HomeMy WebLinkAbout04 - Peninsula Point Alley ReplacementAgenda Item No. 4
March 13, 2012
TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: Public Works Department
Stephen G. Badum, Public Works Director
949 - 644 -3311, sbadum @newportbeachca.gov
PREPARED BY: Frank Tran, PE
APPROVED: C~ V-2kA
TITLE: Peninsula Point Alley Replacement — Award of Contract No. 4627
ABSTRACT:
With the final utility pole removal and completion of the utility undergrounding in the
Peninsula Point neighborhood, staff now requests City Council approval to award the
Peninsula Point Alley Replacement project to Hillcrest Contracting, Inc. as the final
improvement phase of Assessment District 103.
RECOMMENDATIONS:
1. Approve the project drawings and specifications.
2. Award Contract No. 4627 to Hillcrest Contracting for the total bid price of
$1,617,335.00, and authorize the Mayor and the City Clerk to execute the contract.
3. Establish an amount of $242,665.00 (15 %) to cover the cost of unforeseen work
and anticipated additional curb and gutter not included in the original contract.
FUNDING REQUIREMENTS:
The current adopted budget includes sufficient funding for this contract. Sufficient funds
will be available in the following accounts for the project:
Account Description
AD -103 Street Rehabilitation
AD -103 Construction Contingency
Water Enterprise Fund
Wastewater Enterprise Fund
General Fund
Account Number
74103 -9804
74103 -9805
7511- C2002040
7541- C2002040
7013- C2002040
Amount
$977,545.00
42,608.00
474,792.00
55,364.00
336.691.00
Total $1,887,000.00
Peninsula Point Alley Replacement — Award of Contract No. 4627
March 13, 2012
Page 2
Proposed uses are as follows:
Vendor
Hillcrest Contracting, Inc
Hillcrest Contracting, Inc
Harrington Geotechnical
Various
DISCUSSION:
Purpose Amount
Construction Contract $ 1,617,335.00
Construction Contingency 242,600.00
Geotechnical Services 24,927.00
Printing and Incidentals 2,138.00
Total: $ 1,887,000.00
At 10:00 A.M. on February 22, 2012, the City Clerk opened and read the following bids for
this project:
The total low bid amount is 43% lower than the Engineer's Estimate of $2,850,000. The
disparity between the estimate and the actual bid prices reflect a more favorable
construction market. The low bidder, Hillcrest Contracting, Inc., (Hillcrest) possesses a
California State Contractors License Classification "A" as required by the project
specifications. A check of Hillcrest's references indicates satisfactory completion of similar
projects for other public agencies.
Given the favorable project unit prices by Hillcrest, staff recommends establishing a fifteen
percent (15 %) contract contingency to be included in the contract award, totaling
$242,665.00. These added funds will provide an opportunity for the City to take advantage
of the low unit prices to perform additional concrete curb, gutter, sidewalk and pavement
rehabilitation work within the project limits.
The work necessary for the completion of this contract consists of removing the existing
asphalt and concrete alleys and streets, constructing new concrete alleys and street
pavement, installing and upgrading corner access ramps, adjusting utilities covers to grade
and performing other appurtenant and incidental items of work as required. The alley
replacement included in this contract is the final work effort for the Assessment District 103
BIDDER
TOTAL BID AMOUNT
Low
Hillcrest Contracting, Inc.
$1,617,335.00
2
GSCI (Golden State)
$1,709,050.00"`
3
Kalban, Inc.
$1,889,355.00
4
Grigolla & Sons Const.
$1,937,350.00
5
All American Asphalt
$2,050,000.00
6
La Strada Contracting
$2,177,777.00
7
EBS General Engineering Inc
$1,293,293.00
8
Martinez Concrete, Inc.
$2,541,992.00
W Bid read
as $1,708,607.00
The total low bid amount is 43% lower than the Engineer's Estimate of $2,850,000. The
disparity between the estimate and the actual bid prices reflect a more favorable
construction market. The low bidder, Hillcrest Contracting, Inc., (Hillcrest) possesses a
California State Contractors License Classification "A" as required by the project
specifications. A check of Hillcrest's references indicates satisfactory completion of similar
projects for other public agencies.
Given the favorable project unit prices by Hillcrest, staff recommends establishing a fifteen
percent (15 %) contract contingency to be included in the contract award, totaling
$242,665.00. These added funds will provide an opportunity for the City to take advantage
of the low unit prices to perform additional concrete curb, gutter, sidewalk and pavement
rehabilitation work within the project limits.
The work necessary for the completion of this contract consists of removing the existing
asphalt and concrete alleys and streets, constructing new concrete alleys and street
pavement, installing and upgrading corner access ramps, adjusting utilities covers to grade
and performing other appurtenant and incidental items of work as required. The alley
replacement included in this contract is the final work effort for the Assessment District 103
Peninsula Point Alley Replacement —Award of Contract No. 4627
March 13, 2012
Page 3
Underground Utility District. In addition, an 8 -inch drainage system will be constructed to
remedy historic flooding at the sump in the middle of Alley No. 205 (between "M" Street and
Channel Road, Seville Avenue and Miramar Drive).
Pursuant to the Contract Specifications, the Contractor will have 100 consecutive working
days to complete the work.
ENVIRONMENTAL REVIEW:
Staff recommends the City Council find this project exempt from the California
Environmental Quality Act ( "CEQA ") pursuant to Section 15301(c) (maintenance
activities with negligible expansion) of the CEQA Guidelines, California Code of
Regulations, Title 14, Chapter 3, because it has no potential to have a significant effect
on the environment
NOTICING:
The agenda item has been noticed according to the Brown Act (72 hours in advance of
the meeting at which the City Council considers the item).
The Notice Inviting Bids was advertised in the City's official publication and in construction
industry publications. Affected residents will be notified prior to the start of the project.
Submitted by: �]
Stepherf . Badum
Publig Arks Director
Attachment: A. Project Location Map
I
LOCATION MAP
PENINSULA POINT ALLEYS REPLACEMENT
PROJECT LIMITS > ®,a
j CHANNEL RD.
�"
�\ Cg\P
112 9
I
M e \
Sevi � Sr \ � Ado
AVI r /2io
�2
LST
4 J S?
/Sr.
HST. �B m
ASE' NTS
\ e Sr
F:\ Users \PBW \Shared \Contracts \FY10 -11 \Peninsula Point Alley Replacement C- 4627\DESIGN PHASE \Location — Map.dwg