Loading...
HomeMy WebLinkAbout09 - 2011-2012 Sidewalk, Curb & Gutter Replacement� CITY OF NEWPORT BEACH . / City Council S i a ff Report Agenda Item August 14, 2012 TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL FRONT: Public Works Department Stephen G. Badum, Public Works Director 949 - 644 -3311, sbadum @newportbeachca.gov PREPARED BY: Alfred Castanon, Associate Civil Engineer APPROVED:C_ TITLE: 2011 -2012 Sidewalk, Curb & Gutter Replacement - Notice of Completion and Acceptance of Contract No. 4850 ABSTRACT: On November 8, 2011, City Council awarded Contract No. 4850 (2011 -2012 Sidewalk, Curb & Gutter Replacement Project) to Grigolla & Sons Construction Company for a total contract cost of $433,950.00 plus a 12% allowance for contingencies. The required work is now complete and staff requests City Council acceptance and close out of the contract. RECOMMENDATIONS: 1. Accept the completed work and authorize the City Clerk to file a Notice of Completion. 2. Authorize the City Clerk to release the Labor and Materials Bond 65 days after the Notice of Completion has been recorded in accordance with the applicable portions of the Civil Code. 3. Release the Faithful Performance Bond one year after Council acceptance. FUNDING REQUIREMENTS: Funds for the construction contract were expended from the following accounts: Account Description Account Number Amount General Fund 7013- C2001009 $ 451,726.50 Total Construction Cost: $ 451,726.50 2011 -2012 Sidewalk, Curb & Gutter Replacement - Notice of Completion and Acceptance of Contract No. 4850 August 14, 2012 Page 2 DISCUSSION: Overall Contract Cost/Time Summary Contract Award Final Cost at Benchmark Actual Contract Time Amount Completion Target Contract Time Under ( -) (days) or Over ( +) $433,950.00 $451,726.50 12% or less 4.1% 85 18 The work necessary to complete this contract consisted of reconstructing sidewalks, curb and gutters, driveway approaches, curb access ramps, tree removal, pruning trees, installing tree root barriers, and replanting new trees in the Newport Center, Harbor View Hills, Corona Del Mar, Corona Highlands, Cameo Highlands and Newport Coast communities. The contract has now been completed to the satisfaction of the Public Works Department. A summary of the contract cost is as follows: Original bid amount: Actual cost of bid items constructed: Contract change orders: Final contract cost: $ 433,950.00 $411,548.50 $ 40,178.00 $ 451,726.50 The final contract cost was 4.1% above the original contract amount. There were two change orders totaling $40,178.00. The change orders were for the Marine Avenue ADA Improvements on Balboa Island and additional concrete replacement work for Dorchester Drive in the Cameo Highlands community. A summary of the project schedule is as follows: Estimated Completion Date per July 2011 Baseline Schedule: February 8, 2012 Project Awarded for Construction: November 8, 2011 Completion Date from Award with Approved Extensions: June 14, 2012 Actual Substantial Construction Completion Date: May 18, 2012 ENVIRONMENTAL REVIEW: City Council found this project exempt from the California Environmental Quality Act ( "CEQX) pursuant to Section 15301(c). This exemption covers the minor alteration of existing public facilities with negligible expansion of the facilities in areas that are not environmentally sensitive. 2011 -2012 Sidewalk, Curb & Gutter Replacement - Notice of Completion and Acceptance of Contract No. 4850 August 14, 2012 Page 3 NOTICING: This agenda item has been noticed according to the Brown Act. In addition, the City Clerk will be filing a Notice of Completion for the project as a result of this action. The Notice Inviting Bids was advertised in the City's official publication and in construction industry publications. Submitted by: Location Maps I �� r� � �� ��� i(�' �J'J �� iii II� ,l �, �4• , p �P �T) U ti Q tP S w x• C F' U P9 O a p e 000x: C,q TF-P n to FTf`,pR NSF Cy/vgr QQ.. IS" D Q AEG aP CLEMENT )WSA14 a z �4• , p �P �T) U ti Q tP S w x• C F' U P9 O a p e 000x: C,q TF-P n to FTf`,pR NSF Cy/vgr QQ.. IS" ♦QW `Bpi � J °v In av qO 'm s Jti o c92 0. 1O 2 FP c QP q /. Lf J FASfl-Jl0N ISLAND v r a o � z R44 � oN DRIVE ENTRY WQ PtiP �Q o wr (Pvr) O�P�o NEWPORT CENTER FY 2011 -2012 SIDEWALK, CURB & GUTTER REPLACEMENT PROJECT LOCATION MAP LN c P.. Oe cOCy OP�CnO Q0 y ti c .O -01 P C.. 4r �Oc z <„ m G � 9 P �T > 2 PVT) 090 r?� o P F r A p O \NS T� N � n v A !a C 2� o0� <R CITY OF NEWPORT BEACH PUBLIC WORKS DEPARTMENT C -4850 I SHEET 1 z n 9 ➢ A Fq P1 Rq; -(ON RI ENTRY P O wQ P Oc k'Y (PVT) a d0 a e 00 �P 9ST hiJ "➢ me Jp ,i 9fTx INC P O F FR JP P 0J ST � yA� r a� < e r �O J� .E9N 4 T f�pR Sfvy y P.F Pf" NJ FP gR� OC. �q,f4s Li^6 9:q. ryLf � P0101c 54v 4..PA;ORP (,�I,, HP' f-ST y C Q tR 0 O "CA TS rR FfT S ARL 4TF r JER o t SAN JOAOUIN CATAIAARaW UP MILLS ROAD r - d"', GO' Y'. CO Tye l Dal 96Ti.'o'hy_� yr. R % T p ^➢ ne (�jcaT a INLET OR BLUE `P V7) P m vI N n 9Cn Un ✓n Q e n_ 9 A w KNEEY k E p? 4, INE ' � W �JAS!fF� s Pn �L�- kMREVJAt�R yP ry, ;ly L '> 11 e ER d' f B A ^ b 9,y00 !I, 'u • T F FP oR v Npf �4C ^J "E" 'A'OU.E PREMIERE POINT \/1 �O (, 'C iFP)I 0416E (PVI) / Q (A MGR ERS nA ,. 'Fr `_ p< '2' a{J, c 90 ROC OR v41A, S( R V 6 hu O ( °4g Pl R 4 C4[N0k O roP Oa�ST �O Nq�awA,lY oRT qry °o (}� SAO OQO :AfMOV TOry T RD z PEAL. N D,. 414 PARRnR \ /IPkAl R rnRnI\lA f1Fl KAAR FY 2011 -2012 SIDEWALK, CURB & GUTTER REPLACEMENT PROJECT LOCATION MAP CITY OF NEWPORT BEACH PUBLIC WORKS DEPARTMENT C -4850 I SHEET 2 a o r� � v � t `✓rc .av< k'� YS45 `L ry G Y 4 a l � v � t `✓rc .av< k'� YS45 ±n 'N n;r }3 ti ct 5 0 �� 2 .vG 9'O � rte:° "•PS ....,° d W� U•'S� S k rSiS { a y1' a .�„ � r �, � •• - v Y > # d d Alt it n+ b f p • S NEWPORT COAST FY 2011 -2012 SIDEWALK, CURB & GUTTER REPLACEMENT PROJECT LOCATION MAP ,; ,E• e° w Q U N O H h O Z CITY OF NEWPORT BEACH PUBLIC WORKS DEPARTMENT C -4850 I SHEET 3