HomeMy WebLinkAbout10 - Eastbluff Park Field Improvements - NOC and Acceptance of Contract No. 6268 (16P11)10-1 NEWPORT BEACH City Council Staff Report COUNCIL STAFF REPORT CITY OF April 12, 2016 Agenda Item No. 10 ABSTRACT: On November 24, 2015, City Council awarded Contract No. 6268, Eastbluff Park Field Improvements project, to Calpromax Engineering, Inc. (Calpromax) for a total contract cost of $138,800.00 with a $21,000.00 (15 percent) allowance for contingencies. The required work is now complete and staff requests City Council acceptance and close out of the contract. RECOMMENDATION: a) Accept the completed work and authorize the City Clerk to file a Notice of Completion for the project; b) Authorize the City Clerk to release the Labor and Materials Bond 65 days after the Notice of Completion has been recorded in accordance with applicable portions of the Civil Code; and c) Release the Faithful Performance Bond one year after acceptance by the City Council. FUNDING REQUIREMENTS: Funds for the construction contract were expended from the following account: Account Description Account Number Amount Building Excise Tax 14101-980000-16P11 $146,746.22 Total:$146,746.22 TO:HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL FROM:David A. Webb, Public Works Director - 949-644-3311, dawebb@newportbeachca.gov PREPARED BY:Peter Tauscher, Civil Engineer, ptauscher@newportbeachca.gov PHONE:949-644-3316 TITLE:Eastbluff Park Field Improvements - Notice of Completion and Acceptance of Contract No. 6268 (16P11) Eastbluff Park Field Improvements - Notice of Completion and Acceptance of Contract No. 6268 (16P11) April 12, 2016 Page 2 10-2 DISCUSSION: Overall Contract Cost/Time Summary Awarded Contract Amount Final Cost at Completion Contingency Allowance Actual Contract Change % Due to Directed Change % Due to Unforeseen Change $138,800.00 $146,746.22 15% or less 5.7% 0% 4.8% Allowed Contract Time (days) 38 Actual Time Under (-) or Over (+)-0 The Eastbluff Park baseball field is currently used by local youth baseball programs. The backstop and fences were dilapidated and needed replacement and upgrades due to the proximity to the playground and parking lot. On occasion, foul balls were hit into the playground and nearby parking lot. For this reason, the outdated backstop and fences were replaced with new fences and netting that extends along the infield up to a maximum height of 40 feet. The work completed consisted of removing the backstop and fencing; installing an up- to-date back stop system; replacing the drinking fountain with bottle filler model; and restoring damaged areas to the field or sidewalk. The contract was completed to the satisfaction of the Public Works Department. A summary of the contract cost is as follows: Original bid amount:$ 138,800.00 Actual cost of bid items constructed:$ 140,042.00 Total change orders:$ 6,704.22 Final contract cost:$146,746.22 The final construction contract cost was approximately 4.8 percent over the original contract amount. A majority of the change order was attributed to relocating an irrigation line to accommodate the new improvements. A summary of the project schedule is as follows: Estimated Completion Date per January 2016 Schedule March 31, 2016 Project Awarded for Construction November 24, 2015 Contract Completion Date with Approved Extensions March 17, 2016 Actual Substantial Construction Completion Date March 17, 2016 Eastbluff Park Field Improvements - Notice of Completion and Acceptance of Contract No. 6268 (16P11) April 12, 2016 Page 3 10-3 ENVIRONMENTAL REVIEW: On November 24, 2015 the City Council found this project exempt from the California Environmental Quality Act (CEQA) pursuant to Section 15302 (replacement of existing facilities involving negligible expansion of capacity) of the CEQA Guidelines, California Code of Regulations, Title 14, Chapter 3, because it has no potential to have a significant effect on the environment. NOTICING: The agenda item has been noticed according to the Brown Act (72 hours in advance of the meeting at which the City Council considers the item). ATTACHMENTS: Attachment A – Location Map 10-4