HomeMy WebLinkAbout06 - Rhine Channel Sediment Cleanup ProjectMOM=
F 1 \
Agenda Item No. 6
January 16—,2012
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: Public Works Department
Stephen G. Badum, Public Works Director
949 - 644 -3311, sbadum @newportbeachca.gov
PREPARED BY: Chris Miller, Harbor Resources Manager
APPROVED: k
TITLE: Rhine Channel Se iment Cleanup Project – Completion and
Acceptance of Contract No. 4555; and Consideration of Sixth
Amendment to Professional Services Agreement with Anchor
QEA, L.P. for Additional Construction Management Tasks and
Necessary Post - Dredge Sediment Sampling and Analysis
ABSTRACT:
On May 10, 2011, City Council awarded Contract No. 4555 to Dutra Dredging Company
( "Dutra ") for a total contract cost of $3,450,405 plus a 15% allowance for contingencies.
The required work is now complete and staff requests City Council accept and close out
of the contract. In addition, Amendment No. 6 to the Professional Services Agreement
( "PSA ") with Anchor QEA, LP ( "Anchor QEA") is requested for unforeseen project
management costs as well as for a new scope of services for required post- dredge
confirmation sediment sampling.
RECOMMENDATIONS:
1. Accept the completed work and authorize the City Clerk to file a Notice of
Completion; and
2. Authorize the City Clerk to release the Labor and Materials bond 35 days after
the Notice of Completion has been recorded in acceptance with applicable
portions of the Code; and
3. Release the Faithful Performance Bond one year after Council acceptance; and
Rhine Channel Sediment Cleanup Project — Completion and Acceptance of Contract
No. 4555; and Consideration of Sixth Amendment to Professional Services Agreement
with Anchor QEA, L.P. for Additional Construction Management Tasks and Necessary
Post - Dredge S
January 10, 2012
Page 2
4. Approve the Sixth Amendment to the Professional Services Agreement with
Anchor QEA, LP for additional unforeseen construction management costs, as
well as for a new scope of services for required post- dredge confirmation
sediment sampling.
FUNDING REQUIREMENTS — DUTRA DREDGING:
Funds for the construction contract were expended from the following accounts:
Account Description
Rhine Channel Dredging
Rhine Channel Private Funding
DISCUSSION — DUTRA DREDGING:
Account Number
7231- C4402004
7231- C4402005
Overall Contract Cost / Time Summary
Amount
$ 3,218,549.90
$ 56.675.85
$ 3,275,225.75
Construction
Final Cost at
Contingency
Actual
Contract
Time
Contract Award
Completion
Target
I
Contract
Time
(Under) or
Amount
Change
(days)
Over
$3,450,405.00
$3,275,225.75
1 15% or less
8.0%
101
52
The work necessary for completion of this contract consisted of dredging contaminated
sediment from the Rhine Channel and portions of the adjacent Newport Channel,
replacing piles that support the private docks that were affected by the dredging,
repairing those private docks where new piles were replaced, and performing additional
dredging for a private property owner at their expense.
The contract has now been completed to the satisfaction of the Public Works
Department, Harbor Resources Division. A summary of the contract cost is as follows:
Original bid amount:
Actual cost of bid items constructed:
Total change orders
Final construction contract cost:
$3,450,405.00
$3,198,109.48
$ 77.116.27
$3,275,225.75
Rhine Channel Sediment Cleanup Project — Completion and Acceptance of Contract
No. 4555; and Consideration of Sixth Amendment to Professional Services Agreement
with Anchor QEA, L.P. for Additional Construction Management Tasks and Necessary
Post - Dredge S
January 10, 2012
Page 3
There were six change orders associated with this contract and are detailed below:
CO #
Description
Cost
1
Deletion of Sea Spray Boat Yard bid quantity reduced b
$ - 42,000.00
2
Deletion of ETCO property (bid quantity reduced b
$ - 32,205.00
3
Steel frame pile guides 16" & 18"
$ 11,000.32
4
Double height steel frame pile guides 16" & 18"
$ 6,461.20
5
Additional pile replacements at the American Legion
$ 62,380.00
6
American Legion marina relocation and dredging
$ 71,479.75
TOTAL
$ 77,116.27
The final construction cost was 8.0% below the original bid amount. As denoted in
addition the above contract change orders, the project realized large savings due to the
deletion of the Sea Spray Boat Yard and the ETCO property from the project.
Additional bid quantity savings resulted from the contractor not fully dredging the "1'
paid over - dredge" amount allowed in the contract.
A summary of the project schedule is as follows:
Estimated completion date per July 2011 schedule: November 4, 2011
Project awarded for construction: May 10, 2011
Contract Completion Date plus Approved Extensions December 1, 2011
Actual Construction Completion Date: November 9, 2011
DISCUSSION — ANCHOR QEA
Anchor QEA is currently assisting the City with construction management services for
the Rhine Channel Dredging Project ( "Project "). During the course of the Project,
several unforeseen tasks that were outside of the contract scope were required to be
immediately addressed or implemented by Anchor QEA staff. Authorization to proceed
with these unforeseen tasks was granted by the City at the time of occurrence to ensure
that project delays did not result. A brief summary of these changes is described below,
with a detailed summary provided in the Appendix. (The Task Numbers correspond to
the respective Tasks in Anchor QEA's original proposal.)
Task 1: Port of Long Beach Coordination ( "POLB ") $737
Although Anchor QEA was on budget for most of the project, a concerted effort
with POLB coordination was needed at the end of the Project to present and
discuss final placement of material within the Middle Harbor Slip 1 fill site.
Task 2: Contractor Selection and Pre - Dredge Deliverables $55,404
31
Rhine Channel Sediment Cleanup Project — Completion and Acceptance of Contract
No. 4555; and Consideration of Sixth Amendment to Professional Services Agreement
with Anchor QEA, L.P. for Additional Construction Management Tasks and Necessary
Post - Dredge S
January 10, 2012
Page 4
This task required significant effort above and beyond initial expectations and
budget projections to work with the contractor on finalizing their pre- dredge
deliverables, specifically regarding planning for the floating docks and guide
piles. In addition, a significant amount of time was needed to satisfy the
unforeseen requests of the Regional Water Quality Control Board ( "RWQCB ") by
negotiating and generating additional detailed water quality monitoring plans.
Task 3: Rhine Channel Tenant Coordination $14,440
This task required coordinating efforts with the POLB on delivery schedules,
numerous meetings with various Rhine Channel property owners, and
considerable effort in ensuring that piles and docks met the approval of the
various property owners upon project completion.
Task 5: Rhine Channel Construction Management ($66,601)
Although in aggregate this task ended up under budget, there were two notable
out of scope items: two Change Orders to reduce the dredge footprint, and five
Change Orders for additional dredging. On the positive side, construction
management was under budget through efficient time management as well as
the Project finishing 52 days ahead of schedule.
Task 6: Water Quality and Air Monitoring $240,306
Implementation of the expanded water quality monitoring program was the single
largest out of scope item required for the Project. An expanded program was
required by the RWQCB which included daily monitoring, special studies, more
frequent data reports to the State, and additional chemical analysis. Anchor QEA
was, however, able to mitigate some of these changes by utilizing City labor
whenever possible to supplement the Anchor QEA team, resulting in a cost
savings of almost $5,000 to the Project.
Task 7: Construction Management at Other City Properties $0
There were no additional out of scope costs associated with the American Legion
dredging portion of the Project.
Total Construction Management Contract - Out of Scope Items 24 266
In addition the above cost identified for items that were out of scope for Anchor's current
Construction Management effort, staff is requesting Anchor QEA to perform post- dredge
confirmation sediment and sampling analysis which is required by the RWQCB to verify
successful removal of chemically impacted sediments, and to determine the final
surface sediment chemical concentrations from a 303(d) listing improvement standpoint.
Rhine Channel Sediment Cleanup Project — Completion and Acceptance of Contract
No. 4555; and Consideration of Sixth Amendment to Professional Services Agreement
with Anchor QEA, L.P. for Additional Construction Management Tasks and Necessary
Post - Dredge S
January 10, 2012
Page 5
This task was not included in the original scope of work because it was not possible at
the time to predict the magnitude of the study that might be required to comply with the
RWQCB permit. Staff now understands the work necessary to comply with the RWQCB
post- dredging requirements.
A total of five tasks for the sampling program are briefly summarized below with a full
explanation in the Appendix.
Task 1: Preparation of a Sampling and Analysis Plan $12,210
This task involves preparing a plan to be submitted and approved by the
RWQCB.
Task 2: Meeting with Regulatory Agencies
Task 3: Sediment Sampling $15,010
This task involves sediment sampling at approximately 15 stations using a
piston core deployed from a vessel.
Task 4: Chemical Analysis $22,670
This task analyzes the sediment samples by Calscience Environmental
Laboratories with Anchor QEA performing the data review, validation, and
verification to ensure that data quality objectives have been met.
Task 5: Reporting $18,420
A final report will be prepared by Anchor QEA documenting all activities
associated with collecting, processing and analyzing sediment samples.
Chemistry will be compared to numeric targets listed in the San Diego
Creek/Newport Bay Toxic TMDL. The final concentrations of chemical
contaminants in the surface layer of the Rhine will be presented using GIS with
a project map of the actual sampling locations included.
Task 6: Contingency $31,250
Unforeseen Costs for Final Testing Requirement from the RWQCB and
additional cores or samples.
Total Post - Dredge Confirmation Sediment Testing Scope of Work: M AD
Rhine Channel Sediment Cleanup Project — Completion and Acceptance of Contract
No. 4555; and Consideration of Sixth Amendment to Professional Services Agreement
with Anchor QEA, L.P. for Additional Construction Management Tasks and Necessary
Post - Dredge S
January 10, 2012
Page
FUNDING REQUIREMENTS — ANCHOR QEA, LP
The current adopted CIP budget includes sufficient funding for the award of this
Amendment Number 6 to Anchor QEA. Approximately $300,000 in project savings will
be returned to the Tidelands /Submerged Land fund account.
Account Description
Anchor QEA Unforeseen Management Costs
Anchor QEA Post - Dredge Sediment Sampling
Total
ENVIRONMENTAL REVIEW:
Account Number Amount
7231- C4402004 $ 244,266.00
7231- C4402004 $ 105,640.00
$ 349,906.00
The City prepared a Mitigated Negative Declaration for this Project that was reviewed
and approved by the City Council in July 2010.
NOTICING:
The agenda item has been noticed according to the Brown Act (72 hours in advance of
the meeting at which the City Council considers the item).
Submitted by:
r
/
Ptephen G. Badum
-Public Works Director
Attachments: A. Vicinity Maps
B. Professional Services Agreement — Anchor QEA, LP
/ MITO Wei ' 1111 L ii;- '`i, --
.y n n
`C 3
� C C
OO Cd N
y r
r C
� E
rc
v
v
A
C
E
c
0
u
v
c
L
U
W
C
L
[Y
J
�$
W (/��
^•T�''� /VR/
C
E j
8 �J
V
,O
AMENDMENT NO. SIX TO
PROFESSIONAL SERVICES AGREEMENT WITH
ANCHOR QEA, LP
FOR RHINE CHANNEL CONTAMINATED SEDIMENT CLEANUP PROJECT
THIS AMENDMENT NO. SIX TO PROFESSIONAL SERVICES AGREEMENT
( "Amendment No. SIX "), is entered into as of this day of 2011,
by and between the CITY OF NEWPORT BEACH, a California Municipal Corporation
( "City "), and ANCHOR QEA, LP a California Limited Partnership, whose address is
26300 La Alameda, Suite 420, Mission Viejo, California 92691 ( "Consultant "), and is
made with reference to the following:
RECITALS:
A. On July 14, 2009, City and Consultant entered into a Professional Services
Agreement ( "Agreement') to develop a Conceptual Design Plan for a Confined
Aquatic Disposal Site in Newport Harbor ('Project').
B. On November 10, 2009, City and Consultant entered into Amendment No. One
to the Agreement to increase the scope of work and to increase the total
compensation ( "Amendment No. One ").
C. On June 22, 2010, City and Consultant entered into Amendment No. Two to the
Agreement to increase the scope of work, to increase the term of the Agreement
to August 30, 2012, and to increase the total compensation ( "Amendment No.
Two ").
D. On October 12, 2010, City and Consultant entered into Amendment No. Three to
the Agreement to increase the scope of work and to increase the total
compensation ( "Amendment No. Three ").
E. On April 28, 2011, City and Consultant entered into Amendment No. Four to the
Agreement to increase the scope of work and to increase the total compensation
( "Amendment No. Four').
F. On June 7, 2011, City and Consultant entered into Amendment No. Five to the
Agreement to increase the scope of work, to increase the total compensation,
and update insurance requirements.
G. City desires to enter into this Amendment No. SIX to reflect additional services
not included in the Agreement or prior Amendments and to increase the total
compensation.
H. City and Consultant mutually desire to amend the agreement, as provided below.
11
NOW, THEREFORE, it is mutually agreed by and between the undersigned
parties as follows:
1. SERVICES TO BE PERFORMED
Section 2 of the Agreement, as amended, shall be supplemented to include the Scope
of Services dated December 7, 2011, which is attached hereto as Exhibit 'A' and
incorporated herein by reference. The City may elect to delete certain tasks of the
Scope of Services at its sole discretion.
2. COMPENSATION
The introductory paragraph to Section 4 of the Agreement as amended, shall be
amended in its entirety and replaced with the following: City shall pay Consultant for the
services on a time and expense not -to- exceed basis in accordance with the provisions
of this Section and the Schedule of Billing Rates attached to the Agreement.
Consultant's total amended compensation for all work performed in accordance with this
Agreement and all prior amendments, including all reimbursable items and
subconsultant fees, shall not exceed One Million, Seven Hundred Ninety -Four
Thousand, Three Hundred Thirty-Three Dollars and no /100 ($1,794,333.00) without
prior written authorization from City ( "Total Amended Compensation "). No billing rate
changes shall be made during the term of this Agreement without the prior written
approval of the City.
2.1 The Total Amended Compensation reflects Consultant's additional
compensation for additional services to be performed in accordance with
this Amendment No. Six, including all reimbursable items and
subconsultant fees, in an amount not to exceed Three Hundred Forty -Nine
Thousand, Nine Hundred Six Dollars and no /100 ($349,906.00), without
prior written authorization from City.
INTEGRATED CONTRACT
Except as expressly modified herein, all other provisions, terms, and covenants set forth
in the Agreement as amended, shall remain unchanged and shall be in full force and
effect.
ANCHOR QEA, LP
Page 2
I
IN WITNESS WHEREOF, the parties hereto have executed this Amendment No.
SIX on the dates written below.
APPROVED AS TO FORM: CITY OF NEWPORT BEACH,
CITY ATTORNEY'S OFFICE A California municipal corporation
Date: 17-/1:3 /11 Date:
By: By:
Aaron arp f/7y Michael F
City Attorney �, 1n�p Mayor
ATTEST:
Date:
By:
Leilani I. Brown
City Clerk
Henn
CONSULTANT: ANCHOR QEA, LP , a
Limited Partnership
Date:
By:
Steve Capellino
Senior Partner
Attachment: Exhibit A — Additional Services to be Performed
ANCHOR QEA, LP Page 3
17
EXHIBIT A
!¢
Dear Mr. Miller:
Anchor QEA, L.P., is currently assisting the City of Newport Beach (City) with. construction
management services for the Rhine Channel contaminated sediment cleanup project. This
letter requests funds for several out -of -scope construction management tasks related to the
dredge effort, and proposes an additional scope of work for conducting post - construction
sediment confirmational testing within the Rhine Channel. Each is described below in more
detail.
CONSTRUCTION MANAGEMENT OUT -OF SCOPE ITEMS
As the City is aware, dredging, of sediments within the Rhine Channel, as well as other
nearby City - managed areas was recently completed. To comply with several last minute
requirements from the Santa Ana Regional Water Quality Control Board (RWQCB), as well
as numerous operational changes required during construction to account for daily water
quality exceedances from the dredge operation, several out -of -scope tasks were required to
be immediately implemented by Anchor QEA staff.
Authorization to proceed with these tasks was granted by the City at the time of occurrence
to ensure that project delays did not result from the agency changes. This letter requests
ANCHOR
OEA�``_"'
26300 La Alameda, Suite 240 ............."..._....._..._,. ��.. w"..... "���— ~--- "���..�.�~�� -.W
Mission Viejo, California 92691
Phone 949.347.2780
..
Fax 949.334.9646
"
December 7, 2011
Mr. Chris Miller
City of Newport Beach, Harbor Resources Division
829 Harbor Island Drive
Newport Beach; California 92660
Re: Request for additional funds for out -of -scope Construction Management tasks, and
scope of work for Post- Dredge Confirmational Sediment Sampling and Analysis for
Rhine Channel Contaminated Sediment Cleanup Project
Dear Mr. Miller:
Anchor QEA, L.P., is currently assisting the City of Newport Beach (City) with. construction
management services for the Rhine Channel contaminated sediment cleanup project. This
letter requests funds for several out -of -scope construction management tasks related to the
dredge effort, and proposes an additional scope of work for conducting post - construction
sediment confirmational testing within the Rhine Channel. Each is described below in more
detail.
CONSTRUCTION MANAGEMENT OUT -OF SCOPE ITEMS
As the City is aware, dredging, of sediments within the Rhine Channel, as well as other
nearby City - managed areas was recently completed. To comply with several last minute
requirements from the Santa Ana Regional Water Quality Control Board (RWQCB), as well
as numerous operational changes required during construction to account for daily water
quality exceedances from the dredge operation, several out -of -scope tasks were required to
be immediately implemented by Anchor QEA staff.
Authorization to proceed with these tasks was granted by the City at the time of occurrence
to ensure that project delays did not result from the agency changes. This letter requests
Mr. Chris Miller
December 7, 2011
Page 2
funds for these out -of -scope items, as smnmarized below in Table 1 and detailed in the
attached summary. Because the project was completed quicker than expected, the actual on-
site construction management task was completed approximately $66,000 under budget.
Table 1
Summary of Construction Management Out -of -Scope Costs
Task C(ut of Sci: g�cc sts t F
. Task 1 -POLB Coordination
$737
Task 2— Contractor Selection and Pre - Dredge Dellverables
$55,404
Tasl<3 —Rhine Channel Tenant Coordination
$.14,420
Task 5— Rhine Channel Construction Management
($66,601)
Task 6 — Water Quality and Air Quality Monitoring
$240,306
Task 7— Construction Management for other City Properties
$0
Total Out -of -Scope Costs
$244,266
(xxx) = represents a credit for task that was under budget.
POST - DREDGE CON FIRMATIONAL SEDIMENT TESTING SCOPE OF WORK
In additional to the out- of-scope task item budget request, this letter also requests funds for
post- dredge confirmational sediment sampling and analysis, which is required by the Water
Board to verify successful removal of chemically impacted sediments and determine the final
surface sediment chemical concentrations. This will allow an assessment of the site from a
303(d) improvement standpoint. At the request of the City, this task was not included
previously in Anchor QEA's original scope of work because we were not previously able to
anticipate the magnitude of the study that might be required to comply with the Water
Board permit.
A total of five tasks have been identified for the Rhine Channel confirniational testing
program:
4 Preparation of a Sampling and Analysis Plan (SAP)
Meeting with Regulatory Agencies
o Sediment Sampling
o Chemical Analysis
Reporting
i
A
r�
Mr. Chris Miller
December 7, 2011
Page 3
The scope and associated costs for these tasks are presented below.
Proposed Tasks +•`,`:LL
Task 1: Preparation of a Sampling and Analysis Plan ~"
Anchor QEA will develop a SAP presenting details on the sampling and analysis strategy. It
will be designed to determine the final concentrations of contaminants within Rhine
Channel following the removal of chemically impacted sediments. It will include procedures
for sediment sample collection, sample handling, chemical analysis, quality assurance/quality
control (QA/QQ, and data analysis, A draft SAP will be submitted to the RWQCB for
review and approval. One round of comments is anticipated. Following approval of the
SAP, sampling will be initiated. Costs associated with this task are estimated at $12,210.
Task 2: Meeting with Regulatory Agencies
Anchor QEA will work closely with regulatory agencies to ensure sampling and analysis
complies with regulatory requirements. This may include meetings with regulatory
agencies, project updates, response to comments, and a presentation of results. Costs
associated with this task are estimated at $6,080.
Task 3: Sediment Sampling
Sediment sampling will be conducted at approximately 15 randomly placed stations using a
piston core. The piston core will be deployed from Anchor QEA's sampling vessel, a 20 foot
AquaSport. Sediment cores will be processed landside. Each core will be logged and
photographed then segmented into 6 inch increments. The top 6 inches will be submitted
for chemical and physical analysis. Remaining core segments will be archived for additional
analysis, if needed. It is assumed that this task will require 3 days of field work for two
Anchor QEA personnel. Costs associated with this task are estimated at $15,010.
Task 4: Chemical Analysis
Approximately 15 samples will be submitted for chemical analysis. In addition, archived
samples may be analyzed if the upper residual layer indicates elevated contaminants.
Chemical analysis will include constituents that are listed and have numeric targets for the
Rhine Channel water body within the San Diego Creek/Newport Bay Toxics Total Maximum
I
Mr. Chris Miller
December 7, 2011
Page 4
Daily Load (TMDL). This includes chromium, copper, lead, mercury, selenium, zinc,
chlordane, dieldrin, DDTs, and PCBs. In addition, pyrethroids will be measured as requested
by the RWQCB. Physical analysis will include grain size, total organic carbon, and total
solids. Chemical analysis will be performed at Calscience Environmental Laboratories,
located in Garden Grove, California. Anchor QEA will perform a data review, validation,
and verification to ensure data quality objectives have been met. Costs associated with this
task are estimated at $22,670. Analysis of archived samples will be an additional $1,050 per =' • ,:
;!s
sample.
Task 5: Reporting
Afinal report will be prepared by Anchor QEA documenting all activities associated with
collecting, processing, and analyzing sediment samples. Chemistry results will be compared
to numeric targets listed in the San Diego Creek/Newport Bay Toxics TMDL. The final
concentrations of chemical contaminants in the surface layer of the Rhine Channel will be
presented using GIS. A project map will be included with the actual sampling locations.
Field logs, core photographs, and reports .received from the laboratories will be included as
appendices. The final report will be submitted to RWQCB for review and approval. Costs
associated with this task are estimated at $18,420.
Summary of Estimated Sediment Testing Costs and Schedule
Total estimated costs associated with the five confirmational testing project tasks are
summarized in Table 2. The total cost is estimated at $74,390. Of this amount,
approximately $16,760 is for subcontractors for analytical charges. If archived samples from
below 6 inches of each core are analyzed, additional costs will be $1,050 per sample.
Additionally, if the Water Board were to require more than 15 sample locations to meet the
permit requirements, additional costs would be incurred. To provide an estimate of the
potential additional costs, a contingency task has been added to the table to reflect the
additional cost of collecting 5 more core samples and analyzing two additional depths at half
of the core locations (40 samples total).
,
Mr. Chris Miller
December 7, 2011
Page 5
We propose to conduct this work on a not -to- exceed, time- and - materials basis, as has been
done for our work to date. Throughout the conduct of these tasks, Anchor QEA will provide
detailed comments and summarize staff efforts on all invoices.
Table 2
Summary of Confirmational Testing Project Costs
Ly , _s.tr
TasP
1.
Preparation of a Sampling and Analysis Plan
12,210
2.
Meeting with Regulatory Agencies
$318,656 - $349,906.
6,080
3.
Sediment Sampling
15,010
4.
Chemical Analysis
22,670
5.
Reporting
18,420
6.
contingency for additional cores /samples
31,250
Total (with and w/out contingency)
74,390- 105,640*
`Base costs do not include analysis of archived samples. A range in costs is provided to account for uncertainty
in final testing requirements from the Water Board.
Work on this task would begin as soon as authorization is received from the City.
Preparation of the draft SAP is expected to take three weeks to complete, followed by
RWQCB review. Immediately upon receipt of comments, the SAP will be revised and
finalized. Upon approval, field sampling will be conducted. Sampling is expected to last 3
days. The standard turnaround time for chemical analysis is 10 to 15 days. The final report
will be submitted to RWQCB 45 days following the completion of sampling.
SUMMARY OF COSTS
The total additional amount requested for both items is summarized in Table 3.
Table 3
Summary of Requested Change Order Costs
i k, it term'
Construction Management Out -of -Scope Items
$244,266
Rhine Channel Confirmational Sediment Sampling
and Testing
$74,390— $105,640*
Total
$318,656 - $349,906.
I
' I
"Range in costs provided to account for uncertainty in final testing requirements from the Water Board.
i
Mr. Chris Miller
December 7, 2011
Page 6
We appreciate the opportunity to work with the City on this project. If there are any
questions about this scope of work, please do not hesitate to contact us at (949) 347 -2780.
Sincerely,
<j
Steve Cappellino
Anchor QEA, L.P.
00
Summary of .Anchor QEA Out of Scope Items
Task 1 — POLB Coordination
Throughout the majority of the project's duration, the level of effort needed for this task was
commensurate with initial expectations and budget projections. However, in November, a
sigtficantly more concerted effort was required by Anchor QEA personnel (Steve Cappellino, Shelly
Anghera; Rob Walker and Michael Whelan) to present and discuss final placement of Rhine Channel
material within the Middle Harbor Slip I fill site with Port of Long Beach (POLB) Construction
Management staff.
Task 2 — Contractor Selection and Pre- Dredge Deliverables
This task required significant effort above and beyond initial expectations and budget projections to
work with the contractor on finalizing their pre- dredge deliverables while meeting the needs of the
Regional Water Quality Control Board (RWQCB) with regards to the water quality permitting and
compliance process. The original scope of work assumed one xeview /comment cycle for each of the
contractor's pre - construction deliverables. However, multiple drafts and rounds of comments were
needed for some of the key submittal documents (most notably the dredge and disposal plan and
environmental protection plan). Similarly, several discussions and meetings were needed to make
sure the final submittals were suitable for submittal to agencies and POLB.
A similar expenditure of labor time was needed prior to construction in responding to contractor
questions regarding work planned for the floating docks and guide piles. It was anticipated that some
discussions would be needed, but the amount of time spent prior to construction was more than
budgeted. These efforts required several meetings and communications so as to ensure that these
aspects of the project would be coordinated and handled properly.
For the RWQCB permit, a Sampling and Analysis Plan (SAP) and Quality Assurance Project Plan
(QAPP) were required prior to construction, although these were not originally anticipated as being
necessary for the project. This was an intensive process that required significant effort and numerous
internal and external meetings, in part because the RWQCB determined that the documents needed
to be consistent with guidelines issued by the Surface Water Ambient Monitoring Program
(SWAMP), significantly increasing the level of effort needed. The following reviews some of the key
steps in the process:
C A meeting was held on 8/5/10 to discuss water quality monitoring and post- sediment
sampling.
• A WQMP was submitted on 8/20/10 by Anchor QEA.
• Comments were provided on 9/9/10 by the RWQCB.
2/
I
I
Summary of Anchor QEA Out of Scope Items
December 7, 2011
Page 2 of 4
• A follow -up meeting was held after comments were received and notes were prepared by
Anchor QEA to document the discussion and planned changes to the document. Anchor QEA
wrote numerous emails and called numerous times to request a timely review of the
SAP /QAPP. To further facilitate the process, Anchor QEA resubmitted an updated document
on 5/19/11.
• Comments from the RWQCB were received on 6/8/11. Due to inconsistencies with previous
comments and discussions, another meeting was scheduled with the RWQCB to discuss on
6/28/11.
• Based on this meeting the SAP /QAPP was further revised and a final SAP /QAPP, along with
response to comments, was submitted on 7/28/11 to the RWQCB.
• Based on comments and emails from the RWQCB, a SWAMP compatible SAP /QAPP was
required to replace the Water Quality Monitoring Plan (WQMP) previously submitted. Due
to the SWAMP requirements, it required more than triple the effort of typical water quality
monitoring SAPS (which have no QAPPs).
• Just prior to construction the RWQCB issued additional comments and concerns which
required addressing and incorporating into the final field monitoring program.
As described above, a significant amount of unanticipated effort went into preparing the WQMP and
various SAP /QAPP drafts, coordinating documents and meetings, soliciting feedback from the
RWQCB through emails and calls, and discussing comments /revising the document numerous times.
This level of coordination that was required with the RWQCB was far greater than what would be
needed for a typical document (SAP or report) submittal procedure, as occurs with other Regional
Boards or regulatory agencies in Southern California. The typical procedure involves submittal of a
draft SAP (if any), respond to one set of comments, one meeting, and submittal a final SAP.
Altogether, four versions of the document were submitted, three meetings, several calls, and
numerous emails tools place to discuss the comments and to keep the process moving forward. In
addition, the RWQCB's determination that the documents needed to be compatible with SWAMP
requirements made their preparation significantly more rigorous than would have been required by
other Regional Boards in California. Anchor QEA suggested that the SWAMP format would not, in
fact, be relevant to this project, because California's SWAMP was not designed for evaluating short -
term water quality impacts such as those due to dredging, but instead is a regional program focused
on assessing long -term water quality trends. Nevertheless, the RWQCB did not change their position
in this regard, although Anchor QEA was successful in reducing the number of required sampling
events, the analytes required for analysis, and some unachievable reporting limit issues initially
proposed by the RWQCB.
?Z
Summary of Anchor QEA Out of Scope Items
December 7, 2011
Page 3 of 4
Task 3 — Pre - Construction Tenant Coordination
Out of scope activities for this task was fairly limited and included working with the contractor to
coordinate with the POLB on delivery schedules, coordinating with various tenants on the Rhine
Channel regarding their participation on the project, and numerous meetings regarding schedule
coordination for dredging the Channel Road area and the accompanying dock relocation. At project's
end considerable effort was expended in ensuring that piles and docks met the approval of the various
property owners and representatives
Task 5 — Rhine Channel Construction. Management
Although in aggregate this task ended up under budget, there were a few notable out of scope items.
For instance, change orders were needed to reduce the dredge footprint for certain properties based
on discussions immediately prior to (or during) construction between these property owners and the
CIty. Both change order efforts required adjusting the plan sheets, calculating adjusted quantities for
contract volume estimates, and preparation of updated specifications and /or narrative descriptions for
the modified work efforts, Ina similar fashion, five separate areas of additional dredging turned out
to be needed, each of which also required generation of figures and coordinates depicting the
additional dredging, calculation of resulting dredge quantities, additional analysis of progress
surveys, and a second round of confirmatory sampling at each location. Although it was anticipated
that additional dredging might be needed, and budgeted accordingly, the incidence of five separate
areas ended up requiring more effort than originally expected.
Task 6 — Water Quality and Air Quality Monitoring
Implementation of the expanded water quality monitoring program was the single largest out of
scope item required for completion of the Rhine Channel construction effort. Based on early water
quality monitoring results, an expanded monitoring program was required by the RWQCB which
included daily monitoring, special studies, more frequent data reports to the State, and additional
chemical analytes. The following highlights the major differences in project assumptions that
changed as a result of the Water Board requirements.
• Budgeted for 64 samples for chemical analysis and ended up with 218 in total.
• Budgeted for 5 QA/QC samples for chemical analysis and ended up with 13 in total.
• Budgeted for 23 sampling events and ended up with 66 in total.
• Budgeted for three reports to the RWQCB (pre - dredge, midpoint and final) and ended up
requiring six (pre - dredge, midpoint, final, 16, week, revised schedule, and two special studies).
• Conducted special studies to evaluate the following issues for the RWQCB: turbidity/TSS
comparison, water quality at additional reference stations, plume tracking studies, follow -up
2�
Summary of Anchor QEA Out of Scope Items
December 7, 2011
Page 4 of 4
turbidity study in main channel. All of these special studies required management,
negotiation and coordination with Water Board staff.
Anchor QEA was, however, able to mitigate the effect of these changes on overall project costs, by
utilizing City labor wherever possible for the water quality monitoring. Approximately 55 man hours
were used to supplement the Anchor QEA field team resulting in a cost savings of almost $5,000 to
the project.
Task 7 — Construction Management at other City Properties
With an agreement reached between the City and American Legion Post 291 to perform additional
dredging and pile replacement activities within the American Legion marina, Anchor QEA provided
additional construction coordination and oversight for the expanded scope of work. This included
several meetings with American Legion staff prior to construction to work through logistical details
relating to construction. During construction, the temporary relocation of the floating docks
required additional oversight. This included documentation of pre - existing conditions, general
construction oversight and documentation throughout the move, and assisting the City in
maintaining public safety protocols for this temporary obstruction to navigation. With an additional
ten piles replaced by the American Legion change order, additional construction oversight during
pile driving activities was provided above our initial expectations. The out of scope items for this task
ended up not requiring addition funds as the work was completed faster than expected so savings
were achieved in other portions of the scope.
tt.