HomeMy WebLinkAbout06 - FY12-13 Sidewalk, Curb Gutter Award C-5204s Agenda Item No. 6 November 13, 2012 TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL FROM: Public Works Department David A. Webb, Public Works Director /City Engineer 949 - 644 - 3311, dawebb@riewportbeachoa.gov PREPARED BY: Alfred Castanon, Associate Civil Engineer APPROVED :: n D. /►q TITLE: ! 2012 -2013 Sidewalk, Curb & Gutter Replacement- -Award of Contract No. 5204 ABSTRACT: Staff has received construction bids Replacement project and is requesting Grigolla & Sons Construction Company, RECOMMENDATIONS: for the 2012 -2013 Sidewalk, Curb & Gutter City Council's approval to award the work to Inc. 1. Approve the project drawings and specifications. 2. Award Contract No. 5204 to Grigolla & Sons Construction Company, Inc., for the Total Bid Price of $491,400, and authorize the Mayor and the City Clerk to execute the contract. 3. Establish an amount of $49,000 (10 %) to cover the cost of unforeseen work not included in the original contract. 4. Approve Budget Amendment No. 136A 019 transferring $206,600.00 in project savings from the Fashion Island Area Streets Overlay - Account No. 7281- C2002046 (Measure M Turnback) to Account No. 7281- C2001009 (Sidewalk Curb and Gutter Replacement) This amendment also recognizes $4,800 in revenues to (Account 9010 -5901) for private contributions from Lido Isle Community Association and appropriates $4,800 to 7013- C2001009. 105 2012 -2013 Sidewalk, Curb & Gutter Replacement — Award of Contract No. 5204 November 13, 2012 Page 2 FUNDING REQUIREMENTS: The FY 2012 -13 Capital Improvement Program budget included $400,000 in general fund monies and $75,880 in CDBG monies for the 2012 -2013 sidewalk project. On September 11, 2012, City Council approved the award of Ocean Boulevard and China Cove Ramp Slope Maintenance Project (C -3912) which included a budget amendment transferring $175,000 in general funds from the Sidewalk, Curb and Gutter Replacement Program to slope project. To restore funding for the sidewalk project, staff is recommending use of surplus Measure M funds from the Fashion Island Area Streets Overlay and Slurry Project which was accepted as completed on September 11, 2012. Also, this year's project includes 8,000 square feet of colored and stamped concrete sidewalk replacement on Lido Isle. Per Council Policy L -1, the Lido Isle Community Association will contribute $4,800 for coloring and stamping of these new walkways, which represents the difference in cost from standard concrete. Upon approval of the proposed Budget Amendment, there will be sufficient funding in the following accounts for the award of this contract. Account Description Account Number Amount General Fund 7013- C2001009 $ 263,020.00 Community Development Block Grant 7161- C2001009 $ 75,880.00 Measure M Turnback 7281- C2001009 $ 206,600.00 $ 545,500.00 Proposed uses are as follows: Vendor Purpose Amount Grigolla & Sons Construction Co., Inc. Construction Contract $ 491,400.00 Grigolla & Sons Construction Co., Inc. Construction Contingency $ 49,000.00 GMU Geotechnical, Inc. Geotechnical Services $ 4,720.00 Various Printing & Incidentals $ 380.00 Total: $ 545,500.00 DISCUSSION: At 10:00 a.m. on October 23, 2012, the City Clerk opened and read the following bids for this project: BIDDER 019 TOTAL BID AMOUNT Low Grigolla & Sons Construction Company, Inc. $491,400.00 2 Golden State Constructors, Inc. $552,390.00 3 CJ Concrete Construction, Inc. $561,350.00 4 Unique Performance Construction, Inc. $594,200.00 5 Nobest, Inc. $710,000.00 6 Kalban, Inc. $799,000.00 7 S. Parker Engineering, Inc. $874,000.00 2 of 2012 -2013 Sidewalk, Curb & Gutter Replacement — Award of Contract No. 5204 November 13, 2012 Page 3 The low total bid amount is 18 percent below the Engineer's Estimate of $600,000. The current competitive construction market most likely contributed to the disparity between the received low bid and staff's cost estimate. The low bidder, Grigolla & Sons Construction Company, Inc., possesses a California State Contractors License Classification "A" as required by the project specifications. A check of the contractor's references indicates satisfactory completion of similar projects for the City of Newport Beach and other public agencies. The work necessary to complete this contract consists of existing sidewalk, curb and gutter replacement, curb access ramps, driveways, and pruning tree roots, installing tree root barriers, removal and replacement of trees per City standards within the Balboa Peninsula, West Newport, Newport Shores and Lido Isle communities. Pursuant to the Contract Specifications, the Contractor will have 85 consecutive working days to complete the work. ENVIRONMENTAL REVIEW: Staff recommends the City Council find this project exempt from the California Environmental Quality Act ( "CEQA ") pursuant to Section 15302 (replacement of existing facilities involving negligible expansion of capacity) of the CEQA Guidelines, California Code of Regulations, Title 14, Chapter 3, because it has no potential to have a significant effect on the environment. NOTICING: The agenda item has been noticed according to the Brown Act (72 hours in advance of the meeting at which the City Council considers the item). The Notice Inviting Bids was advertised in the City's official pub Ic tion and in construction industry publications. Submitted David A. Webb Public Works Director /City Engineer Attachments: A. Location Map B. Budget Amendment 019 3 of !I ly UR IsTH PR,OQUC11014 _PIACE tl oqF °Q rU, E STREET y dl (A" �R ^CoypµIVATE) r I 15TH STREET lt£ST abY COURTLL �A GooSEIt �y IG I IC�Rt I IAEUtCAI (9 SUMHERIMB :' � l �; bf tio44, _ /H.� rt.R Gl°URT (. f.. "( °, HA YA)iI �{.y yaGgo <Sr J OOYP$SfY ct •01✓ti�IAP BT >�f lA'&9 llPVi ('° t{>QY ,`y �` ST •, �/: SLOE `PVT) ! •F�H)� AC916,f 9 Ups N �C Or '•`P �G� y~ t� ) S,f CO lsi - v==im COLRT, ST1 Ct/ §r �Q� ,4L '/f h � < 44 Y ' R^ (P °Rl CtrT ) f`i'b `•t� \t \u., �j °S �? 4. tit y 9 yN y~ l\� .�'R14ER q�. - NICHI /AY . / HOAit V E( AAA w s5 <�' $ `. � ��Fm °. •.��T:.L � \. � O by <y 5 < •(^���o 5t. ry0 ryE 1 019 NEWPORT SHORES, BALBOA PENIN FY 2012 -2013 SIDEWALK, CURB & GUTTER REPLACEMENT PROJECT LOCATION MAP ATTACHMENT & WEST NEWPORT CITY OF NEWPORT BEACH PUBLIC WORKS DEPARTMENT C -5204 I SHEET I 4 of OR, .{S... p� P G O 1 I I Ij.S SW41 A�.AVpN CLIF OR KS) (PVL) `1qPl (Pv;) C0491 y4 st•; Cc 1�iol ^DAP I '?A. e " /14.�N11 lr lir n � h N N 019 �/1 I N 1 tl T N W p T WEST NEWPORT. BALBOA PENINSULA & LIDO ISLE FY 20122013 SIDEWALK, CURB & GUTTER REPLACEMENT PROJECT LOCATION MAP ATTACHMENT CITY OF NEWPORT BEACH PUBLIC WORKS DEPARTMENT C -5204 I SHEET 2 50f5 J' Jsn:• S�FfT . H 9�Cry :I Sl AMP SS Q Ta �kl i .11 ORIV[ J HV(i �/1 I N 1 tl T N W p T WEST NEWPORT. BALBOA PENINSULA & LIDO ISLE FY 20122013 SIDEWALK, CURB & GUTTER REPLACEMENT PROJECT LOCATION MAP ATTACHMENT CITY OF NEWPORT BEACH PUBLIC WORKS DEPARTMENT C -5204 I SHEET 2 50f5