HomeMy WebLinkAbout05 - City Radio Tower Rehabilitation — Award of Contract No. 7094-1July 26, 2016 Agenda Item No. 5 TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL FROM: David A. Webb, Public Works Director - 949-644-3311, dawebb@newportbeachca.gov PREPARED BY: Ben Davis, Associate Civil Engineer, bdavis@newportbeachca.gov PHONE: 949-644-3317 TITLE: City Radio Tower Rehabilitation — Award of Contract No. 7094-1 ABSTRACT: Staff has now received construction bids for the City Radio Tower Rehabilitation project and requests City Council's approval to award the construction contract to Petroleum Telcom, Inc. dba Telcom, Inc. RECOMMENDATION: a) Staff recommends the City finds this project exempt from the California Environmental Quality Act (CEQA) pursuant to Section 15302(c) (reconstruction of existing facility involving negligible or no expansion of capacity) of the CEQA Guidelines, because it has no potential to have a significant effect on the environment; b) Approve the project drawings and specifications; c) Award Contract No. 7094-1 to Telcom, Inc. for the total bid price of $425,458.00, and authorize the Mayor and City Clerk to execute the contract; d) Establish a contingency of $42,500 (approximately 10 percent) to cover the cost of unforeseen work not included in the original contract; e) Authorize City Manager to execute a Reimbursement Agreement with the County of Orange for its contribution to the project on a form approved by the City Attorney; and f) Approve Budget Amendment No. 17BA-004 appropriating $184,000.00 from 800MhZ Equipment unappropriated balance to Account No. 75401-980000-16M13; $34,500 from Water Enterprise unappropriated balance to Account No. 70101- 980000-16M13; $11,500 from Wastewater Enterprise unappropriated balance to Account No. 71101-980000-16M13; and $25,000 from IT Equipment unappropriated balance to Account No. 76501-980000-16M13 for City Radio Tower Rehabilitation Project. 5-1 City Radio Tower Rehabilitation — Award of Contract No. 7094-1 July 26, 2016 Page 2 FUNDING REQUIREMENTS: Upon adoption of the budget amendment, sufficient funding for this project is in the budget to complete the work. The following funds will be expensed: Account Description IT Replacement (temp. cable) Water Enterprise (15%) Wastewater Enterprise (5%) 800 MhZ Equipment (80%) Proposed uses are as follows: Vanrinr Telcom, Inc. Telcom, Inc. Alltech Communications, LLC On-call geotechnical Various Time Warner Cable, Inc. Account Number Amount 76501-980000-16M13 $ 425,458.00 $ 25,000.00 70101-980000-16M13 Temporary Utility Tower $ $ 75,180.00 71101-980000-16M13 16,210.00 Printing & Incidentals $ 25,060.00 75401-980000-16M13 $ 25,000.00 $ 400,960.00 526,200.00 Total: $ 526,200.00 Purpose Amount Construction Contract $ 425,458.00 Construction Contingency $ 42,500.00 Temporary Utility Tower $ 15,000.00 Special Inspections $ 16,210.00 Printing & Incidentals $ 2,032.00 Temporary IT Connection $ 25,000.00 Total: $ 526,200.00 City Council authorized a preliminary budget of $400,000 for the City Radio Tower Rehabilitation project for the design and fabrication of tower parts at its September 8, 2015 meeting. Design as well as the manufacturing of new tower segments, galvanizing and painting has been completed. Funding sources included the City's 800 MhZ Equipment Fund, Water Enterprise Fund and Sewer Enterprise Fund with an 80-15-5 percent split ratio based on uses and connections to/from the tower. Savings from the design portion are being applied to the construction budget. Funding for the construction portion of the tower maintains the same 80-15-5 percent ratio. Additional expenses for temporary cabling will be paid from the IT Equipment Fund. DISCUSSION: The City owns and operates a 320 -foot radio communications tower located at the City Utilities Yard in West Newport. The tower is a critical communications link used by the City for routine and emergency communication as well as by surrounding public safety agencies, for emergency communications. The tower also provides a crucial communication link between many of the City's facilities. This tower is approximately 50 years old and has undergone recent inspections that revealed a need of rehabilitation. At 10 a.m. on July 7, 2016, the City Clerk opened and read the following bid for this project: BIDDER TOTAL BID AMOUNT Low Petroleum Telcom, Inc. $425,458.00 5-2 City Radio Tower Rehabilitation — Award of Contract No. 7094-1 July 26, 2016 Page 3 The City received only one bid on this project and the low bid amount is 22 percent above the engineer's estimate of $350,000.00. There are many factors for the increased cost and lack of bidders. Our research prior to the bid and after the receipt of the bid, confirmed that the radio tower industry is extremely busy and the work is highly specialized. There are only a few California contractors that are licensed and qualified to work towers above 300 -feet. Also, the City's requirement for minimal downtime on the Public Safety communications during the City's Radio Tower rehabilitation is very stringent. These factors appear to have added to the increased cost. Staff spoke with other potential bidders and they all indicated that due to a heavy industry work load, they could not complete the City project in a timely manner. There is urgency to this project as last year's inspection has raised concerns about the tower integrity and some needed antenna maintenance can't be performed with the tower in its current condition. Staff met with the low bidder to review costs and potential savings that could be realized by re -bidding the project, installing a temporary tower and extending the construction period. After those discussions, it was determined that little, if any, savings could be realized, and re -bidding the project may result in higher costs and delay of several other critical maintenance items related to the City's safety communications (Fire, PD and Lifeguards). Staff recommends moving forward with the award of this contract. Petroleum Telcom, Inc. possesses a California State Contractors License Classification "B" as required by project specifications. A check of contractor's references indicates satisfactory completion of similar projects for other local cities and municipalities. Pursuant to contract specifications, Contractor will have 50 working days to complete the work. Construction will begin in mid-August with dismantling of the existing tower starting in September. Coordination and detailed scheduling efforts are underway to minimize communication downtime for Public Safety, IT and Utilities. A small temporary tower for Utilities' communication will be erected and a temporary hard -wire cable TV connection for the City's IT connection between the two City maintenance yards will be implemented during construction. Required funding is included in the budget requested. The County of Orange and its Sheriffs Communication Division is a partnering agency with the City for the 800MhZ radio communication equipment located on the City's tower. Although radio tower rehabilitation work was originally envisioned to be funded solely by the City, staff pursued further discussions with the County and they have indicated support of the project and are willing to partially fund this work as they have done in the past. A County Reimbursement Agreement (Agreement) is in progress to recognize a contribution of approximately one-third of project expenses. The Agreement is currently being drafted by the County. Since time is of the essence for project delivery and coordination efforts, staff is requesting authorization for the City Manager to approve the Agreement upon a final form approved by the City Attorney. The Agreement with the County will reimburse the City's 800 MhZ Equipment Fund. 5-3 City Radio Tower Rehabilitation — Award of Contract No. 7094-1 July 26, 2016 Page 4 ENVIRONMENTAL REVIEW: Staff recommends the City Council find this project exempt from the California Environmental Quality Act (CEQA) pursuant to Section 15302(c) (reconstruction of existing facility involving negligible or no expansion of capacity) of the CEQA Guidelines, California Code of Regulations, Title 14, Chapter 3, because it has no potential to have a significant effect on the environment. NOTICING: The agenda item has been noticed according to the Brown Act (72 hours in advance of the meeting at which the City Council considers the item). ATTACHMENTS: Attachment A — Location Map Attachment B — Budget Amendment 5-4 17TH STREET 16TH STREET f I PROJECT LOCATION I I w z w 4 Q 0 ry z 0 ATTACHMENT A PRODUCTION PL 15TH STREET 0 w z w z w 17, C CITY RADIO TOWER REHABILITATION CIN OF NEWPORT BEACH LOCATION MAP PUBLIC WORKS DEPARTMENT C-7094-1 1 7/26/2016 5-5 ATTACHMENT B City of Newport Beach BUDGET AMENDMENT 2016-17 EFFECT ON BUDGETARY FUND BALANCE: Increase Revenue Estimates X Increase Expenditure Appropriations AND Transfer Budget Appropriations SOURCE: from existing budget appropriations from additional estimated revenues X from unappropriated fund balance EXPLANATION: NO. BA- 17BA-004 AIVIOUNT:J $255,000.00 Increase in Budgetary Fund Balance X Decrease in Budgetary Fund Balance No effect on Budgetary Fund Balance This budget amendment is requested to provide for the following: To increase expenditure appropriations for the rehabilitation of the City Radio Tower. 80% will be funded by the 800 MHZ equipment fund, 15% will be funded by the Water fund, and 5% will be funded by the Sewer fund. Savings from the design portion approved by Council in FY16 will be carried forward. Temporary cabling will be added from the IT Equipment Fund. ACCOUNTING ENTRY: BUDGETARY FUND BALANCE Amount Fund Account Description Debit Credit 765 300000 IT Equipment Fund - Fund Balance $25,000.00 754 300000 800 MHZ Radio Fund - Fund Balance $184,000.00 701 300000 Water Enterprise Fund - Fund Balance $34,500.00 711 300000 Sewer Enterprise Fund - Fund Balance $11,500.00 EXPENDITURE APPROPRIATIONS (3603) Signed: City Council Approval: City Clerk Date W Description Org Number 76501 IT Equipment CIP Account Number 980000 CIP Expenditures for GL Project Number 161VI13 City Radio Tower Rehabilitation $25,000.00 Project String E-1 6M1 3 -CONSTRUCT -765 -UNASSIGNED Org Number 75401 800 MHZ CIP Account Number 980000 CIP Expenditures for GL Project Number 161VI13 City Radio Tower Rehabilitation $184,000.00 Project String E-1 6M 13 -CONSTRUCT -754 -UNASSIGNED Org Number 70101 Water Enterprise Fund CIP Account Number 980000 CIP Expenditures for GL Project Number 16M13 City Radio Tower Rehabilitation $34,500.00 Project String E -16M13 -CONSTRUCT -701 -UNASSIGNED Org Number 71101 Sewer Enterprise Fund CIP Account Number 980000 CIP Expenditures for GL Project Number 161VI13 City Radio Tower Rehabilitation $11,500.00 Project String E-1 M13 -CONSTRUCT -711 -UNASSIGNED Automatic System Entry. Signed:" '7 p Fina i Approva . Finance Director Date Signed: (P1 �()L -7 r D 'L Adminibtr,dve Approval: City Manager Date Signed: City Council Approval: City Clerk Date W