HomeMy WebLinkAbout09 - Marina Park Project - NOC for Contract No. 3897-C (15P14) - Building and Site Development - Bid Package 3CITY OF
NEWPORT BEACH
City Council Staff Report
TO:
FROM:
PREPARED BY:
PHONE:
June 14, 2016
Agenda Item No. 9
HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
David A. Webb, Public Works Director - 949-644-3311,
dawebb@newportbeachca.gov
Iris Lee, Senior Civil Engineer, ilee@newportbeachca.gov
949-644-3323
TITLE: Marina Park Project - Notice of Completion for Contract No. 3897-C
(15P14) - Building and Site Development - Bid Package 3
ABSTRACT -
On May 13, 2014, City Council awarded Contract No. 3897-C, Marina Park Project —
"Building and Site Development" to KPRS Construction Services, Inc. (KPRS) for a total
contract cost of $18,748,000.00 plus a 10 percent contingency allowance. The work on
Contract No. 3897-C is now complete and staff requests City Council acceptance and close
out of this contract. This contract is one of four Marina Park construction contracts. With
the recommended acceptance and completion, the entire Marina Park project would be
considered complete. A summary of the entire project cost is included in this report and
shown on Attachment B.
RECOMMENDATION:
a) Determine that no further California Environmental Quality Act (CEQA) action is
necessary. All significant environmental effects for Marina Park have been adequately
addressed in the previously certified Environmental Impact Report No. (SCH No.
2008051096);
b) Accept the completed work for Contract No. 3897-C, Marina Park Project — "Building and
Site Development" and authorize the City Clerk to file a Notice of Completion for the
project;
c) Authorize the City Clerk to release the Labor & Materials Bond for Contract No. 3897-C
65 days after the Notice of Completion has been recorded in accordance with applicable
portions of the Civil Code; and
d) Release the Faithful Performance Bond for Contract No. 3897-C one year after
acceptance by the City Council.
9-1
Marina Park Project — Building and Site Development (Bid Package 3) — Notice of
Completion of Contract No. C -3897-C (15P14)
June 14, 2016
Page 2
FUNDING REQUIREMENTS:
Funds for the construction for Contract No. 3897-C were expended from the following
accounts:
Account Description Account Number Amount
Marina Park 15P14 -construct -551 -unassigned $ 19,715,588.59
Lighthouse Cafe Deposit Account 017-241079 $ 44,500.43
Total: $ 19,760,089.02
The Lighthouse Cafe Deposit account was established to facilitate tenant -related
improvements that could be completed by the City's contractor that would otherwise not be
constructed in a timely and/or cost efficient manner by the tenant. Expenditures associated
with this account were deducted from tenant -advanced private funds for such work. This
account is now closed and has a zero balance.
DISCUSSION:
Overall Contract No. 3897-C Cost/Time Summary
Awarded
Final Cost at
Contingency
Actual
% Due to
% Due to
Contract Amount
Completion
Allowance
Contract
Directed
Unforeseen
Change
Change
Change
$19,715,588.59
5.16%
1.24%
3.92%
$18,748,000
10% or less
$19,760,089.02*
5.40%*
1.46%*
3.94%*
Allowed Contract Time (days) =
340
Actual Time
-14
Approved Extensions
Under (-) or Over (+)
* Includes Lighthouse Cafe expenditures for tenant improvements that were requested by
and paid for by the restaurant operator.
Contract No. 3897-C, Marina Park Project — "Building and Site Development" has now been
completed to the satisfaction of the Public Works Department. A summary of this contract's
construction cost is as follows:
Original bid amount:
Total change orders related to City portion of work:
Total change orders related to Lighthouse Cafe work:
Final contract cost:
$18,748,000.00
$ 967,588.59
$ 44,500.43
$19,760,089.02
The 10 -acre Marina Park Project is located on the bay side of the Balboa Peninsula
between 15th Street and 19th Street (Attachment A). This project included the demolition
and removal of the former mobile home park and other City facilities, construction of a new
23 -slip visitor -serving marina and two instructional sailing basins, a community center and
9-2
Marina Park Project — Building and Site Development (Bid Package 3) — Notice of
Completion of Contract No. C -3897-C (15P14)
June 14, 2016
Page 3
sailing center, children's themed playground and picnic area, two half -court basketball
surfaces, a fitness circuit, Lighthouse Cafe (operated privately under lease), reconstruction
of the 19th Street public restroom facility, beach frontage improvements, and 177 on-site
parking spaces. After many years of planning, design and permitting, the project broke
ground in December 2013.
Due to the complexity and prominently different types of construction operations needed to
build this new park facility, the Marina Park project was divided into four general
construction plan sets and bid packages. The first construction bid package involved the
demolition and removal of the prior mobile home park, site utilities and tree relocation. The
second construction bid package involved the construction of the new Marina Basin and
moving the resulting sand to specific beaches for replenishment. The third construction bid
package, which staff is requesting that City Council accept tonight, is for construction of the
buildings and park site. The fourth construction bid package included the construction of
the new dock facilities in the new marina. Notices of completion have already been filed for
construction bid packages 1, 2 and 4.
This third and final construction bid package (Contract No. 3897-C — "Building and Site
Development") was approximately 5.16 percent above the original bid amount. This
accounted for 19 change orders that amounted to $967,588.59. While the change orders
primarily stemmed from unforeseen issues, there were directed change orders involving
items that enhanced functionality and aesthetics such as plaster coating, additional
cabinetry, lighting, and communication equipment. Unforeseen change orders included
additional removals and grading, foundation rework and delays, underground utility
services, and extended landscape maintenance efforts, of which all were thoroughly
examined and negotiated. The project change orders are not uncommon for a development
of this magnitude and character, and are accounted within the construction allowance.
A summary of the schedule for Construction Package 3 (Contract No. 3897-C) is as follows:
Estimated Completion Date April 2016
Project Awarded for Construction May 13, 2014
Contract Completion Date with Approved Extensions December 17, 2015
Actual Substantial Construction Completion Date December 4, 2015
The project was substantially complete as of December 4, 2015, with all building and site
improvements. Some miscellaneous close-out items, operation & maintenance turnover,
and financial paperwork post -substantial completion needed to be finalized prior to the
Notice of Completion action.
Overall Project Final Budget Summary:
Staff has included a running summary table of the total Marina Park Budget to date (see
Attachment B). The "all -in" estimated total project budget was established at $39,500,000.
This estimated cost included conceptual design and permitting; land acquisition; all soft
costs such as project design, geotechnical testing and inspection, and construction
management; hard construction cost for all four bid packages, fixtures furniture & equipment
9-3
Marina Park Project — Building and Site Development (Bid Package 3) — Notice of
Completion of Contract No. C -3897-C (15P14)
June 14, 2016
Page 4
(commonly known as FF&E); as well as a City Reserve. While Marina Park construction
now is complete, some very minor expenditures for additional furnishing and administrative
close-out work will be forthcoming in the coming months. The anticipated total project cost is
$36,435,000.00, which is approximately $3,065,000 under the estimated project budget.
The total awarded construction contract amount for all four bid packages was
$26,666,870.00, with a final construction cost of $27,852,643.87. This represents an overall
construction change order rate of 4.45 percent.
ENVIRONMENTAL REVIEW:
All significant environmental effects for the Marina Park project have been adequately
addressed in the previously certified Environmental Impact Report (SCH No. 2008051096)
(EIR). Copies of the previously prepared and approved environmental document are
available for public review and inspection at the City of Newport Beach website at
http://www.newportbeachca.gov/cegadocuments.
NOTICING:
The agenda item has been noticed according to the Brown Act (72 hours in advance of the
meeting at which the City Council considers the item).
ATTACHMENTS:
Attachment A — Location Map
Attachment B — Budget Summary
W. BAY AVENIJE`— d
w
w
2
F-
m
w
w
cnI-
2
t -
a2
ATTACHMENT A
NEWPORT HARBOR
Xs] ir=1►
w
Lu
ir
F -
u7
2
u -s
► :� :ice :�' �'a�
Ld
w w
Lu w
F. H
w U7
n � n
OCEAN FRONT WEST
BUILDING & SITE DEVELOPMENT
LOCATION MAP
I Fr,FKIn
MARINA PARK PACKAGE 3
BOUNDARIES
CITY OF NEWPORT BEACH
PUBLIC WORKS DEPARTMENT
C -3897-C 6/14/16
(15P14)
a
MARINA PARK
MASTER BUDGET
im
BUDGETED
BUDGETED
ACTUAL
ACTUAL
TASK DESCRIPTION
DETAIL COST
TOTAL
DETAIL COST
TOTAL
COMMENTS
1
CONCEPTUAL DESIGN/PERMITTING
$ 1,680,441
$ 1,685,019
Complete
a
b
RHdo Conceptual Design - closed
Newfields (marine sediment sample) -closed
$ 480,427
$ 114,772
$ 480,427
$ 119,350
a
Coast Survey -closed -closed
$ 27,980
$ 27,980
b
Schmitz & Associates (CCC Application) -closed
$ 225,000
$ 225,000
a
Coastal Resource Management (sand disposal study) -closed
$ 14,637
$ 14,637
b
Gable Engineering (on-going support) -closed
$ 363,715
$ 363,715
a
Traker (cost estimating) -closed
$ 103,815
$ 103,815
b
Michael Branman (environmental) -closed
$ 195,187
$ 195,187
a
Leighton (SCE parcel Phase 1/11 report) -closed
$ 26,452
$ 26,452
b
George Hamilton (appraisal) -closed
$ 28,500
$ 28,500
a
Austin Foust -closed
$ 8,960
$ 8,960
b
Sirius EIR consultant) -closed
$ 90,996
$ 90,996
2
LAND ACQUISITION
$ 600,000
$ 605,116
$600k cash plus closing fees
a
SCE Parcel
$ 600,000
$ 605,116
3
SOFT COSTS
$ 5,035,156
$ 4,867,473
a
A/E SERVICES / RABBEN HERMAN
$ 2,620,861
$ 2,574,770
Rabben Herman and Design Team
RHdo
$ 2,574,770
b
GEOTECHNICAL (Stone Column Design) /TERRACOSTA
$ 145,635
$ 159,434.90
Design/Inspection of Stone Column system
$ 145,635
$ 145,635
Terra Costa
Preconstruction Mtg
Incl
Incl
Stone Column Installation Observation
Incl
Incl
Stone Column Reports
Incl
Incl
Amendment 1 to PSA
$ 13,800
Terra Costa Amendment 1 was approved for $30,982.76)
c
TESTING AND INSPECTION
$ 305,000
$ 552,786
Soils Testing, Material Testing, Final Report
$ 205,000
$ 206,487
GMU Geotechnical
GMU PSA Amendment No. 1
$ 158,758
Additional Testing/oversight for Marina
GMU PSA Amendment No. 2
$ 5,857
Additional Testing/oversight for Marina Pile Driving
Roofing Inspections
$ 20,000
$ 26,383
Independent Roofing Consultants (IRC)
Specialty Paint and Coating Inspection
$ 10,000
Coating & Inspection Services
Environmental Plan, WQ & Biological Monitoring
$ 80,000
$ 145,301
d
CONSTRUCTION MANAGEMENT
$ 1,222,860
$ 1,222,860
Griffin Structures
Construction Management
$ 1,199,860
$ 1,199,860
Reimbursable
$ 23,000
$ 23,000
im
MARINA PARK
MASTER BUDGET
9-7
TASK DESCRIPTION
BUDGETED
DETAIL COST
BUDGETED
TOTAL
ACTUAL
DETAIL COST
ACTUAL
TOTAL
COMMENTS
e
SOFT COST CONTINGENCY
$ 450,000
$
Soft Cost Contingency
$ 450,000
f
HAZMAT ABATEMENT
$ 27,800
$ 25,670
Environcheck; LBP & Asbestos Report
$ 12,800
$ 12,800
3rd Party Abatement Observation and Reporting (SCS)
$ 15,000
$ 12,870
Total of SCS ($10,500) & H2 ($2,370)
g
UTILITY COMPANY CONNECTION SERVICES AND FEES
$ 205,000
$ 182,606
Edison
$ 100,000
$ 89,102
So Cal Gas
$ 35,000
$ -
($25,277.50 paid through KPRS CO)
Time Warner
$ 35,000
$ 33,608
Cable installation
ATT
$ 35,000
$ 59,896
h
CITY OF NEWPORT BEACH/OTHER AGENICIES FEES
$ 5,000
$ 25,820
MEP Plan Check Fees
$ -
$ -
Grading Plan Check (Based on 43750 cut / fill)
$ -
$ 22,016
GMU Grading Plan Check Fees
Sanitation District Fee
$
$ -
School District Fee
$
$ -
Plan Check Fee
$
$ -
Permit Fee
$
$ 2,508
Seismis Safety & Green Building Registration
CONBFD
$
$ -
Coastal Commission Fees
$ -
$ -
OC Health Dept. Fees
$ 5,000
$ 1,296
i
MISCELLEANOUS COST/FEES
$ 53,000
$ 123,525
Submittal Exchange/Plan Reproduction
$ 25,000
$ 14,778
Final Parcel Maps & Easements
$ 15,000
$ 24,532
Public Outreach
$ 10,000
$ -
LEED Certification
$ 3,000
$ -
Deleted Requirement
Tight Quarters
$ 5,200
Additional Beach Sand Management
Misc Survey and Legal Descriptions
$ 8,835
Misc Charges and Items
$ 70,180
9-7
MARINA PARK
MASTER BUDGET
BUDGETED BUDGETED
ACTUAL
ACTUAL
TASK DESCRIPTION
DETAIL COST TOTAL
DETAIL
COST
TOTAL COMMENTS
4 HARD COSTS
$ 29,543,281
$ 27,862,644
a PACKAGE 1: Demolition and Tree Relocation
$ 410,471
Final Total Contract Amount = $332,934
Original Contract
$
405,130
Unlimited Environmental Inc.
Remainder of 10% Contingency (Began with $40,513)
$
-
None Used in Contract
Change Order No. 1
$
(67,516)
Credit for Mobile Homes
Reduction to Senna Tree Company Work
$
(4,680)
Initial Contract Amount Reduced at Conclusion
b PACKAGE 2: Marina Basin Construction
$ 3,671,724
Final Total Contract Amount = $4,842,769
Original Contract
$
4,576,079
The Dutra Group
Remainder of 10% Contingency (Began with $457,608)
$
-
Final - Used 5.83% Contingency
Bid Item Adjustment Amount
$
(8,127)
Final addition/deduction in bid quantities
Change Order No. 1
$
(26,543)
Deletion of Deadman Support
Change Order No. 2
$
13,565
Install Additional Rock/Fabric for GS Facility Pad
Change Order No. 3
$
10,493
Changed Condition regarding American Legion wall
Change Order No. 4
$
243,000
Excavation of additional 4000 cy suitable beach sand
Changed sub -surface condition on bulkhead install
Removal of unknown & abandon utilities & structures.
Change Order No. 5
$
34,302
WiFi, Added Sand 18th ST, grout tie -back holes
c PACKAGE 3: Community Center and Park
$ 17,421,081
Final Total Contract Amount = $19,760,089
Original Contract
$
18,748,000
KPRS Construction Services Inc.
Remainder of 10% Contingency (Begin with $1,874,800)
$
-
Final - Used 5.4% Contingency
Change Order No. 1
$
27,247
Additional asbestos, footing/concrete removals in Demo
Change Order No. 2
$
948
Change Order No. 3
$
17,026
Delay Cost associated with Pad delivery
Change Order No. 4
$
47,726
Change Order No. 5
$
65,454
Change Order No. 6
$
14,474
Change Order No. 7
$
84,337
Change Order No. 8
$
15,652
Restaurant to Reimburse City
Change Order No. 9
$
81,563
Change Order No. 10
$
51,696
Change Order No. 11
$
52,492
Change Order No. 12
$
1,166
Restaurant to Reimburse City
Change Order No. 13
$
41,631
Change Order No. 14
$
28,922
Change Order No. 15
$
1,711
Restaurant to Reimburse City
Change Order No. 16
$
87,756
Change Order No. 17
$
15,598
Restaurant to Reimburse City
Change Order No. 18
$
110,452
Change Order No. 19
$
77,922
Change Order No. 20
$
5,688
Restaurant to Reimburse City
Change Order No. 21
$
59,477
Change Order No. 22
$
28,243
Change Order No. 23
$
4,687
Restaurant to Reimburse City
Change Order No. 24
$
87,225
Change Order No. 25
$
3,000
9-8
MARINA PARK
MASTER BUDGET
Last Updated 5-31-16
Overall Project Construction Contingency Summary
BUDGETED
BUDGETED
Contingency
ACTUAL
ACTUAL
Package
TASK DESCRIPTION
DETAIL COST
TOTAL
DETAIL COST
TOTAL
COMMENTS
d
PACKAGE 4: Docks
$ 2,217,741
Final Total Contract Amount = $2,926,852
$
Original Contract
$ 40,513
-$72,196.04
$
$ 2,937,661
27.82%
Package 2
$
Remainder of 10% Contingency (Begin with $293,766)
$ 457,608
$266,689.89
$
$ -
4.17%
None Used in Contract
$
Change Order No. 1
$ 1,874,800
$1,012,089.02
$
$ (11,918)
4.60%
credit for pile size reduction
$ 2,937,661
Change Order No. 2
-$20,809.00
$ 314,575.10
10.71%
$ 1,109
$
Modifications to light lens and swim ladders
$ 2,666,687
Reduction in Schedule of Values Item
$
1,480,913
5.55%
$ (10,000)
Reduced long term maintenance work
e
PREVAILING WAGE
$ 3,883,764
Incl
Now Included in Actual Direct Costs
f
CONTINGENCY - COURSE OF CONSTRUCTION
$ 1,938,500
g
MISCELLAIOUS CONSTRUCTION COST
0-
2017 (one time) Marina Dock Inspection/Tuneup
$ 10,000
5
FIXTURES, FURNISHINGS, & EQUIPMENT (FF&E)
$ 560,000
$ 467,740
a
Package 5: FF&E
$ 500,000
$ 414,543
430k for Fixtures + 70k for tax, install
b
Computers, Phones, Servers, Scanners, Copiers
$ 60,000
$ 53,197
CONB IT provided
6
ICITY RESERVE
$ 2,081,000
$
-$54,975.85
7
Credits and Reimbursements
$
Change Order Cost to be Reimbursed from Lighthouse Cafe
-$44,500.43
Proposed Sale of Property to OCSD
$0.00
SCE Savings by Design Incentive
-$10,475.42
PROJECT TOTAL
i $ 39,500,000
$ 35,433,016
Last Updated 5-31-16
Overall Project Construction Contingency Summary
Total Award Construction Contracts = $ 26,666,870.00
Total Construction Change Orders = $ 1,185,773.87
Total Final Construction Cost = $ 27,852,643.87
Final Overall % Change Orders = 4.45%
Contingency
Contingency
Package
Award
Allowance
Used to Date
Contingency Remaining
(10%)
Package 1
$
405,130
$ 40,513
-$72,196.04
$
112,709.04
27.82%
Package 2
$
4,576,079
$ 457,608
$266,689.89
$
190,918.01
4.17%
Package 3
$
18,748,000
$ 1,874,800
$1,012,089.02
$
862,710.98
4.60%
Package
$ 2,937,661
$ 293,766
-$20,809.00
$ 314,575.10
10.71%
Total Award
$
26,666,870
$ 2,666,687
$ 1,185,774
$
1,480,913
5.55%
Total Award Construction Contracts = $ 26,666,870.00
Total Construction Change Orders = $ 1,185,773.87
Total Final Construction Cost = $ 27,852,643.87
Final Overall % Change Orders = 4.45%