C'9CIFORN`P C ty CouncH Staff Report .Agenda Item No. 8
May 22, 2012
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: Public Works Department
Stephen G. Badum, Public Works Director
949 - 644 -3311, sbadum @newportbeachca.gov
PREPARED BY: Tom Sandefur, P.E., Associate Civil Engineer
APPROVED: A ��
TITLE: 19th Street Tide Gate Retrofit — Award of Contract No. 4773
ABSTRACT:
Staff received favorable construction bids for the 19th Street Tide Gate Retrofit and is
requesting City Council's approval to award the work to Palp Inc., (dba Excel Paving
Company).
RECOMMENDATIONS:
1. Approve the project drawings and specifications;
3. Award Contract No. 4773 to Excel Paving Company for the total bid price of
$182,501.00 and authorize the Mayor and City Clerk to execute the contract; and
4. Establish a contingency of $27,375.00 (approximately 15 percent) to cover the
cost of unforeseen work.
FUNDING REQUIREMENTS:
The current adopted budget includes sufficient funding in the following accounts for the
award of this contract. The following funds will be expensed:
Proposed uses are as follows:
Account Description Account Number Amount
General Fund 7012- C2502006 $ 109,876.00
Tide and Submerged Lands 7231- C2502006 $ 100,000.00
Total: $ 209,876.00
19th Street Tide Gate Retrofit — Award of Contract No. 4773
May 22, 2012
Page 2
Vendor Purpose Amount
Excel Paving, Inc. Construction Contract $ 182,501.00
Excel Paving Inc. Construction Contingency 27,375.00
Total: $ 209,876.00
DISCUSSION:
The tide vault at 19th Street serves as the terminus for the storm drain line that drains
19th Street and Balboa Boulevard from 19th Street to 16th Street. The significant depth of
the outlet pipe draining into the Bay requires a tide gate. Without the gate, the low lying
areas of 19th Street and Balboa Boulevard would flood during high tide events. During
combination high tide and rain events, the system is quickly overwhelmed and Municipal
Operations field crews stage pumps at the end of 19 h Street to prevent street flooding.
The project proposes to remove the existing electric tide valve and install a new passive
tide valve. A similar valve operates at Pearl Avenue and has been successful in
reducing the need for human intervention during high tide events. In addition, the project
will install a submersible pump in the tide vault. The pump will operate according to the
level of water in the vault and drain the storm drain system on occasions where rain and
high tides make flooding possible. The pump will eliminate the need to pull portable
pumps to the site during rain and tide events. The pump control panel is being installed
in a fashion that allows for future integration into the City's Supervisory Control and
Data Acquisition ( SCADA) system. The SCADA system permits an operator to monitor
the pump from a central terminal or via handheld electronics.
At 9:00 A.M. on May 9, 2012, the City Clerk opened and read the following bids for this
project:
BIDDER
Low Palp Inc, dba Excel Paving, Inc.
2 Atlas Allied, Inc.
3 Fleming Environmental, Inc.
4 GCI Construction, Inc.
5 4 -Con Engineering, Inc.
6 AToM Engineering Construction, Inc.
TOTAL BID AMOUNT
$182,501.00
$194,550.00
$202,560.00
$214,858.00
$223,950.00
$291,398.00
The low total bid amount is 1.5 percent below the Engineer's Estimate of $185,350. The
low bidder, Excel Paving, Inc., possesses a California State Contractors License
Classification "A" as required by the project specifications. A check of the contractor's
references indicates satisfactory completion of similar projects for other public agencies.
The work necessary to complete this contract consists of removing the existing tide
gate, vault lid, motor, and controls; furnishing and installing Tideflex check valves,
submersible trash pump, piping, and sidewalk; connecting to existing electrical facilities,
19th Street Tide Gate Retrofit — Award of Contract No. 4773
May 22, 2012
Page 3
adding irrigation lines and control equipment, replacing existing walls relocating existing
handrails, relocating existing street light, and installing planting material. Pursuant to
the Contract Specifications, the Contractor will have 100 consecutive working days to
complete the shop drawings and procure the materials and 25 consecutive working
days to install the work.
ENVIRONMENTAL REVIEW:
Staff recommends the City Council find this project exempt from the California
Environmental Quality Act ( "CEQA ") pursuant to Section 15301(d) (Restoration of
deteriorated facilities to meet current safety standards) of the CEQA Guidelines,
California Code of Regulations, Title 14, Chapter 3, because it has no potential to have
a significant effect on the environment.
The agenda item has been noticed according to the Brown Act (72 hours in advance of
the meeting at which the City Council considers the item).
Submitted by:
aaum
Director
A. Location Map
0
I ll
N
LOCATION MAP
19TI -I STREET TIDEGATE RETROFIT
CONTRACT NO. 4773
PROJECT LOCATION