Loading...
HomeMy WebLinkAbout08 - 2014-2015 Streetlight Improvement Project - NOC and Acceptance of Contract No. 5818 (15E01)��WPaRT CITY OF O � _ z NEWPORT BEACH Cq</ Fp P City Council Staff Report May 10, 2016 Agenda Item No. 8 TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL FROM: David A. Webb, Public Works Director - 949-644-3311, dawebb@newportbeachca.gov PREPARED BY: Peter Tauscher, Civil Engineer, ptauscher@newportbeachca.gov PHONE: 949-644-3316 TITLE: 2014-2015 Streetlight Improvement Project - Notice of Completion and Acceptance of Contract No. 5818 (15E01) ABSTRACT - On January 27, 2015, City Council awarded Contract No. 5818, 2014-2015 Streetlight Improvement Project to Elecnor Belco Electric, Inc. (Belco), for a total contract cost of $930,484.00 with a $94,516.00 (10 percent) allowance for contingencies. The contracted work involved the replacement of existing streetlight fixtures with new energy-efficient LED streetlight fixtures and upgrading existing streetlight circuits. The required work is now complete and staff requests City Council acceptance and close out of the contract. RECOMMENDATION: a) Accept the completed work and authorize the City Clerk to file a Notice of Completion for the project; b) Authorize the City Clerk to release the Labor and Materials Bond 65 days after the Notice of Completion has been recorded in accordance with applicable portions of the Civil Code; and c) Release the Faithful Performance Bond one year after acceptance by the City Council. FUNDING REQUIREMENTS: The current adopted budget included sufficient funding for this project. It is being expensed to the general fund account in the Public Works Department, 15E01 - Construct -010 -Unassigned. 8-1 2014-2015 Streetlight Improvement Project - Notice of Completion and Acceptance of Contract No. 5818 (15E01) May 10, 2016 Page 2 DISCUSSION: Overall Contract Cost/Time Summary Awarded Final Cost at Contingency Actual % Due to % Due to Contract Amount Completion Allowance Contract Directed Unforeseen Change Change Change $930,484.00 $972,184.19 10% or less 4.5% -7.2% 11.7% Allowed Contract Time (days) 195 Actual Time +0 Under (-) or Over (+) The contract has now been completed to the satisfaction of the Public Works Department. A summary of the construction contract cost is as follows: Original Bid Amount: $930,484.00 Actual Cost of Bid Items Constructed: $863,413.40 Total Change Orders: $108,770.79 Final Contract Cost: $972,184.19 The contract replaced 214 existing streetlight fixtures with new energy-efficient LED streetlight fixtures and upgraded the existing streetlight circuits as part of the City's Streetlight Replacement Program. The project area included Irvine Avenue from north of Santiago Road to Tustin Avenue, and a portion of the Westcliff neighborhood. The contract was completed to the satisfaction of the Public Works Department. The final construction contract cost was approximately 4.5 percent over the original contract amount. A majority of the cost increase was caused by the unforeseen need to locate and accommodate existing utilities previously unknown and discovered during the construction. As a result of needing to address unforeseen underground utility conflicts, Belco was granted an additional 10 working days to complete the project. ENVIRONMENTAL REVIEW: City Council found this project exempt from the California Environmental Quality Act (CEQA) pursuant to Section 15302 (replacement of existing facilities involving negligible expansion of capacity) of the CEQA Guidelines, California Code of Regulations, Title 14, Chapter 3, because it has no potential to have a significant effect on the environment. 8-2 2014-2015 Streetlight Improvement Project NOTICING: - Notice of Completion and Acceptance of Contract No. 5818 (15E01) May 10, 2016 Page 3 The agenda item has been noticed according to the Brown Act (72 hours in advance of the meeting at which the City Council considers the item). ATTACHMENTS: Attachment A — Location Map 8-3 ATTACHMENT A STREETLIGHT CIRCUIT SLD0067 "' NTS \4 NEWPORT BACK BAY I FGFNn CONSTRUCTION LIMITS STREETLIGHT CIRCUIT SLD0076 NTS 2014-2015 STREETLIGHT CITY OF NEWPORT BEACH IMPROVEMENT PROJECT PUBLIC WORKS DEPARTMENT LOCATION MAP C-5818 5/10/16 15E01 1 OF 2 ATTACHMENT A I FrFND CONSTRUCTION LIMITS STREETLIGHT CIRCUIT SLD0074 NTS 2014-2015 STREETLIGHT CITY OF NEWPORT BEACH IMPROVEMENT PROJECT PUBLIC WORKS DEPARTMENT LOCATION MAP C-5818 5/10/16 15E01 2 OF 2 RIM