HomeMy WebLinkAbout01 - NBR Master Development Plan Revisions and ErrataExhibit D
NBR Master Development Plan Revisions and Errata
Page 3 -3
Revise Section 3.2.2 as follows:
3.2.2. Parklands
Public Community Park comprising approximately 264 21.8 gross /24.7 18.0 net
acres in SPAS 7a-, 7b, and 7c, which shall be developed for public active and passive
recreation as part of the Project and offered for dedication to the City and Public
Community Park comprising approximately 5.0 gross /3.7 net acres in SPA 7a, which
shall be developed for public park purposes, privately maintained, and made
permanently available for public use through deed restriction and /or recorded
easement.
Page 3 -29
Change Section 3.5.2 as follows:
3.5.2 Public Community Park Development Plans
As part of the Project, a 24.4 21.8 gross -/24-4- 18.0 net -acre Community Park North
Community Park and Central Community Park) will be developed and offered for dedication
to the City of Newport Beach. The development plan for the Community Park (SPAs
7b, and 7c) is a Project Development Plan providing a sufficient level of design detail for
Coastal Commission approval of a Coastal Permit for this park. The Public Community
Park site to be offered for dedication to the City is comprised of the three two subareas as
described below:
• The North Community Park Project Development Plan, illustrated in Exhibit 3 -6a,
contains 15.9 gross /13.5 net acres and will be improved as an active park to include
lighted turf sports fields, lighted hard courts, picnic facilities, age - specific playground,
restrooms, off - street public parking, and may include synthetic turf.
. The Central Community Park Project Development Plan, illustrated in
Exhibit 3 -6b, contains 5.9 gross /4.5 net acres and will be improved as a passive
recreational area, including picnic areas, informal open play turf areas, and off -
street public parking. The Development Plan for the Central Community Park
Road to provide
pedestrian access through the
park from the boundary of the
Newport Crest residential community. The trail
connection will be constructed
subject to
the approval
by the Newport Crest
Homeowners Associate of the
provision
of a
gate at the boundary of Newport
Crest at the terminus of
Ticonderoga
to provide
secure pedestrian movement to and from Newport Crest.
Exhibit 3 -6b, Central Community Park Development Plan — Replace with new park
plan exhibit included as Attachment 1.
As part of the Project, a 5.0 gross/ 3.7 net acre Community Park (South Community
Park) will be developed, privately maintained, and made permanently available for
public use -. The development plan for the Community Park (SPA 7a) is a Project
Development Plan providing a sufficient level of design detail for Coastal
Commission approval of a Coastal Permit for this park. The South Community Park
is described below.
The South Community Park Project Development Plan, illustrated in
Exhibit 3 -6c, contains 5.0 gross /3.7 net acres and _will be improved as a
passive natural recreation area to complement the City's Sunset Ridge Park
site to the east and will include park access, native habitat, and interpretive
opportunities.
Section 3.5
Page 10 -3
Revise Section 10.6.2 as follows:
10.6.2 Activities Requiring Subsequent Site Development Review Approval
Following approval by the City of the NBR -MDP the following development activities are
permitted within the Project Site subject to recordation of Final Map No. 17308 and any
subsequent subdivision map(s), approval by the City of Site Development Review pursuant
to NBR -PC Section 4.5, "Site Development Review," any additional local required permits,
and any permits from State (including Coastal Commission), and Federal agencies with
permitting jurisdiction over the activity:
1. Construction of residential, commercial, and visitor serving resort uses in all Villages and
Colonies;
2. Construction of Bluff Parks and Interpretive Parks; and
3. Construction of South Community Park
Page 10 -3
Add new Section 10.6.3 as follows:
10.6.3 Activities Requiring Community Park Improvement Plan
Following approval by the City of the NBR -MDP the following development activities are
permitted within the Project Site subiect to recordation of Final Map No. 17308 and any
subseauent subdivision map(s), approval by the City of a Community Park Improvement
Plan, pursuant to NBR -PC Section 4.4.6.1 " Activities Subject to Community Park
Improvement Plan Approval." any additional local required permits, and any permits from
State (including Coastal Commission), and Federal agencies with permitting jurisdiction
over the activity:
1. Construction of the public Community Park (North and Central Community Park).
Page 10 -5
Revise Section 10.7.3 as follows:
10.7.3 Authorization for City to Issue Construction -Level Permits as part of MCDP
The MCDP shall authorize the City to be the final review authority for any subsequent
planning development permits and construction level permits, as required by the NBR -PC,
for implementation of those activities described in Section 10.6 of the NBR -MDP and within
the areas illustrated on Exhibit 10 -1, without additional Coastal Development Permits,
provided the subsequent permits are consistent with the NBR -MDP Project Development
Plans. Subsequent required planning development permits and construction level permits
shall include, but are not limited to, Site Development Review, Community Park
Improvement Plan Approval, Use Permits, Final Tract Maps, final grading permits, model
home permits, building permits, and other required permits.
Page 10 -10
Add new Section 10.12, "Community Park Improvement Plan," as follows:
10.12 Communitv Park Improvement Plan
Approval by the Director of Recreation and Senior Services of a Community Park
Improvement Plan, in accordance with the provisions of NBR -PC Section 4.6, "Community
Park Improvement Plan," shall be required prior to construction of the public Community
Park.
Page 10 -10
Renumber Section 10.12 and revise text as follows:
4012 Miner Modification-,;
10.13 Substantial Conformance
The following are sensideFed constitute substantial conformance
with the NBR -MDP including Exhibit 1 -4, "Site Planning Areas Map," Exhibit 3 -1, "Master
Development Plan," and Exhibit 3 -2, "Master Development Table."
Land Use Acreage Refinements
A change in the Site Planning boundary lines as illustrated on Exhibit 1 -4 "Site Planning
Areas Map," and corresponding change in the Gross Acres for the respective Site Planning
Area as described on Exhibit 1 -5, "Site Planning Areas Table," of up to fifteen percent
(15 %) are as approved permitted as part the approval of either a Site Development Review,
or subdivision map application submitted for the Site Planning Area, provided the
refinement(s) to Gross Acres does not result in:
than 29 n
1. A reduction in the total acreage allocated to Open Space;
2. A reduction in the total area allocated to the Parklands;
3. The total area within the Project Site boundaries exceeding 401.1 gross acres;
4. Less than two roadway access points from North Bluff Road into the North
Family Village; and /or
5. Less than two roadway access points into both the South and North Family
Village.
Page 10 -10
Renumber and Revise Section 10.12.2 as follows:
10_14 Transfer of Residential Dwelling Units
A change in the number of residential dwelling units for any Site Planning Area as
described on Exhibit 1 -5, "Site Planning Areas Table," resulting from a transfer of
residential dwelling units from one Site Planning Area to another, and as approved
pursuant to the provisions of NBR -PC Section 4.18. " Transfer of Residential Dwellina
Units." is permitted as part of the approval of a Site Development Review provided
Page 10 -11
Renumber and Revise Section 10.12.14 as follows:
10 X17 14 AddoUnn..1 Manny h4nd:foratonnc:
10.15 Modifications to ADDroved Proiect Development Plans
The following constitute additieaal 0110WAb� ° rRinnr modifications to the NBR -MDP Proiect
Development Plans which may be approved as part of Site Development Review or
subdivision review, and not requiring an amendment to the NBR MDP:
1. Change in utility or public service provider as described in NBR -MDP Chapter 8,
"Master Roadway and Infrastructure Plans ;"
2. Change in roadway alignment of any roadway illustrated on the "Master Roadway
Plan" of the NBR -MDP when the change results in a centerline shift of 150 feet or less;
3. Change to roadway sections as described in NBR -MDP Chapter 8, "Master
Roadway and Infrastructure Plans as approved by the Director of Public Works;
4. Refinements to the Architectural Design Guidelines pursuant to Section 10.10;
5. Refinements to the mix, distribution, and design of architectural products With asv°
pt of ubsequeRt Site n.,.,..i.,.... ent Rpyip' -V ARd „StF tiGR .tFaWiRg provided that:
a. The character and style of the architecture remains consistent with the intent of the
Project's architectural style;
b. The nominal lot size dimensions and nominal building square footages do not
exceed 20% of the original architecture proposed within the Site Planning Area; and
c. All applicable development regulations and standards set forth in the NBR -PC are
complied with.
Page 10 -12
Delete the following text:
Page 10 -13
Renumber and revise Section 10.13 as follows:
4912 10.16 Amendments to the NBR -MDP
All proposed changes to the NBR -MDP other than those identified in Section ' 0i o 12, Whip{
Medifisatieas" 10.14 Transfer of Residential Dwelling Units and Section 10_15
"Modifications to Approved Project Development Plans," shall be considered amendments
to the NBR -MDP and shall be reviewed in accordance with the provisions of NBR -PC
Section 4.4 "Master Development Plan." When any CDP(s) or MCDP is approved by the
Coastal Commission that varies from the approval granted by the City for the NBR -MDP or
any approved amendment, the applicant shall submit a request for determination of
substantial conformance to the Director or Community Development. The Director of
Community Development has the authority to refer any request for substantial conformance
to the City Council for consideration and final action on the request.
Page 10 -13
Renumber and revise Section 10.14 as follows:
49 44 10_17 Amendments to the Master CDP
Amendments to the MCDP are considered to be those changes considered as
amendments to the NBR -MDP pursuant to NBR -MDP Section 494310.16. Following City
approval of any amendment to the NBR -MDP a corresponding application for an
amendment to the MCDP shall be submitted for approval to the California Coastal
Commission.
Exhibit 10 -1, Master Entitlements and Subsequent Approvals Map
Add the following text to the notations:
Land Use Development per City- approved Master Development Plan and CCC- approved
Master Coastal Development Permit. Additional Site Development Review, and /or
Community Park Improvement Plan Approval. by City is required, but additional Coastal
Development Permit is not required, prior to Land use Development and construction
permits.