planned facilities
Provide and install "skate stopper" bolting on handrails throughout the park $5,235.48
Prime and paint tree grates in the play areas $8,778.92
Provide and install infield irrigation modifications $6,195.94
Total $20,210.34
Change Order No. 31 — Provide multiple items
Add Soil Amendments
$4,195.14
Modify Restroom Partitions to match walls
$1,680.00
Modify restroom doors
$1,666.50
Relocate balifield sprinklers to 60' radius
$2,503.08
Raise water access manhole to grade
$5,661.05
Add catch bollards to bar swing gates
$2,022.02
Raise 4' chain link fencing at midpark to match sidewalk
$2,777.50
Modify irrigation heads at midpark
$3,365.17
Modify hyroseed mix design
($1,862.40)
Credit for rototilling deletion
($24,089.00)
Provide and install anti - graffiti paint on pilasters
$899.91
Add misc. plants at Eastpark
$149.59
Stain drinking fountains to match pavers
$2,649.74
Extra work to chip back block wall
$194.43
Add mid rails to tennis court fencing
$1,706.50
Add catch basin at West Park
$944.35
Total
$4,463.58
Change Order No. 32 — Provide additional SWPP work along MacArthur Boulevard Vold
Change Order No. 33— Provide drainage inlets and mulch binder
Add two curb drains
$11,037.79
Add three drains adjacent to the West Park restroom
$3,316.33
Add binder to mulch topdressing
$8,545.61
Total
$22,899.73
Change Order No. 34 — Provide additional catch basin and inlet piping at Mid Park
restroom
Install additional storm drain inlet and catch basin at Mid Park restroom 2451.71
Provide watering support services by hand for installed planting 2664.33
Total $5,116.04
Change Order No. 35 — Provide wire mesh grill backing in park restrooms $5,206.06
Change Order No. 36 — Provide misc. changes to the West Park landscape and
drainage
Landscaping misc. clean up items $6,883.00
Storm drain inlet adjustments and curb drain installations $3,925.00
Remove and replace sidewalk for curb drains in West Park $3,465.20
Provide 2 extra stock removable bollards $400.00
Markup $1,140.23
Total $15,813.43
Page 4
Bonita Canyon Sports Park Change Order Summary
Change Order No. 37 — Credit for delayed 90 day West Park maintenance ($54,892.00)
Change Order No. 38 — Credit for water billing during construction and maintenance ($40,493.88)
Total Change Orders
$559,692.66
Page 6